HomeMy WebLinkAboutContracts & Agreements_17-2004_CCv0001.pdf FIRST AMENDMENT TO AGREEMENT TO FURNISH CONSULTING SERVICES FOR
DESIGN OF BRIDGES OVER THE SANTA ANA RIVER AT ORANGE STREET AND AT
ALABAMA STREET PHASE I
This Agreement is made and entered into this third day of February 2004, by and between
the City of Redlands, a municipal corporation("City"), and TYLIN International ("Consultant").
In consideration of the mutual promises contained herein, City and Consultant agree to the
following amendments to the Agreement to Furnish Consulting Services dated November 4, 1997
(hereinafter the "Agreement"):
Section 1. In addition to those services listed in Exhibit "A" to the Agreement, Consultant
shall provide additional services as listed in Appendix 1.
Section 2. In addition to the compensation payable to Consultant in Section 4.1 of the
Agreement, Consultant shall be paid the additional sum of$50,840.00 for the additional services
described in Section 1, above. The total compensation now payable to Consultant pursuant to the
Agreement is $211,544.44.
Section 3. Consultant's Services under the Agreement shall now be completed by June 10,
2004.
IN WITNESS WHEREOF,duly authorized representatives of the parties have signed in confirmation
of this First Amendment to Agreement.
CITY OF REDLANDS
Attests j*
By
City Mayor City:Oerk J,
Date February 3 , 2004
TYLIN International
gy Date
David Griffit VU
I ,Capital P1"jects,Fant , Ula Rl'-1 C) 01 ��Al`Col 0I c�',A!,,'Coji�ifflwit %nwnd \,)I wpd
APPENDIX 1
y
TYL1
NCP
6
January 12, 2004 z
Received
Bill Hemsley, P.E. CA Public dors
CITY OF REDLANDS Department
Public Works Department
P.O. Box 3005
Redlands, CA 92373
RE: Orange Street and Alabama Street Bridges
Geotechnical Investigation
Dear Bill:
Pursuant to your request to begin the geotechnical investigation, this letter is a request for
approval to add that task to our scope of work and the corresponding fees to our budget for
the Preliminary Engineering phase of the project. This investigation had been planned for the
Final Design phase, but is needed now as part of the preliminary engineering to establish the
remaining final design parameters and expedite the project completion.
The work will consist of a foundation investigation and report and will be preformed by our
geotechnical subconsultant, Converse Consultants. A summary of the scope of work for this
task is attached. The compensation needed to complete this work is$25,420 for each bridge
location, for a total amount of$50,840.
If the above described amendment to our Preliminary Engineering agreement is acceptable,
please sign below and return one copy of this letter to our office as approval and signifying
notice to proceed. Do not hesitate to contact me with any questions, or if you require
additional information.
Sincerely,
T.Y. LIN INTERNATIONAL
t
David Griffith, P.
Project Manager
Enclosure
T.Y. Lin International
SCOPE OF WORK AMENDMENT
Jnr
THE REPLACEMENT OF ORANGE STREET AND ALABAMA STREET BRIDGES
AT THE SANTA ANA RIVER
PHASE I - PRELIMINARY ENGINEERING SERVICES
January 9, 2004
I. ADDITIONAL BASIC SERVICES TO BE PERFORMED BY CONSULTANT
Task 1 -Site Reconnaissance and Investigations
1-1 Foundation Investigation
A subsurface investigation conforming with Article 43.5, -Required Subsurface
Investigations,"of the Caltrans Bridge Design Specifications and other Caltrans standards
and requirements shall be made by a geologist or civil engineer licensed in California
specializing in foundations.
In general, the subsurface investigation shall be of sufficient scope to reasonably identify
subsurface conditions and obtain relatively undisturbed material samples for testing and
development of design recommendations.
For this project. the subsurface investigation shall include the following tasks:
I-LI Develop access for a drill rig to reach the river channel area.
1-1.2 Twelve borings (6 borings at Orange Street and 6 borings at Alabama Street) will be
drilled with Becker Hammer and Hollow-stem auger drilling equipment. The
borings will be drilled to depths between 40 and 60 feet below existing ground
surface (bgs) or to refusal, whichever is shallower. If possible, undisturbed samples
of the subsurface materials will be obtained at approximately five-foot intervals in
the borings. Bulk samples of representative soil types will be obtained.
1-1.3 Standard Penetration Tests (SPTs) will be conducted using a 1.4-inch interior
diameter(ID) sampler driven by a 140-pound hammer falling 30 inches in general
accordance with ASTM Standard D1586 test method. Disturbed samples of
subgrade soils will be obtained.
1-1.4 If groundwater is encountered, groundwater levels in the borings will be recorded.
1-1.5 Sufficient laboratory tests will be performed to assess the engineering properties for
the analyses of the design conditions and preparing construction recommendations.
1-1.6 The draft lo---s of borings shall be submitted to the City Public Works Director.
Scope of Work Amendment—Phase I Preliminary Engineering Services
Orange Street and Alabama Street Bridge Replacements
January 9,2004
Page 2 of 2
1-2 Foundation & Materials Report
The Foundation and Materials Report shall conform with Sections 3-8 and 6-1 of the
Caltrans EFP13 Information and Procedures Guide and with "Guidelines for Preparation of
Structure Foundation Reports"by the Caltrans Office of Structural Foundations and shall
include the following:
1-2.1 Evaluation of types, locations, and engineering characteristics of foundation
materials.
1-2.2 Assessment of engineering seismology and liquefaction potential.
1-2.3 Evaluation of factors affecting the design of the proposed structures, including total
settlement and groundwater.
I-2A Recommendation of the most feasible methods of foundation support with allowable
and ultimate bearing capacities, uplift capacities and resistance to lateral loads.
1-2.5 R-value tests and recommendations for roadway pavement structural sections.
1-2.6 Specified and probable tip elevations for 45 and 70-ton piles.
1-2.7 Evaluation of the corrosion potential.
1-2.8 Recommended amendments to Caltrans'Standard Specifications regarding site
grading.
1-2.9 Identification of unsuitable materials requiring removal and re-compaction or
replacement.
1-2,10 The estimated acceleration and depth to rock-like materials in accordance with
Caltrans'Bridge Design Si)ecifications.
1-2.11 Preparation of a "Log of Test Borings" sheet measuring 24 inches by 36 inches
presented in the standard Caltrans format on City title block drawing sheets.