HomeMy WebLinkAboutContracts & Agreements_22-1989_CCv0001.pdf AMENDMENT NO. 1
TO THE
AGREEMENT TO FURNISH CONSULTING SERVICES
FOR
CONSTRUCTION OF THREE WELLS AND GROUNDWATER ASSESSMENT
IN SAN TIMOTEO AND LIVE OAK CANYONS
This Amendment authorizes the Consultant to provide con-
struction specifications and preconstruction activities for
the wells as separate projects and services during well
construction and development for the Hog Canyon Well in
accordance with the Agreement dated August 3 , 1988 and this
Amendment.
This Amendment makes the following changes to the Agreement;
all other provisions of the Agreement remain in effect.
ARTICLE 3. - ENGAGEMENT DF THE C4N3IILTANT
No changes .
ARTIQU 2_- SERVICES,_QF_THE_ENGINEER
Add Article 2 .3 as follows:
2.3 The construction specifications and precon-
struction activities scope is changed to pre-
paration of the technical portions of three
separate well bid packages and services during
three bid periods .
ARTICLE_3_- REjqRQNfj1BILITIES OF THE OWNER
No changes .
ART CI 4 - PERIQP QZ SERVICE
Add Articles 4 .3 and 4 .4 as follows:
4.3 The period of service for the Project 3 con-
struction specifications shall be 30 days after
notice to proceed for each well, and for the
Project 3 prebid and preconstruction meetings,
shall be as defined in the construction contract
documents .
4.4 The period of service for Project 4 and 5,
services during well construction and well
development, shall be the period defined in the
construction contract documents.
ARTICLE 5 - PAYMENTS_X0_TffK_CQN6ULT&NT
Add Articles 5 .5 and 5 .6 as follows:
5 .5 The payment for Project 3, construction speci-
fication and preconstruction activities, shall
be in accordance with Attachment A, herewith,
and be on a time and materials basis in ac-
cordance with the Consultant' s Schedule of
Charges, Attachment B of the August 3, 1988
Agreement .
5.6 The payment for Hog Canyon Project 4 and 5 scope
of work shall be in accordance with Attachment
Bt herewith, and be on a time and materials
basis in accordance with the Consultant's
Schedule of Charges, Attachment B of the August
3 , 1988 Agreement.
ARTICLE 6 - INgLJMLqCF_ANPqIr
_JWPKL IgATION
No changes.
&RTICL.A 7 - GENERAL_CONglpERATIONS
No changes.
SUMMARY BUDGET
Original Agreement Amount $ 20,447
Project 3 Revised Budget $ 15,261
Hog Canyon Project 4&5 Budget $ 21,528
New Agreement Amount $ 57,236
-2-
IN WITNESS WHEREOF, duly authorized representatives of the
parties have signed in confirmation of this Amendment.
CITY OF REDLANDS RICHARD SLADE
Mayor R chard Slade
M" x
Date: 4 , 198.9 Date: 6Y
L 1.s1 Lk i
Attachments: A. Project 3 Construction Specifications and
Preconstructon Cost Estimate.
B. Project 4 & 5 Roca Canyon Construction and
Well Development Cast Estimate.
-3
ATTACHMENT A
Revised Cost Estimates -- Job S8812 1 of 3
December 27, 1933
REVISED COST ESTIMATES
PROJECT NO. 3 CONSTRUCTION SPECIFICATIONS AND PRE-CONSTRUCTION
For Hoq Canyon Replacement Weil
Task No. 1 -- Technical Specifications
Hydrogeologist 15 hrs
Geologist 32 hrs
Clerical 14 hrs
Task No. 2 - En ineers Estimate
Hydrogeologist 2 hrs
Geologist 3 hrs
Clerical 2 hrs
Task No� 3 - Assist on Hid Process
Hydrogeologist 4 hrs
Geologist 2 hrs
Clerical 0 hrs
Task No . 4 - Pre-Hid and Pre-Construction Meetings
Hydrogeologist 12 hrs
Geologist 10 hrs
Clerical 4 hrs
Subtotal for Hog Canyon Project :
Hydrogeologist 33 hrs CW $85 $ 2, 305 .00
Geologist 47 hrs C $45 2, 115 .00
Clerical 20 hrs 4 27 540.00
Miscellaneous 50. 00
$ 5,510.00
Revised Cost Estimates - Job 58812 2 of 3
December 27, 138E
For Mill geek e lacement Well
Task No. 1 - Technical S ecificatic�ns
Hydrogeologist 14 hrs
Geologist 24 hrs
Clerical 16 hrs
Task No. 2 - Engineer ' s Estimate
Hydrogeologist 3 hrs
Geologist 4 hrs
Clerical 3 hrs
Task No. 3 - Assist on Bid Process
Hydrogeologist 4 hrs
Geologist 2 hrs
Clerical 0 hrs
Task No. 4 - Pre-Bid and Pre-Construction Meetings
Hydrogeologist 12 hrs
Geologist 10 hrs
Clerical 4 hrs
Subtotal for Mill Creek Project :
Hydrogeologist 33 hrs @ $85 $ 2 ,805 . 00
Geologist 40 hrs @ $45 1 , 800. 00
Clerical 23 hrs @ $27 621 .00
Miscellaneous 50. 00
$ 5, 276.00
For Orange Street �3ell
Task No. 1 -- Technical Specifications
Hydrogeologist 15 hrs
Geologist 12 hrs
Clerical 8 hrs
Revised Cost Estimates - Job 58812 3 of 3
December 27, 1388
Task No. 2 - Engineers Estimate
Hydrogeologist 2 hrs
Geologist 3 hrs
Clerical 3 hrs
Task No. 3 - Assist on Bid Process
Hydrogeologist 4 hrs
Geologist 2 hrs
Clerical 0 hrs
Task No. 4 - Pre--Bich and Pre-Construction Meetings
Hydrogeologist 12 hrs
Geologist 10 hrs
Clerical 4 hrs
Subtotal for Orange Street Well
Hydrogeologist 33 hrs C $85 $ 2,8035 .00
Geologist 27 hrs @ $45 1 , 215 . 030
Clerical 15 hrs @ $27 405 .00
Miscellaneous 50. 030
$ 4475 .00
Final Total of Revised Estimate�3 Wells}
Hydrogeologist 99 hrs @ $85 $ 8,415 . 00
Geologist 114 hrs @ $45 5, 130. 003
Clerical 58 hrs C 27 1 , 558 .00
Miscellaneous 1503 .00
=15, 261 .003
Fee Proposal - Hog Canyon Replacement Well 3
Subtotals for Project No
Hydrogeologist 23 hrs 4 $85 .00/hr $1 ,955 . 00
Geologist 146 hrs 4 $45 .00/hr 6, 570 .00
Clerical 22 hrs 4 $27 .00/hr 594 .00
Drafting 6 hrs 4 $31 .00/hr . 186 .00
Miscellaneous ( telephone, mileage, report and
map reproductions, etc. ) 500 .00
$9, 805 .00
Estimated Cost Total for Projects Nos . 4 and 5 21 528' 00
Fee Proposal - Hog Canyon Replacement Well 2
Task No. 8 _7 Casing Alignment Testing
Geologist 6 hrs
Subtotals for Project No. 4
Hydrogeologist 27 hrs @ $85 .00/hr $ 2, 295 .00
Geologist 180 hrs @ $45 . 00/hr 8, 100.00
Clerical 14 hrs @ $27 .00/hr 378 .00
Grain Size Tests (5 @ $110 .00 ea. ) 550 .00
Miscellaneous ( telephone, mileage, reproduction) 400 .00
$11 ,723 .00
Services During Well Development
and Testing
Task No. 1 - Well Development - Mechanical and Pumping
Hydrogeologist 8 hrs
Geologist 80 hrs
Task No. 2 - Step Drawdocn Testing
Hydrogeologist 3 hrs
Geologist 12 hrs
Task No. 3 - Final A uifer Test Pum in Test
Hydrogeologist 4 hrs
Geologist 18 hrs
Task No. 4 - Submittals
Hydrogeologist 2 hrs
Geologist 6 hrs
Clerical 8 hrs
Task No. 5
Hydrogeologist 6 hrs
Geologist 30 hrs
Clerical 14 hrs
Drafting 6 hrs
ATTACHMENT B
FEE PROPOSAL
HOG CANYON REPLACEMENT WELL
PROJECT NO. 4 11 Construction
Task No. I - Mobilization
Hydrogeologist 2 hrs
Geologist 6 hrs
Task No. 2 - Pilot Hole Logging_
Hydrogeologist 8 hrs
Geologist 90 to 115 hrs
(use 115 for final estimate)
Grain Size Testing (up to 5 samples)
Task No. 3 - Geophysical Log Analysis
Hydrogeologist 6 hrs
Geologist 4 hrs
Task No. 4 - Down-hole Aquifer Zone Sampling
Not a part of this project
Task No. 5 - Well Completion Recommendations
Hydrogeologist 4 hrs
Geologist 4 hrs
Task No. 6 ion
Hydrogeologist 4 hrs
Geologist 36 hrs
Task No. 7 - Submittals
Hydrogeologist 3 hrs
Geologist 9 hrs
Clerical 14 hrs