HomeMy WebLinkAboutContracts & Agreements_97-1999_CCv0001.pdf AGREEMENT TO FURNISH
PRELIMINARY ENGINEERING DESIGN
FOR THE CALIFORNIA STREET LANDFILL
HORIZONTAL EXPANSION
This Agreement is made and entered into this 19th day of October, 1999,by and between the City
of Redlands, a municipal corporation(hereinafter"City") and Vector Engineering,Inc., (hereinafter
"Engineer")-
In consideration of the mutual promises, covenants and conditions hereinafter set forth, City and
Engineer hereby agree as follows:
ARTICLE I - ENGAGEMENT OF ENGINEER.
1.1 City hereby engages Engineer, and Engineer hereby accepts the engagement, to perform
preliminary engineering design("Services")related to the City's California Street Landfill
horizontal expansion("Project"),
1.2 The Services shall be performed by Engineer in a professional manner, and Engineer
represents that it has the skill and the professional expertise necessary to provide high quality
Services for the Project at the level of competency presently maintained by other practicing
professional Engineers in the industry providing similar types of services.
ARTICLE 2 - SERVICES OF ENGINEER
2.1 The specific Services which Engineer shall perform are more particularly described in
Attachment"A,"entitled"Scope of Work,"which is attached hereto and incorporated herein
by this reference.
ARILC,LE-L--RESPO—N,SlBILIIIES-OE-CLT-Y
3.1 City shall make available to Engineer information in its possession that is pertinent to the
performance of Engineer's Services.
12 City will provide access to and make provisions for Engineer to enter upon City-owned
property as required by Engineer to perforin the Services.
33 City designates Valorie Shatynski, Solid Waste Manager, to act as its representative with
respect to the Services to be performed under this Agreement.
I
Agreement to Furnish Preliminary Engineering Design
For The California Street Landfill Horizontal Expansion
Vector Engineering, Inc.
October 19, 1999
ARTI ,F -TIMOD-OESERY10E
4.1 Engineer shall perform the Services in a diligent manner and in accordance with the
schedule set forth in Attachment B - Project Schedule.
ARTICLE E - PAYMENTS TO THE ENGINEER
5.1 The total compensation for Engineer's performance of the Services shall not exceed
$99,704.04 in accordance with Attachment C - Project Fee and Rate Schedule. City shall
pay Engineer on a time and materials basis at the hourly rates shown in Attachment C.
5.2 Engineer shall bill City within ten days following the close of each month by submitting an
invoice indicating the Services performed, who performed the Services,indirect costs, and
the detailed cost of all Services including backup documentation. Payments by City to
Engineer shall be made within 30 days after receipt and approval of Engineer's invoice,by
warrant payable to Engineer.
5.3 All contractual notices, bills and payments shall be made in writing and may be given by
personal delivery or by mail. Notices, bills and payments sent by mail shall be addressed as
follows:
Cid Engineer
Valorie Shatynski Scott Purdy, President
Municipal Utilities Department Vector Engineering, Inc.
35 Cajon Street 12438 Loma Rica Drive, Suite C
P. O. Box 3005 Grass Valley, CA 95945
Redlands, CA 92373
When so addressed, such notices shall be deemed given upon deposit in the United States
Mail. In all other instances, notices, bill and payments shall be deemed given at the time of
actual delivery. Changes may be made in the names and addresses of the person to whom
notices, bills, and payments are to be given by giving notice pursuant to this paragraph.
Agreement to Furnish Preliminary Engineering Design
For The California Street Landfill Horizontal Expansion
Vector Engineering, Inc.
October 19, 1999
ARTICLE 6—�OLJRAN F AND INDFMNIF1CATIQN
6.1 Engineer shall maintain worker's compensation insurance and, in addition, shall maintain
insurance to protect City from claims for damage due to bodily injury,personal injury and
death, and claims for injury to or destruction of tangible property while performing the
Services required by this Agreement. Said public liability and property damage insurance
shall be in a minimum combined single limit of$1,000,000, and in the aggregate. Engineer
shall maintain professional liability insurance in the aggregate amount of$1,000,000 with
a minimum of$500,000 per occurrence. City shall be named as an additional insured under
all policies for public liability,property damage and comprehensive automobile liability and
professional liability insurance, and such insurance shall be primary with respect to City and
non-contributing to any insurance or self-insurance maintained by the City. Engineer shall
provide City with certificates of insurance evidencing such insurance coverage prior to
commencing the Services.
6.2 Engineer shall indemnify, hold harmless and defend City and its elected officials, officers,
agents and employees from and against all claims, loss, damage, charges or expense, to
which it or any of them may be put or subjected to the extent that they arise out of or result
from any willful or negligent act or actions, omission or failure to act on the part of the
Engineer,its contractors,its suppliers,anyone directly or indirectly employed by any of them
or anyone for whose acts or omissions any of them maybe liable in the performance of the
Services required by this Agreement.
ARTICLE-7---GENERAI-CONSIDERAIJONS
7.1 In the event any action is commenced to enforce or interpret any of the terms or conditions
of this Agreement the prevailing party shall, in addition to any costs and other relief, be
entitled to the recovery of its reasonable attorneys' fees.
7.2 Engineer shall not assign any of the Services required by this Agreement, except with the
prior written approval of City and in strict compliance with the terms, provisions and
conditions of this Agreement.
3
Agreement to Furnish Preliminary Engineering Design
For The California Street Landfill Horizontal Expansion
Vector Engineering, Inc.
October 19, 1999
7.3 Engineer's key personnel for the Project are:
Principal and Project Manager: Scott Purdy, C.E.G.
Project Engineer: Thomas Woodward, P.E.,R.G.
Engineer agrees that the key personnel shall be made available and assigned to the Project,
and that they shall not be replaced without concurrence from City.
7.4 All documents, records, drawings, designs, costs estimates, electronic data files and
databases and other Project documents developed by the Engineer pursuant to this
Agreement shall become the property of City and shall be delivered to City upon completion
of the Services or upon the request of City. Any reuse of such documents for other projects
and any use of incomplete documents will be at City's sole risk.
7.5 Engineer is for all purposes an independent contractor. All personnel employed by Engineer
are for its account only, and in no event shall Engineer or any personnel retained by it be
deemed to have been employed by City or engaged by City for the account of or on behalf
of City.
7.6 Unless earlier terminated, as provided for below, this Agreement shall terminate upon
completion and acceptance by City of the Services.
7.7 This Agreement may be terminated by either party, without cause, by providing thirty(30)
days prior written notice to the other(delivered by certified mail, return receipt requested)
of intent to terminate.
7.8 Upon receipt of a termination notice, Engineer shall (1) promptly discontinue all services
affected, and(2)deliver or otherwise make available to City, copies(in both hard copy and
electronic form, where applicable), of any data, design calculations, drawings,
specifications, reports, estimates, summaries and such other information and materials as
may have been accumulated by Engineer in performing, the Services required by this
Agreement.
7.9 Engineer shall maintain books and accounts of all Project related payroll costs and all
expenses. Such books shall be available at all reasonable times for examination by the City
at the office of Engineer.
4
Agreement to Furnish Preliminary Engineering Design
For The California Street Landfill Horizontal Expansion
Vector Engineering, Inc.
October 19, 1999
7.10 This Agreement, including the attachments incorporated herein by reference, represents the
entire agreement and understanding between the parties and any prior negotiations,proposals
or oral agreements are superseded by this Agreement. Any amendment to this Agreement
shall be in writing, approved by the City Council of City and signed by City and Engineer.
7.11 This Agreement shall be governed by and construed in accordance with the laws of the State
of California.
IN WITNESS WHEREOF, duly authorized representatives of the City and Engineer have signed in
confirmation of this Agreement.
City of Redlands Vector Engineering, Inc.
("City") ("Engineer")
By: t = By:
WILLE. CH - VINCE SURYASASMITA, P.E.
fAM UNNfN
Mayor ' Executive Vice President
ATTEST:
44e L---
e-
y.,`
, lands
City CVrk, Cit
ATTACHMENT A
SCOPE OF WORK
ATTACHMENT A— SCOPE OF WORK
Task 1: Preliminary Engineering Design
Task 2 will consist of a design report and drawings associated with the proposed design
of the horizontal expansion at the California Street Landfill. The design report will
consist of the following components:
• Stability analyses of cut and fill slopes;
• Leachate generation analysis;
• Alternative liner system demonstration;
• Surface drainage/stormwater analysis; and
• Landfill capacity and sequencing.
Along with the design report, the drawings associated with the first phase of
development will be prepared. The drawings will not be construction ready, but will
show all the approximate grades and liner system components. The drawings to be
prepared will include, but not be limited to the following:
• Cover sheet;
• Existing site plan;
• Grading plan;
• Liner system layout;
• Leach collection and removal system layout;
• Surface drainage; and
• Details.
Although the first phase of construction will be designed in detail, the overall
development of the site is also necessary for permitting. Vector will prepare
development drawings showing the proposed construction of subsequent phases of
landfill construction. The capacity and sequencing of each of the phases will be
determined based on current refuse quantities adjusted for growth. From the site
development work, the overall life of the site can be estimated and included in the
permit documents.
Deliverables for Task 1: Phase I Drawings, Design Report, Site Development
Drawings, and Site Capacity.
Page 1
Task 2. Preliminary Closure Plan and Joint Technical Document
Task 3 will involve the development of preliminary closure documents and the
preparation of the Joint Technical Document for the horizontal expansion. The
preliminary closure development drawings will be prepared showing the final refuse fill
capacity and grades. A capping system design will also be developed. The preliminary
closure drawings will include, but not be limited to the following:
• Existing conditions;
• Foundation layer grades;
• Capping system layout;
• Drainage layer layout;
• Surface water collection;
• Protective layer grades; and
• Details.
Along with the preliminary closure development drawings, a preliminary closure plan,
preliminary post-closure plan, and cost estimates will be prepared.
Following preparation of the design drawings, site development, engineering
calculations, and closure work, a Joint Technical Document will be prepared for the
California Street Landfill horizontal expansion. Where feasible, Vector will utilize the
previously prepared JTD that was recently completed for the existing site.
Deliverables for Task 2: Preliminary Closure Drawings, Preliminary
Closure/Preliminary Post-Closure Plans, Permit JTD
Page 2
ATTACHMENT B
SCHEDULE
SCHEDULE FOR HORIZONTAL CONCEPTUAL DESIGN AND PERMITTING AT THE
CALIFORNIA STREET LANDFILL, REDLANDS, CALIFORNIA
2000
ID Task Name Nov Dec Jan Feb Mar Apr May Jun Jul AugSe
1 Preliminary Engineering Design
2 Preliminary Closure Plan and JTD
Task Summary Rolled Up Progress
Project: P992090.00 Critical Deadline ♦ Rolled Up Task External Tasks
Date:October 1, 1999 Progress Rolled Up Split Project Summary
Milestone . Rolled Up Milestone 0
ATTACHMENT B
ATTACHMENT C
PROJECT FEE AND RATE SCHEDULE
ATTACHMENT C-PROJECT FEE AND RATE SCHEDULE
Scott Purdy/Marc Orman Woodward/Ramey/ Moorehead/Russell/ Cathy Stone/Amy Butler Hours
($90/hour Twede($80/hour) King($65/hour) ($35/hour) Well Drilling Per Costs Per -—Remaining
Task Description Hours Costs Hours Costs Hours Cos#s Hours Costs Each Costs Task Task Budget
Task 1. Preliminary Enqineer120: $ 10,800 2201 $ 17,600 540: $ 35,100 40 $ 1,400 0 $ 880 $ 64,900 $ 64,900
Task 2. Prefinninaa Closure Plan and JTD 801 $ 7,200 100! $ 8,000 280 $ 18,200 40 $ 1,400 0 $ 460 $ 34,800 $ 34,800
Total Project CostsW
200.0 $ 18,000 1 320.01 $ 25,600 1 820.01 $ 53,300 80.0 $ 2,800 0.0 $ - 1340 $ 99,7
Vector Engineering,Inc.