HomeMy WebLinkAboutContracts & Agreements_125-2020AMENDMENT NO. 1
TO COOPERATIVE AGREEMENT NO 17-1001603
BETWEEN
SAN BERNARDINO COUNTY TRANSPORTATION AUTHORITY
AND
CITY OF REDLANDS
FOR
PLANNING, PROJECT REPORT AND ENVIRONMENTAL DOCUMENT,
PLANS, SPECIFICATIONS AND ESTIMATE (PS&E), RIGHT-OF-WAY (ROW),
AND CONSTRUCTION PHASES FOR THE ALABAMA STREET AND
INTERSTATE 10 IN THE CITY OF REDLANDS
THIS AMENDMENT No 1 (AMENDMENT) to the Cooperative Agreement No 17-
1001603 (AGREEMENT) is made and entered into by and between the San Bernardino
County Transportation Authority (hereinafter referred to as AUTHORITY) and the City
of Redlands (hereinafter referred to as CITY) AUTHORITY and CITY may be referred
to herein as a `PARTY" and collectively "PARTIES"
RECITALS
A AUTHORITY and CITY entered into the AGREEMENT on November 9, 2016,
to delineate their respective roles, responsibilities, and funding commitments
relative to the Project Management, Planning, Environmental, PS&E, ROW and
Construction activities of the Alabama Street and Interstate 10 interchange in the
City of Redlands (PROJECT), and
B Pursuant to the AGREEMENT, AUTHORITY is the lead agency for the
PROJECT and is responsible for the diligent undertaking and completion of the
Planning, Environmental, PS&E, ROW, and Construction phases of the
PROJECT, and
C The AGREEMENT presently provides that the cost of the PROJECT is estimated
at $10,968,000 which includes $330,000 for AUTHORITY to provide project
management services for the Planning, Environmental, PS&E, ROW, and
Construction phases of the PROJECT, and
D The PROJECT is now estimated to cost a total of $15,150,600 which includes
$330,000 for the AUTHORITY to provide project management services for the
Planning, Environmental, PS&E, ROW, and Construction Phases of the
PROJECT, and
17 1001603-1
L caudjm\Agrcemcnts\Amcndmcnt No 1 to SBCrA CiKtpera1i c Agreement 1 10 Mamma lntcrchange.doc jn
E. On November 13, 2019, the California Department of Transportation (Ca!trans)
committed to make a financial contribution (FCO) of $1,250,000 towards the
construction of the eastbound off -ramp widening portion of the PROJECT, and
F The remaining PROJECT cost, aside from AUTHORITY project management
costs and the abovementioned Caltrans FCO, now is estimated at $13,570,600,
which shall be funded with 50 5% Development Share funds and 49 5% Public
Share funds, as defined by AUTHORITY's Nexus Study and the Measure 12010-
2040 Strategic Plan, and
G The PARTIES desire to amend the AGREEMENT, and its Attachment A, to
redefine their respective funding responsibilities based on the revised PROJECT
costs and to provide a new, updated, estimated schedule for completion of the
PROJECT
IT IS THEREFORE MUTUALLY AGREED TO AMEND THE AGREEMENT
AS FOLLOWS:
1 Section III. C of the AGREEMENT is amended in its entirety to read as follows
To contribute towards the Planning, Environmental, PS&E, ROW, Construction
and Project Closeout phases of the PROJECT cost an amount not to exceed
$6,717,447, as shown in Attachment A The actual cost of specific phase may
ultimately vary from the estimates provided in Attachment A, however, under no
circumstances is the total combined AUTHORITY contribution to exceed
$6,717,447 without an amendment to this Agreement
2 Section 11I J of the AGREEMENT, is amended in its entirety to read as follows
To provide CITY an opportunity to review and comment on the Planning,
Environmental, PS&E, ROW, and Construction documents. For construction
change orders, the construction change order documents submitted to
AUTHORITY by contractors performing construction work on the PROJECT
will be forwarded to CITY for review and comment
3 Section IV A of the AGREEMENT is amended in its entirety to read as follows.
To reimburse AUTHORITY for the actual costs incurred estimated at $6,853,153
towards the Planning, Environmental, PS&E, ROW, Construction and Project
Closeout phases of the PROJECT cost and $330,000 for AUTHORITY project
management for a total amount not to exceed $7,183,153, as shown in Attachment
A. The actual cost of a specific phase may ultimately vary from the estimates
provided in Attachment A, however, under no circumstances is the total combined
CITY contribution to exceed $7,183,153 or AUTHORITY project management
costs to exceed $330,000 without an amendment to this Agreement
17 1001603 1
4 Section IV of the AGREEMENT is amended by the addition of Subsection G
which shall read as follows
To provide permits, inspections, reviews, and oversight at no cost to
AUTHORITY or to consultants and contractors contracted by AUTHORITY to
work on the PROJECT
5 Section V.R of the AGREEMENT is amended in its entirety to read as follows
Any notice or other communication required, or which may be given, pursuant to
this Agreement, shall be in writing. Any such notice shall be deemed delivered (i)
on the date of delivery in person, (ii) five (5) days after deposit in first class
registered mail, with return receipt requested, (iii) on the actual delivery date if
deposited with an overnight courier, or (iv) on the date sent by facsimile, if
confirmed with a copy sent contemporaneously by first class, certified, registered
or express mail, in each case properly posted and fully prepaid to the appropriate
address set forth below, or such other address as a Party may provide notice in
accordance with this section
If to AUTHORITY
If to CITY•
Paula Beauchamp
Director of Project Delivery
1170 West Third Street, Second Floor
San Bernardino, CA 92410-1715
Telephone (909) 884-8276
City Clerk
City of Redlands
35 Cajon Street
P 0 Box 3005 (mailing)
Redlands, CA 92373
jdonaldson@cityotredlands.org
cityotredlands.org
(909) 798-7531
6 Attachment A to the AGREEMENT is amended and replaced in its entirety with
Attachment A to this AMENDMENT, which is attached to and made a part of
this AMENDMENT
7 PARTIES understand that the PROJECT cost provided in this AMENDMENT is
an estimate and there is a potential for cost increases or decreases If a cost
increase becomes apparent, PARTIES agree to work in good faith to amend the
AGREEMENT
8 All other terms and conditions of the AGREEMENT shall remain in full force and
effect
3
17 1001603 1
9 This AMENDMENT is deemed to be Included and made part of the
AGREEMENT
10 This AMENDMENT is effective upon execution by AUTHORITY
17 1001603 1
-SIGNATURES ON FOLLOWING PAGE
4
SIGNATURE PAGE TO
AMENDMENT NO. 1 TO COOPERATIVE AGREEMENT NO 17-1001603
BETWEEN
SAN BERNARDINO COUNTY TRANSPORTATION AUTHORITY
and CITY OF REDLANDS
SAN BERNARDINO COUNTY CITY OF REDLANDS
TRANSPORTATION AUTHORITY
By
Darcy McNaboe
President, Board of Directors
Date
Y
aul W Foster
Mayor, City of Redlands
Date fcli 6 P
APPROVED AS TO FORM APPROVED AS TO FORM
By By
Juanda L Daniel Da ie McHugh
Assistant General Counsel City Attorney
CONCURRENCE
ATTEST
By By
Jeffery Hill
Procurement Manager
5
17-1001603 1
Je/ e Donaldson
ity Clerk
Attachment A
PROJECT DESCRIPTION
The project funding is based on a design layout that adds two lanes each on the
westbound and eastbound off -ramps, adds a northbound right -turn lane to eastbound on-
ramp, and adds a southbound right -turn lane to the westbound on-ramp
PROJECT FUNDING TABLE
Public Share. 49 5%
Nexus Development Impact Fee Share (DIF or "Local Share") 50 5%
Caltrans Financial Contribution (FCO) Lump Sum $1,250,000
*Project Cost is based on 20I9's Authority's Estimate At Completion and 65% Engineer s Estimate
**Public Shan. will be funded with MCasun, 1 Valley Fru.way Interchange fund
***Caltrans FCO will be available m fiscal year 2020:2021 upon execution of a separate cooperative
agreement bctwcen Authority and Caltrans
PROJECT SCHEDULE
Milestones
Project Cost*
Public Share**
DIF
Caltrans FCO***
Planning,
Environmental,
Design, and Right-
of-way
$1,920,600
$950,697
$969,903
$0
Construction
Manag.ement
$1,500,000
$742,500
$757,500
$0
Construction Capital
$10,900,000
$4,776,750
$4,873,250
$1,250,000
Landscape
Maintenance (EEP)
$500,000
$247,500
$252,500
$0
Project Management
$330,000
$0
$330,000
$0
$15,150,600
56,717,447
$7,183,153
$1,250,000
*Project Cost is based on 20I9's Authority's Estimate At Completion and 65% Engineer s Estimate
**Public Shan. will be funded with MCasun, 1 Valley Fru.way Interchange fund
***Caltrans FCO will be available m fiscal year 2020:2021 upon execution of a separate cooperative
agreement bctwcen Authority and Caltrans
PROJECT SCHEDULE
Milestones
Estimated Completion Date (Actual)
Environmental Approval
(February 2019)
PS&E Approval
December 2020
Construction Contract Award
April 2021
Complete for Beneficial Use
March 2022
6
17-1001603-1