HomeMy WebLinkAboutContracts & Agreements_180-2019aw
August 28, 2019
Via Email
Mayor Paul W. Foster
City of Redlands, California
DAN VOTENILEK
Area Manager, Construction &
Engineering
AT&T Mobility Services LLC
1452 Edinger
Tustin, CA 92780
(562) 716-4647 Phone
dv574p@att.com
Re: Extension of FCC Shot -Clock Deadline on Six (6) AT&T Small Wireless Facility Applications
Site One:
Site Two:
Site Three
Site Four:
Site Five:
Site Six:
Dear Mayor Foster:
AT&T Site ID SNBRN_001; City File CUP No. 1117
PROW near 991 Pine Avenue
AT&T Site ID SNBRN_002; City File CUP No. 1118
PROW near 278 New York Street
AT&T Site ID SNBRN_003; City File CUP No. 1119
PROW near 535 New Jersey Street
AT&T Site ID SNBRN_004; City File CUP No_ 1115
PROW near 800 Tri City Center Drive
AT&T Site ID SNBRN_005; City File CUP NO. 1116
PROW near 28 1998 West Redlands Boulevard
AT&T Site ID SNBRN_006; City File CUP No. 1120
PROW near 1811 West Lugonia Street
With respect to the above -referenced applications, the federal Telecommunications Act of 1996, 47 U.S.C. §
332(c)(7)(B)(ii), requires the City of Redlands to take action "within a reasonable period of time." Federal
Communications Commission rules and regulations establish applicable review timeframes (called "shot clocks") to
implement this requirement. The FCC has explained that siting authorities must take action on all approvals and
authorizations necessary for deployment within these review timeframes. The reasonable period of time to act
may be extended or otherwise defined by mutual agreement between the City and AT&T. AT&T understands that
the City needs additional review time in order to process these six applications. Without agreeing that this is an
appropriate reason for delay, and in an effort to work cooperatively with the City, AT&T offers this extension of the
applicable shot clocks for these six applications. Thus, AT&T and the City of Redlands agree to extend the FCC shot
clock deadline for this application to and including September 30, 2019. The parties further agree that no
limitations period for any claim of unreasonable or unlawful delay in processing the application shall commence to
run before September 30, 2019.
To confirm the City's agreement, please countersign below and return this letter to me. Thank you.
Si ceLVozeni
Dan
cc: Daniel J. McHugh, City Attorney
City of Redlands
Toiling Agreement for Six Small Cell Applications
August 8, 2019
Page 2 of 2
Agreed:
CITY OF REDLRNDS, CALIFORNIA
By: Paul W. Foster, Mayor
Attest:
knne Donaldson,
City Clerk