HomeMy WebLinkAboutContracts & Agreements_97-2013_CCv0001.pdf PUBLIC WORKS CONSTRUCTION CONTRACT
This Public Works Construction Contract ("Contract") made and entered into this 21st day of
May 2013, by and between the City of Redlands, a municipal corporation organized and existing
under the laws of the State of California, (hereinafter "City"), and Davis Electric, Inc.
(hereinafter "Contractor"). City and Contractor are sometimes individually referred to herein as a
"Party" and,together, as the "Parties."
In consideration of the mutual promises contained herein, City and Contractor agree as follows:
1. SCOPE OF WORK: Contractor shall furnish all materials and perform all of the work
for the following: Water Distribution SCADA System Upgrade, complete all items as
required by the Contract Documents (as herein defined) and Specifications for City's
WATER DISTRIBUTION SCADA SYSTEM UPGRADE, Project No. 71305.
2. THE CONTRACT SUM: City shall pay Contractor the sum of $2,563,128.00 as
consideration for its performance of the Work in accordance with the terms and
conditions set forth in the Contract Documents. Pursuant to Public Contract Code Section
22300, Contractor has the option to deposit securities with an escrow agent as a substitute
for retention of earnings requirement to be withheld by City pursuant to an escrow
agreement as set forth in the Public Contract Code Section 22300,
3. TIME FOR COMPLETION: The Work shall be completed within Three Hundred
(300) calendar days from and after the date of the delivery to Contractor of a written
Notice to Proceed by City.
4. LIQUIDATED DAMAGES: Contractor's failure to complete the work within the time
allowed will result in damages being sustained by City. Such damages are, and will
continue to be, impracticable and extremely difficult to determine. Accordingly,
Contractor shall pay to City, or have withheld from monies due to Contractor, the sum of
One Thousand Dollars ($1,000) for each consecutive calendar day in excess of the
specified time for completion of Work.
Execution of the Contract shall constitute agreement by City and Contractor that One
Thousand Dollars ($1,000) per day is the estimated damage to City caused by the failure
of the Contractor to complete the Work within the allowed time. Such sum is for
liquidated damages and shall not be construed as a penalty, and may be deducted from
payments due Contractor if such delay occurs.
5. CONTRACT DOCUMENTS: This Contract includes all of the Contract documents set
forth herein where applicable, to wit; Notice Inviting Bids, Instructions to Bidders,
Contractor's Proposal, Bid Bond, Agreement, Performance Bond, Labor and Material
Bond, Plans, General Conditions, Special Conditions, Special Provisions and
Specifications, and any addenda thereto.
6. ATTORNEYS' FEES: In the event any legal action is commenced to enforce or
interpret the terms or conditions of the Contract documents, the prevailing Party in such
CD I
action, in addition to any costs and other relief, shall be entitled to recover its reasonable
attorneys'fees, including fees for use of in-house counsel by a Party.
7. RESOLUTION OF CONSTRUCTION CLAIMS: Claims by Contractor in the amount
of$375,000 or less shall be made by Contractor and processed by the City pursuant to the
provisions of Part 3, Chapter 1, Article 1.5 of the Public Contract Code (commencing
with Section 20104). All claims shall be in writing and include the documents necessary
to substantiate the claim. Nothing in subdivision (a) of Public Contract Code Section
20104.2 shall extend the time limit or supersede the notice requirements provided in this
case from filing claims by Contractor.
8, ELIGIBILITY OF CONTRACTOR/SUBCONTRACTOR: Contractor and all of its
subcontractors shall abide by California Public Contract Code, Section 6109, and
California Labor Code Sections 1777.1 and/or 1777.7, and certify that they are not
debarred and are eligible to work on this project.
9. ASSIGNMENT OF AGREEMENT: No assignment by a Party of any rights or interests
under this Contract shall be binding on another Party without the written consent of the
Party sought to be bound.
10. SUCCESSORS AND ASSIGNS: City and Contractor each binds itself and their
respective successors and assigns in respect to all covenants, agreements, and obligations
contained in the Contract Documents.
11. SEVERABILITY: Any provision or part of the Contract documents held to be void or
unenforceable under any law or regulation shall be deemed stricken and all remaining
provisions shall continue to be valid and binding upon City and Contractor.
CD2
IN WITNESS WHEREOF,the parties hereto have executed this Agreement the day and year first
written above.
City of Redlands
(SEAL) (Owner)
By.
Mayor, City o edlands,County of
San Bernardino,California
ATTEST.
Cityderk,&6 of Itedlands
County of San Bernardino, California (SEAL)
Davis Electric, Inc.
Name of Contractor
By:
Signature of Authorized Agent
President
Title
Signature of Authorized Agent(if necessary)
Title
761 461
Contractor's License No.
CD3
WORKER'S COMPENSATION INSURANCE CERTIFICATION
Description of Contract: City of Redlands
Municipal Utilities&Engineering Department
Water Distribution SCADA System Upgrade Project
Labor Code Section 3700,provides, in part that:
"Every employer except the State, shall secure the payment of compensation in one or more of
the following ways:
(a) By being insured against liability to pkv compensation in one or more insurer
Z:�
duly authorized to write compensation insurance in this State.
(b) By securing from the Director of Industrial Relations a certificate of consent to
self-insure, either as an individual employer, or as one employer in a group of
employers which may be given upon furnishing proof satisfactory to the Director
of Industrial Relations of ability to self-insure and to pay any compensation that
may become due to his or her employees.
I am aware of the provisions of Section 3700 of the Labor Code which requires every employer to be
insured against liability for worker's compensation or to undertake self-insurance in accordance with the
provisions of that Code, and I will comply with such provisions before commencing the performance of
the work of this contract. (Labor Code section 186 1)
Dated this. day of 2013.
Davis Electric, Inc.
(Contractor)
(Signature)
President
(Official Title)
(SEAL)
(Labor Code Section 1861 provides that the above certificate must be signed and filed by the Contractor with
the Owner prior to performing the work of the contract.)
CD4
BOND NUMBER 024049279
EXECUTED IN TRIPLICATE PREMIUM: $25,036.00
FAITHFUL PERFORMANCE BOND
Whereas, the City of Redlands ("City"), State of California, and Davis Electric, INC.
(hereinafter designated as "Principal") have entered into an agreement dated May 21st, 2013
("Agreement") whereby Principal agrees to install and complete certain public improvements
(the "Work"), which said Agreement is identified as Water Distribution SCADA System
Upgrade, Project No. 71305 and is hereby referred to and made a part hereof; and
*THE OHIO CASUALTY INSURANCE COMPANY
Whereas, said Principal is required under the terms of the Agreement to furnish a bond
for the faithful performance of the Agreement, now, therefore, we, the Principal and
, as Surety, are held and firmly bound unto the City in the penal sum of
TWO MILLION FIVE HUNDRED SIXTY-THREE ** Dollars ($ 2,563,128.00 lawful money of the
United States, for the payment of which sum we bind ourselves, and our heirs, successors,
executors and administrators, I*ointly and severally, firmly by these presents.
**THOUSAND ONE HUNDRED TWENTY-EIGHT AND NO1100
The condition of this obligation is such that if the above bounded Principal, his or its
heirs, executors, administrators, successors or assigns, shall in all things stand to and abide by,
and well and truly keep and perform the covenants, conditions and provisions in the Agreement
and any alteration thereof made as therein provided, on his or its part, to be kept and performed
at the time and in the manner therein specified, and in all respects according to their true intent
and meaning, and shall faithfully fulfill the one-year guarantee of all materials and workmanship,
and shall defend, indemnify and save harmless the City and its elected officials, officers, agents
and employees,as therein stipulated, then this obligation shall become null and void;otherwise it
shall be and remain in full force and effect.
As a part of the obligation secured hereby and in addition to the face amount specified
therefor, there shall be included costs and reasonable expenses and fees, including reasonable
attorneys' fees, incurred by the City in successfully enforcing such obligations, all to be taxed as
costs and included in the judgment rendered.
As a condition precedent to the satisfactory completion of the Agreement, the above
obligation shall hold good for a period of one (1) year or longer if required by the Agreement
after the acceptance of the work by the City, during which time if the Principal shall fail to make
full, complete, and satisfactory repair and replacements and totally protect the City from loss or
damage made evident during this period from the date of completion of the Work, and resulting
from or caused by defective materials or faulty workmanship, the above obligation in penal sum
thereof shall remain in full force and effect. The obligations of Surety hereunder shall continue
so long as any obligation of the Principal remains.
Whenever the Principal shall be, and is declared by the City to be, in default under the
Agreement, the City having performed the City obligations thereunder, the Surety shall promptly
remedy the default, or shall promptly, at the City's option:
1. Complete the Agreement in accordance with its terms and conditions; or
2. Obtain a bid or bids for completing the Agreement in accordance with its terms
and conditions, and upon determination by Surety of the lowest responsive and
responsible bidder, arrange for a contract between such bidder and the City, and
CD
make available as work progresses sufficient funds to pay the cost of completion
of the Work less the balance of the Agreement price,but not exceeding, including
other costs and damages for which Surety may be liable hereunder,the amount set
forth above. The term "balance of the Agreement price," as used in this
paragraph, shall mean the total amount payable to the Principal by the City under
the Agreement and any modifications thereto, less the amount previously properly
paid by the City to the Principal.
Surety expressly agrees that the City may reject any contractor or subcontractor which
may be proposed by Surety in fulfillment of its obligations in the event of default by the
Principal.
Surety shall not utilize the Principal in completing the Agreement nor shall Surety accept
a bid from the Principal for completion of the Work if the City, when declaring the Principal in
default, notifies Surety of the City's objection to the Principal's further participation in the
completion of the Work.
No right of action shall accrue on the bond to or for the use of any person or corporation
other than the City named herein or the successors or assigns of the City. Any suit under this
bond must be instituted within the applicable statute of limitations period.
The said Surety, for value received, hereby stipulates and agrees that no change,
extension of time, alteration or addition to the terms of the agreement or to the work to be
performed thereunder or the Specifications accompanying the same shall in any way affect its
obligations on this bond, and it does hereby waive notice of any such change, extension of time,
alteration or addition to the terms of the agreement or to the work or to the specifications.
No final settlement between the City and the Principal shall abridge the right of any
beneficiary hereunder whose claim may be unsatisfied.
The Principal and Surety agree that if the City is required to engage the services of any
attorney in connection with the enforcement of this bond, each shall pay the City's reasonable
attorneys' fees incurred,with or without suit,in addition to the above sum.
The Surety hereby stipulates and agrees that no change, extension of time alteration or
addition to the terms of the Agreement or to the Work to be performed thereunder or the
specifications accompanying the same shall in any way affect its obligations on this bond, and it
does hereby waive notice of any such change, extension of time, alteration or addition to the
terms of the agreement or to the work or to the specifications.
In witness whereof, this instrument has been duly executed by the Principal and Surety
above named,on MAY 22, 201 3.
(SEAL) (SEAL)
DAVIS ELECTRIC, INC. THE OHIO CASUALTY INWRANCE COMPANY
(Contractor) {S
�11- IV
(Signature)
(Signatute) MICHAEL U. TONG, ATTOR 'EYLTN- 'ACI
CD