HomeMy WebLinkAboutContracts & Agreements_22-2002_CCv0001.pdf AGREEMENT TO FURNISH ENGINEERING SERVICES
RECYCLED WATER PROJECT
TASK ORDER NO. 4
(Amendment No. 4)
This Task Order No. 4 (Amendment No. 4) authorizes the performance of Engineering Services
included in this Amendment and in Accordance with the AGREEMENT to perform professional
engineering services for recycled water project entered into the 16th day of January 2001 by
and between the City of Redlands, a municipal corporation (hereinafter"CITY"), and Carollo
Engineers, a Professional Corporation (hereinafter"ENGINEER").
This Amendment makes the following changes to the AGREEMENT, effective
December 18, 2001; all other provisions of the AGREEMENT remain in effect.
ARTICLE 1 — ENGAGEMENT OF ENGINEER
No changes.
ARTICLE 2— SERVICES OF THE ENGINEER
2.1 The Scope of Services is amended to include Attachment"A" of this Amendment, which
defines the scope of work for engineering services for Task Order No. 4.
ARTICLE 3— RESPONSIBILITIES OF CITY
No changes.
ARTICLE 4— PERIOD OF SERVICE
4.1 The time period for performance of the ENGINEER's services for Task Order No. 4 set
forth in Article 2 shall be in accordance with the schedule defined in Attachment"B"to
this Amendment.
ARTICLE 5— PAYMENTS TO THE ENGINEER
5.1 The total compensation to perform work under this Amendment for Task Order No. 4
shall be in accordance with Attachments"C" and "D" to this Amendment.
ARTICLE 6— INSURANCE AND INDEMNIFICATION
No changes.
ARTICLE 7—GENERAL CONSIDERATION
No changes.
February 8, 2002
\\Sbo\data\DatalClient\Rediands—SBO\CONTRACT\To#4\TO#4.doc
IN WITNESS WHEREOF, duly authorized representative of the i have
signed in confirmation of this Agreement.
City of Redlands Carollo Engineers, a Professional Corporation
("CITY') ("ENGINEER")
By. By:
KARL. N. (KASEY) HAWS S E G. G
Mayor Principal
Date: February 19, 2002 By:
GEOG �r EL.IEW
Pr' ci
v wY..
ATTEST:
f
t
erk, City of I nds
February 8, 2002
SBO\DATAIDATAlCiierrtlRediands.SBO\CONTRACT,To#41TO#4.doc 2
TASK ORDER NO. 4
ATTACHMENT A
City of Redlands
Engineering Services for Recycled Water Project
SRF/Value Engineering Assistance
SCOPE OF SERVICES
INTRODUCTION
The purpose of this Task Order is to provide the CITY with supplemental engineering services
needed to assist the CITY's value engineering consultant with completing the value engineering
study required by the State in order to obtain funding under the State Revolving Fund (SRF)
loan program. As described in the tasks below, the engineering services will include providing
information on the project's design to the value engineering consultant; reviewing and
responding to the value engineer's recommendations; submitting the responses to the State,
and revising existing contract documents and developing new plans and specifications to
accommodate accepted value engineering recommendations.
SCOPE OF SERVICES
Performance of engineering services necessary to assist the CITY's value engineering
consultant and revising the design to incorporate the accepted recommendations for the 2003
Water Recycling Project. Engineering services shall include assistance with value engineering
as defined in the tasks below. Assistance with SRF financing will be provided by others.
Task 1 — Support for Value Engineering Consultant
Provide information, background, history, and explanation of the project and its design to the
City's value engineering consultant. This task will include providing Treatment Alternatives
Feasibility Study, 90%plans, specifications, cost estimates, and other documents and
information to the value engineering team; meeting with the team to provide an overview of the
project and its design; and attending a post value engineering presentation by the value
engineering team to receive the team's recommendations.
Task 2 —Review of and Response to the Value Engineering Consultant
Recommendations
Review the value engineering team's recommendations, prepare a preliminary response,
discuss this response with the CITY, and prepare a joint response for submittal to the State's
funding agency. Develop report to submit to State and discuss the response with the State and
address its concerns in a Final Report.
February 8, 2002
\\Sbo\data\Data\Ciient\Rediands—SBO\CONTRAC1*\To#4\TO#4.doe A - 1
Task 3— Incorporate Accepted Value Engineering Recommendations
Revise the existing plans and specifications to incorporate the accepted value engineering
recommendations as summarized below:
3.1 Delete the UV disinfection system's civil, mechanical, structural, electrical, and
instrumentation (P&lDs) from the plans and specifications.
3.2 Develop design criteria for the revised disinfection system. Meet with City's staff and
present design criteria prior to revising the design.
3.3 Add a sodium hypochlorite disinfection system with chlorine contact basin, bypass
system, and effluent pumping system, complete with electrical and controls system.
Anticipated drawing list is presented in Exhibit A. Summary of Value Engineering
Recommendations is presented in Exhibit B.
3.4 Revise plans and specifications to incorporate other accepted value engineering
recommendations as identified in the Value Engineering Report and Designer's
Responses.
3.5 Add buried piping between the cogeneration facility and the existing digester control
buildings as needed for future transfer of digester gas to the cogeneration facility and
future transfer of heat from the cogeneration facility to the digesters. Pumps, hydronic
equipment, heat exchangers, temperature controls, gas compressors, and similar
equipment are not included in this Task 3.
3.5 Revise the project Engineer's Cost Estimate to reflect modifications noted above.
Task 4—Suggestions to Designer
Review plans and specifications to include accepted recommendations to Suggestions to
Designer.
February 8, 2002
\\Sbo\data\Data\ClientRediands—SBO\CONTRAC-RTo#4\TO#4.doc A - 2
TASK ORDER NO. 4
ATTACHMENT A- EXHIBIT A
City of Redlands
Engineering Services for 2003 Recycled Water Project
SRFNalue Engineering Assistance
CHLORINE CONTACT TANK DESIGN ADDITION
Sheet
Count Chlorine Contact Tank New Drawings
I 13SM01 Chlorine Contact Tank Foundation Plan
2 13SM02 Chlorine Contact Tank Roof Plan
3 13SM03 Chlorine Contact Tank Sections
4 13SM04 Chlorine Contact Tank Sections
5 13SM05 Chlorine Contact Tank Sections and Details
Above SM Drawings are primarily STR with MECH design info included such as gates,12ioing,etc.
6 13M01 Mechanical Pump Station Plan
7 13MO2 Mechanical Pump Station Sections
8 13MO3 Mechanical Pump Station Sections and Details
9 13EO1 Chlorine Contact Tank Electrical Plan
10 OOE04A Electrical Site Plan 4
11 131\101 Chlorine Contact Tank P&D
Modifications To The Existing Drawings
1 00GO3 Process Flow Diagram
2 00GO4 Hydraulic Profile
3 00GO6 Design Criteria
4 01Y01 General Site Plan
5 01YO2 Overall Site Plan
6 01Y06 Yard Area D Paving and Grading
7 01Y07 Yard Area E Paving and Grading
8 01YO9 Yard Area B Piping Plan
9 01Y11 Yard Area D Piping Plan
10 01Y12 Yard Area E Piping Plan
11 01Y13 Yard Piping Profile
12 01Y14 Yard Piping Profile
13 14MOI Chemical Facility Plan
14 14MO2 Chemical Facility Sections
15 14MO3 Chemical Facility Sections and Details
16 15M01 Membrane Facility EquipmentrTank Location Plan
17 15M02 Membrane Facility Equipment/Tank Plan A
18 15MO6 Membrane Facility Equipment/Tank Sections
19 15MO9 Membrane Facility Equipment/Tank Sections
20 OOE02 Electrical Site Plan 1
21 OOE03 Electrical Site Plan 2
22 OOE04 Electrical Site Plan 3
23 OOE05 Overall One Line Diagram
24 OOE06 Single Line Diagrams—SWBD"M"&SWBD"MA:'
25 OOE15 Single Line Diagrams—MCC"ZB"&MCC"U"
26 OOE17 Equipment Elevations
27 OOE24 Schematics
28 14EO1 Electrical Plan—Chemical Facility
29 0ONO2 Control System Block Diagram
30 141\101 Sodium Hypochlorite Chemical Metering
Item No. Design Support Tasks
1 Preliminary Design/CCT Definition
2 Specifications(new sections&modify existing sections)
3 Project Management
4 Revise Cost Estimate
February 8, 2002
\\Sbo\data\Data\Client\Rediancts_SBO\CONTRACT\To#4\TO#4,doc A - 3
TASK ORDER NO. 4
ATTACHMENT A- EXHIBIT B
City of Redlands
Engineering Services for 2003 Recycled Water Project
SRF/Value Engineering Assistance
DESIGNER'S RESPONSE TO
SUMMARY OF VALUE ENGINEERING TEAM'S RECOMMENDATIONS
Membrane System
M1 Reduce scope of Zenon supplied equipment.
M2 Add recycle line from membrane recycle task to aerobic zone of aeration tank to reduce DO
recycle to anoxic zone.
M5 Replace 316 stainless steel piping with 304 stainless steel piping.
M9 Bid alternative membrane system.
M11 Reduce the size of the overflow box on recycled channel.
M13 Tie membrane equipment roof into basin bridge crane columns.
M21 Replace 60-inch membrane influent pipe with pressurized channel.
Electrical and Controls
E3 Eliminate the ground grid in Electrical and Control Building, use Ufer ground.
E5 Put in SCADA terminal.
E6 Centralize panels in buildings, eliminate individual panel air conditioners.
E8 Do not use energy efficient motors.
Disinfection
D1 Use hypochlorite versus UV for disinfection.
D4 Simplify piping for UV system.
D5 Bid alternative UV system.
D7 Eliminate influent static mixer in UV system.
D8 Reduce size of UV effluent static mixer.
D9 Relocate influent mixer to effluent after initial testing.
D11 Relocate distribution system bypass valve.
Nitrification
N3 Leave air piping out of aeration basin.
N4 Do not install diffusers, piping, baffle walls in aeration basin 5 until flow increases.
N8 Reduce depth of aeration basin influent flow splitter box.
N9 Create larger openings in the aeration basin baffle walls.
N10 Abandon the 30-inch aerator effluent pipe in place.
Headworks
1-11 Eliminate the bypass line around the screens.
Chemical Building
CB1 Reduce metal canopy; cover pumps only.
Pumping
Pi Reduce the number of VFDs at pump stations.
P2 Reuse existing motors in the Raw Sewage Pump Station.
P9 Eliminate one of the RAS pumps.
February 8, 2002
\\Sbo\data\Data\Client\Rediarvds_SBO\CONTRAC"RTo#4\TO#4.doe A - 4
TASK ORDER NO. 4
ATTACHMENT B
City of Redlands
Engineering Services for 2003 Recycled Water Project
SRFNalue Engineering Assistance
PROJECT SCHEDULE
ENGINEER shall commence work immediately following approval of the Scope of Work and
authorization from the CITY. ENGINEER has reviewed the project with CITY and agrees that
the following schedule presents a reasonable time frame in which to complete the work.
Item Time
1. Receive Value Engineering Comments February 20, 2002
2. Submit Contract Documents to State February 28, 2002
3. Revise Drawings March 29, 2002
ENGINEER and CITY mutually agree that they will work earnestly toward meeting the above
tentative schedule. Should the Scope of Services change or should problems arise during the
work period which could affect the above schedule, it is understood that both ENGINEER and
CITY will develop a revised schedule to address such scope changes and problems. The
costing herein assumes that all work will be completed by March 29, 2002. Should the project
be delayed for any reason beyond ENGINEER's control past this date, ENGINEER reserves the
right to renegotiate the Task Order to cover actual increases in cost.
February 8, 2002
k1Sbo\data\[)atalCtient\Rediards—SBO\CONTRAC1'1To#41TO#4.doc B - 1
TASK ORDER NO. 4
ATTACHMENT C
City of Redlands
Engineering Services for 2003 Recycled Water Project
SRFNalue Engineering Assistance
FEE PROPOSAL
Fee proposals for each Task are presented on the attached pages. It is agreed that the
ENGINEER has apportioned the total proposed fee among the Tasks of this Task Order for
project management purposes only and that any unused fee from any task may be applied to
other Tasks at ENGINEER's discretion.
February 8, 2002
\\Sbo\data\Data\Clienffledlands_SBO\CONTRAGT1To#4\TO#4.doc " 1
TASK ORDER NO. 4
ATTACHMENT C
City of Redlands
Engineering Services for 2003 Recycled Water Project
SRFNalue Engineering Assistance
ESTIMATED MANHOUR BUDGET
Task Description Manhours
1 Support for Value Engineering Consultant 80
2 Review of/Response to VE Consultant's 260
Recommendations
3 Incorporate Accepted VE Recommendations:
a. Revisions Except Disinfection 220
b. Disinfection Revisions(l) 1,506 ......
Subtotal, Task 3: 1,726
4 Review/Respond/Incorporate Recommendations to 160
Designers
TOTAL: 2,226
Deduct
VE Recommendation Reduced Task Order No. 3
a. Task 3— UV Disinfection System < 60>
b.Task 6— Coordinate with DHS < 60>
Total Deduction: < 120>
(1) Includes General, Mechanical, Structural, Civil, Electrical, and Instrumentation
drawings for the revised disinfection system, plus revisions to other existing drawings
impacted by VE decisions.
February 8, 2002 C 2
\\Sbo\data\Data\CiiantNRediarids_SBO\CONTRACT\To#4\TO#4.doc
TASK ORDER NO. 4
ATTACHMENT C
City of Redlands
Engineering Services for 2003 Recycled Water Project
SRFNalue Engineering Assistance
COST ESTIMATE
Description Amount
LABOR COSTS $ 267,120
Engineering Labor:
2,226 hours @ $120/hour= Subtotal: $267,120
INDIRECT COSTS
Computer Equipment including Word
Processing and AutoCAD (PECE) $ 11,508
Subtotal: $ 11.508
Submittals:
Reports = 200
Plans & Specifications for CCT = 800
Subtotal: $ 1,000
Subtotal: $279,628
Deduction From Task Order No. 3
120 hours @ $120/hour= < $ 14,400>
TOTAL: $265,228
February 8, 2002 C 3
\\Sbo\data\Data\Client\Redlands-SBO\CONTRACT\To#4\TO#4,doc
TASK ORDER NO. 4
EXHIBIT D
City of Redlands
Engineering Services for 2003 Recycled Water Project
SRF/Value Engineering Assistance
FEE SCHEDULE
As of March 1, 2001
Southern California
Hourly Rate
Engineers/Scientists(EIS} $88-00
E/S 1
EIS 11 96.00105-00
E/S 111 113-00
EIS IV 120.00
EIS V 12&00
E/S VI 142.00
EIS VII 167.00
EIS Vill
Principal 181.00
Engineering Aides(EA) -0
EA 1 45.0
EA 11 54.0063.00
EA 111 72.00
EA IV
EA V 81-00 EA VI 89.0096.00
EA Vil
Engineering Technicians(ET)
ET 1 53.00
ET 11 60-0064.00
ET 111 69-00
ET IV
ET V 77.00 ET VI 88.00107.00
ET VII 119.00
ET Vill
Support Staff
Office Aides 36-00
Clerical 54.00
Word Processors 57.00
PECE Charge(Per DL Hour) 5.17
Travel and Subsistence At cost
Mileage .35/mile
Subconsultant Cost+ 100/0
Other Direct Costs Cost+ 10%
This fee schedule is subject to annual revisions due to labor adjustments.
February 8, 2002 D1