HomeMy WebLinkAboutContracts & Agreements_13-1987_CCv0001.pdf AGREEMENT TO FURNISH ENGINEERING SERVICES
FOR
REDLANDS WASTEWATER TREATMENT PLANT EXPANSION
TASK ORDER NO. 3
(PRELIMINARY AND FINAL DESIGN SERVICES
IMMEDIATE CAPACITY PROJECT)
This AGREEMENT is made and entered into as of this 21st day
of April 1987,
by and between City of Redlands, hereinafter
referred to as "OWNER"
and John Carollo Engineers, hereinafter
referred to as "ENGINEER"
In consideration of the mutual promises, covenants and conditions hereinafter
set forth, the parties do hereby agree as follows:
SECTION 1 (Purpose)
The purpose of this Task Order is to authorize and direct the ENGINEER to
proceed with certain "PRELIMINARY AND FINAL DESIGN SERVICES" as described in
SECTION 2(B) of the January, 1987 AGREEMENT, and as more specifically de-
scribed below.
SECTION 2 (Scope of Work)
The following items will be included in this preliminary engineering effort;
accordi ngly:
1. Design and prepare plans and specifications for the following faci-
lities and equipment necessary to increase the plant's capacity to
6.8 MGD.
A. New unlined sludge beds (approximately 1-acre in size).
B. Pump station to pump sludge from the digesters to the new
sludge beds.
C. Pump station to pump sludge from the decant (degasification)
basins to the new sludge beds.
D. Yard piping to serve the above.
E. Provide for temporary access road from the existing plant to
the new sludge beds.
F New pump, piping, power and controls in the existing headworks
pump station.
G. New pump, piping, power and controls in the final effluent pump
station (if evaluation shows additional pumping to be needed to
reliably meet the needs of a 6.8 MGD plant).
H. Provide for installation of new Owner-furnished screen in the
headworks.
I. Provide for piping, controls and appurtenances to activate the
second grit chamber, and the installation of City furnished
equipment and materials.
J. New chemical feed (ferrous chloride) and storage system.
2. Prepare plans and specifications for the portions of the Rapid Bloc
renovations to be constructed by construction contractor.
3. Meet with Owner approximately monthly to present progress prints and
discuss the project.
4. Submit five copies of plans, specifications and bidding documents to
Owner for review at the 50 and 85 percent completion points.
5. Review Owner's comments and make agreed upon revisions to the plans,
specifications and bidding documents.
6. Print and furnish Owner with 50 sets of plans, specifications and
bidding documents. Specifications and bidding documents will be
bound in 8-1/2 x 11 books.
7. Assist Owner in working with RWQCB and in filing for discharge
requi rements.
A preliminary list of drawing sheets is included as Exhibit B.
SECTION 3 (Time of Performance)
The ENGINEER and OWNER have agreed upon the scope and recognize that time is
of the essence. To this extent, the following schedule has been proposed:
Days Following
Item Authorization to Proceed
1. Notice to Proceed 0
2. Complete Rapid Bloc Renovation 65
3. Provide 85 Percent Design Submittal 40
4. Provide Final Plans and Specifications 65
The OWNER/ENGINEER agree that each will diligently work toward meeting the
above schedule.
-2-
It is envisioned that all work covered by the Task Order will be completed by
September 1987. If for unforeseen reasons the work is delayed beyond this
date, the ENGINEER may need to revise the scope and payment provisions for
work accomplished at a later date.
SECTION 4 (Payment)
Payment to the ENGINEER for services performed under this Task Order shall be
as provided for in SECTION 3B of the January 1987 AGREEMENT. Payment for
services under this Task Order shall be based on the ENGINEER'S Direct Salary
times a Multiplier. The Multiplier for this Task Order shall be 2.761. A
cost ceiling of Sixty Thousand Seven Hundred Dollars ($60,700.00) is hereby
established for the envisioned work, and will not be exceeded except as
provided for in SECTION 3 of the January 1987 AGREEMENT. Exhibit A is
attached hereto, and reflects the above costs.
SECTION 5 (Effective Date)
This Task Order No. 3 is effective as of 21 April 1987.
IN WITNESS WHEREOF, this AGREEMENT is executed by the Mayor and City Clerk of
the CITY OF REDLANDS, pursuant to action of its City Council authorizing same,
and the ENGINEER has caused this AGREEMENT to be executed the day and year
first written above.
CITY OF REDLANDS JOHN CAROLLO ENGINEERS
By BY A[
Mayor '7 Gail P. Lv1A ch
Partne�j
ATTEST
ity Clerk
kv
-3-
EXHIBIT A
BUDGET SUMMARY
TO TASK ORDER NO. 3
1. Sheet count (see Exhibit B) 14 Sheets
2. Manhours @ 120 hrs/sheet (9 sheets) 1,080 hrs.
(5 repeat sheets)
3. Labor and Budget @ $19.00/hr @ 2.761 $56,656
4. Expense Budget
• Reproduction $3,500
s Computer 10 hrs @ $15 150
• CADD 10 hrs @ $25 250
3 hrs @ $35 105
$4,005
Budget Total $60,661
Say $60,700
JCE 4/13/87
EXHIBIT B
TO
TASK ORDER NO. 3
PRELIMINARY DRAWING LIST
IMMEDIATE CAPACITY PROJECT
Sheet Dwg.
No. No. Title
1 G1 Cover, Legend, Index
2 G2 Coordinate Control Sheet
3 Y1 Grading, Paving and Piping
4 Y2 Sections and Details
5 HW1 Plan and Sections - Head
6 HW2 Sections and Details - Headworks Modifications
7 EPS1 Effluent Pump Modifications
8 CH1 Plan and Sections
9 CH2 Sections and Details
10 spi Sludge Pump Station Plan
11 SP2 Sludge Pump Station Details and Sections
12 El Symbols and Legend
13 E2 Plans and Details
14 E3 Single Line and Schematics
JCE 4/13/87
AGREEMENT TO FURNISH ENGINEERING SERVICES
FOR
REDLANDS WASTEWATER TREATMENT PLANT EXPANSION
TASK ORDER NO. 4
(DESIGN REPORT AND PRELIMINARY DESIGN SERVICES)
This AGREEMENT is made and entered into as of this 21 -,t day
of April , 1987,
by and between City of Redlands, hereinafter
referred to as "OWNER"
and John Carollo Engineers, hereinafter
referred to as "ENGINEER"
In consideration of the mutual promises, covenants and conditions hereinafter
set forth, the parties do hereby agree as follows:
SECTION 1 _jP�ose}_
The purpose of this Task Order is to authorize and direct the ENGINEER to
proceed with certain "DESIGN REPORT AND PRELIMINARY DESIGN SERVICES" as de-
scribed in SECTION 2(A) and 2(B) of the January, 1987 AGREEMENT, and as more
specifically described below.
SECTION 2 (Scope of Work)
The following items will be included in this preliminary engineering effort;
accordingly:
1. Further analyze those processes and process combination issues not
fully resolved in the Design Update.
2. Select and recommend the process train to be used.
3. Size and develop design criteria for all processes.
4. Develop an hydraulic flow diagram, an hydraulic profile and' a solids
balance for the plant.
5. Determine outline dimensions and geometry for major process struc-
tures, buildings, and major conduits. Develop preliminary design
drawings at full scale for major structures.
6. Prepare a preliminary, full-scale site layout considering hy-
draulics, construction requirements, topography and access.
7. Prepare an estimate of electrical loads and preliminary motor
horsepower li st.
-1-
8. Determine the adequacy of the electrical power source and the exist-
ing distribution system. Recommend additions and upgrades where
needed. Develop provisions and recommendations for standby elec-
trical power.
9. Prepare a cost estimate based on the preliminary designs, refining
and updating earlier estimates.
10. Prepare a detailed schedule for all design, construction and
permitting.
11. Provide for a geotechnical investigation and report covering new and
existing areas of the plant site.
12. Meet with the Owner at least monthly to present and discuss con-
cepts, progress and recommendations.
13. Provide review sets of drawings and text at appropriate times during
the progress of the work.
14. Furnish three (3) copies of pre-design memorandums and applicable
drawings for review by the Owner.
15. Make appropriate changes based on Owner's review comments.
16. Furnish Owner three (3) copies of completed pre-design memorandums
and associated drawings.
17.. Assist Owner in working with RWQCB and in filing for discharge
requirements.
18. Assist Owner in working with AQMD and in filing for permits.
SECTION 3 (Time of Performance)
The ENGINEER and OWNER have agreed upon the scope and recognize that time is
of the essence. To this extent, the following schedule has been proposed:
Days Following
Item Authorization to Proceed
1. Notice to Proceed 0
2. Submit Draft Pre-Design Notebook Report 60
3. Submit Completed Pre-Design Memorandums 75
The OWNER/ENGINEER agree that each will diligently work toward meeting the
above schedule.
It is envisioned that all work covered by the Task Order will be completed by
September 1987. If for unforeseen reasons the work is delayed beyond this
date, the ENGINEER may need to revise the scope and payment provisions for
work accomplished at a later date.
-2-
SECTION 4 (Payment)
Payment to the ENGINEER for services performed under this Task Order shall be
as provided for in SECTION 3B of the January 1987 AGREEMENT. Payment for
services under this Task Order shall be based on the ENGINEER'S Direct Salary
times a Multiplier. The Multiplier for this Task Order shall be 2.761. A
cost ceiling of Eighty Three Thousand Five Hundred Dollars ($83,500.00) is
hereby established for the envisioned work, and will not be exceeded except as
provided for in SECTION 3 of the January 1987 AGREEMENT. Exhibit A is
attached hereto, and reflects the above costs.
SECTION 5 (Effective Date)
This Task Order No. 4 is effective as of 21 April 1987.
IN WITNESS WHEREOF, this AGREEMENT is executed by the Mayor and City Clerk of
the CITY OF REDLANDS, pursuant to action of its City Council authorizing same,
and the ENGINEER has caused this AGREEMENT to be executed the day and year
first written above.
CITY OF REDLANDS JOHN CAROLLO ENGINEERS
By By 'I A
Mayor N Gail P V14ch
Parin r
ATTEST
City Clerk
-3-
EXHIBIT A
BUDGET SUMMARY
TO TASK ORDER NO. 4
1. Budget Hours 1,000 hrs
2. Labor Budget 1,000 hrs @ $20.00/hr @ 2.761 $55,220
3. Expense Budget
• Computer 40 hrs @ $15 $ 600
• Reproduction 2,500
3,100
4. Outside Services
9 Soils (Geotechnical Report) $25,000
Budget Total $83,320
Say $83,500
JCE 4/13/87
AGREEMENT TO FURNISH ENGINEERING SERVICES
FOR
REDLANDS WASTEWATER TREATMENT PLANT EXPANSION
TASK ORDER NO. 5
(PRELIMINARY AND FINAL DESIGN SERVICES FOR
OPERATIONS AND LABORATORY BUILDING)
This AGREEMENT is made and entered into as of this 21st day
of April 1987,
by and between City of Redlands, hereinafter
referred to as "OWNER"
and John Carollo Engineers, hereinafter
referred to as "ENGINEER"
In consideration of the mutual promises, covenants and conditions hereinafter
set forth, the parties do hereby agree as follows :
SECTION 1 (Purpose)
The purpose of this Task Order is to authorize and direct the ENGINEER to
proceed with certain "PRELIMINARY AND FINAL DESIGN SERVICES" as described in
SECTION 2(B) of the January, 1987 AGREEMENT, and as more specifically de-
scribed below.
SECTION 2 -(Scope of Work)
The following items will be included in this engineering effort; accordingly:
1. Meet with Owner to discuss requirements and architectural motifs for
the Operations and Laboratory Building.
2. Prepare layouts and floor plans for a building of approximately
5,500 square feet (4,000 square feet operations/1,500 square feet
laboratory). Planning shall include future expansions of the
building to approximately 12,000 square feet.
3. Prepare Architectural elevations of the building. - Up to three
motifs will be shown.
4. Meet with Owner to present and discuss the layouts, floor plans and
architectural elevations. Make changes as agreed upon.
5. Prepare plans, specifications and bidding documents for construction
of the building including adjacent site work, parking, landscaping,
finishes and floor coverings, and laboratory furniture. Laboratory
equipment other than major items such as fume hoods and vacuum pumps
will not be included.
-1-
6. Meet with Owner approximately monthly to present progress prints and
discuss the project.
7. Submit five copies of plans, specifications and bidding documents to
Owner for review at the 50 and 85 percent completion points.
8. Review Owner's comments and make agreed upon revisions to the plans,
specifications and bidding documents.
9. Print and furnish Owner with 50 sets of plans, specifications and
bidding documents. Specifications and bidding documents will be
bound in 8-1/2 x 11 books. Plans will be reduced to half scale and
bound with covers.
A preliminary list of drawing sheets is included as Exhibit B.
SECTION 3 (Time of Performance)
The ENGINEER and OWNER have agreed upon the scope and recognize that time is
of the essence. To this extent, the following schedule has been proposed:
Days Following
Item Authorization to Proceed
1. Notice to Proceed 0
2. Provide Architectural Layouts 50
3. Provide 50 Percent Submittal 90
4. Provide 85 Percent Submittal 160
5. - Provide Final Plans and Specifications 180
The OWNER/ENGINEER agree that each will diligently work toward meeting the
above schedule.
It is envisioned that all work covered by the Task Order will be completed by
January 1988. If for unforeseen reasons the work is delayed beyond this date,
the ENGINEER may need to revise the scope and payment provisions for work ac-
complished at a later date.
SECTION 4 (Payment)
Payment to the ENGINEER for services performed under this Task Order shall be
as provided for in SECTION 3B of the January 1987 AGREEMENT. Payment for
services under this Task Order shall be based on the ENGINEER'S Direct Salary
times a Multiplier. The Multiplier for this Task Order shall be 2.761. A
cost ceiling of Eighty Two Thousand Nine Hundred Dollars ($82,900.00) is
hereby established for the envisioned work, and will not be exceeded except as
provided for in SECTION 3 of the January 1987 AGREEMENT. Exhibit A is
attached hereto, and reflects the above costs.
-2-
SECTION 5 (Effective Date)
This Task Order No. 5 is effective as of 21 April 1987.
IN WITNESS WHEREOF, this AGREEMENT is executed by the Mayor and City Clerk of
the CITY OF REDLANDS, pursuant to action of its City Council authorizing same,
and the ENGINEER has caused this AGREEMENT to be executed the day and year
first written above.
CITY OF REDLANDS JOHN CAROLLO ENGINEERS
By
By
4 Af
Mayor Gail P. ch
Partn r
ATTEST
City Clerk
City
-3-
EXHIBIT A
BUDGET SUMMARY
TO TASK ORDER NO. 5
1. Sheet count (see Exhibit 8) 17 Sheets
2. Manhours @ 100 hrs/sheet (14 sheets) 1,400 hrs.
(3 repeat sheets)
3. Labor and Budget @ $19.00/hr @ 2.761 $73,443
4. Expense Budget
• Plane - 3 trips $ 450
0 Rental Car 150
0 Per Diem (6 days @ $50) 300
• Reproduction 3,500
$4,400
5. Outside Services
Local Architectural Theme $5,000
Budget Total $82,843
Say $82,900
JCE 4/13/87__
EXHIBIT 8
TO TASK ORDER NO. 5
PRELIMINARY DRAWING LIST
OPERATIONS AND LABORATORY BUILDING
1 Title Sheet
2 Grading/Paving and Plot Plans
3 Landscaping and Irrigation
4 Building Elevations
5 Foundation Plans and Details
6 Floor Plan
7 Roof Framing and Roof Plan
8 Structural Sections and Details
9 Structural Details
10 HVAC
11 Plumbing
12 Interiors and Schedules
13 Lab Sections and Details
14 Electrical - Site and General
15 Electrical - Floor Plan
16 Electrical - Reflected Ceiling
17 Electrical - Single Lines and Details
JCE 4/13/87