HomeMy WebLinkAboutContracts & Agreements_146-2013_CCv0002.pdf TAKEOVER AGREEMENT
THIS TAKEOVER AGREEMENT ("Agreement")is made and entered into this 16I'day of
July 2013 ("Effective Date")by and between the City of Redlands("Obligee") and The Ohio
Casualty Insurance Company("Surety"). The Obligee and the Surety are sometimes
individually referred to herein as a"Party"and, together, as the"Parties."
RECITALS
WHEREAS, Christiansen Pipeline, Inc. ("Principal") heretofore entered into a Contract
("Contract") awarded on or about October 2, 2012, with the Obligee for the
construction of the Obligee's Brookside Avenue Water Pipeline Replacement Project,
Project No. 71234, ("Project"). A true and correct copy of the Contract for the Project is
attached hereto as Exhibit"A" and incorporated herein by this reference; and
WHEREAS, the Surety issued a Performance Bond No. 024045047 ("Bond") in
connection with the Project; and
WHEREAS, the Obligee certifies to the Surety that the initial Contract amount was Two
Hundred Eighty Nine Thousand Six Hundred Sixty Dollars ($289,660) and that the adjusted
Contract amount as of the Effective Date of this Agreement is Three Hundred One Thousand
Three Hundred Seventy Seven and Seven One Hundredths Dollars ($301,377.07) as there was
one change order submitted by the Principal and approved by the Obligee in the amount of
Eleven Thousand Seven Hundred Seventeen and Seven One-Hundredths Dollars ($11,717.07).
The Obligee further represents to the Surety that One Hundred Sixty Seven Thousand One
Hundred Forty Nine and Seventy Two One Hundredths Dollars ($167,149.72) was paid to the
Principal pursuant to the Contract and that the balance of the Contract funds currently held by
the Obligee is One Hundred Thirty Four Thousand Two Hundred Twenty Seven and Thirty
Five One Hundredths Dollars($134,227.35); and
WHEREAS, in entering into this Agreement, the City and the Surety each reserve their
respective rights to verify the accuracy of the Contract, change order, and payment amounts
identified in this Agreement; and
WHEREAS, although the Principal asserts it performed its last labor on the Contract on or
about April 4, 2013,the City asserts the Principal performed its last labor on the Contract on or
about March 20,2013; and
WHEREAS, on or about April 16,2013 the Obligee terminated the Principal as a result of
the Principal's default under the Contract; and
WHEREAS, the Obligee desires to effect and expedite the completion of the said Contract
in order to preserve the work in place and to avoid the delays and inconvenience of reletting;
and
WHEREAS, the Surety is willing to exercise its election to complete or to procure the
J:1,ca\djm\Agreements\Takeover Agreement(FINAL).6.26,13.doex
completion of the Contract as a measure of cooperation with the Obligee provided the Surety
can be assured that in doing so, it will receive the Contract payments as hereinafter set forth;
NOW THEREFORE, in consideration of the mutual promises set forth herein, and for such
other good and valuable consideration, the receipt and sufficiency of which are hereby
acknowledged, the Parties agree as follows:
AGREEMENT
1. The recitals set forth above are incorporated herein.
2. The work remaining to be completed ("Remaining Work") on the Project under the
Contract, and this Agreement, shall be derived based on the work in place, valued at the unit
and/or lump sum prices set under the Contract, and the Surety shall be responsible for all
Remaining Work set forth in the Contract not otherwise completed by the Principal, as set forth
in the Principal's percentage of completion provided to the Obligee. The Obligee agrees that
Exhibit "B,"which is attached hereto and incorporated herein by this reference, is a complete
list of the Remaining Work which must be corrected or completed by Surety to finish and close
out the Contract. Except to the extent provided in this Agreement, the Obligee and the Surety
shall have all rights, obligations and responsibilities under the Contract with respect to each
other, to the same extent and effect as if the Surety had executed the Contract initially instead
of the Principal, and the Principal had not defaulted.
3. The Obligee acknowledges that the Surety has a prior equitable right to receive all
Contract proceeds upon completion of the Remaining Work covered by the Contract.
Accordingly,the Obligee shall pay to the Surety,or its designee, all amounts(if any)to be paid
by the Obligee to Principal under the Contract at the times and under the procedures according
to terms and conditions of the Contract. The Obligee represents that as of Effective Date of
this Agreement the initial Contract amount and the one change order in the amount of Eleven
Thousand Seven Hundred Seventeen and Seven One-Hundredths Dollars($11,717,07),totaling
Three Hundred One Thousand Three Hundred Seventy Seven and Seven One Hundredths
Dollars ($301,377.07), has been decreased by payments totaling One Hundred Sixty Seven
Thousand One Hundred Forty Nine and Seventy Two One Hundredths Dollars ($167,149.72)
The Surety agrees to expend such of its own funds as may, from time to time, be necessary to
pay for completion of the Remaining Work and to pay appropriate claims; provided, however,
that the Surety's performance and payment obligation, over and above the amount paid by the
Obligee and received by the Surety under this Agreement, shall in no event increase the
Surety's legal obligations required under the Bond. Nothing in this Agreement constitutes a
waiver or an increase in the liability of the Surety under the Surety's Bond.
4. The Obligee has and will assert claims for liquidated or delay damages, as well as
back charges for improperly completed work by the Principal, which may result in a decrease
in, or withholding from, any amount owed under a progress payment or retention that is
remaining to be paid under the Contract. The Obligee reserves all rights to pursue its rights
and remedies, including back charges and liquidated damages, under the Contract or law. The
Remaining Contract Balance shall be increased or decreased by the value of any proposed
2
1:\ca\djm\Agreements\Takeover Agreement(FINAL).6.26.13.docx
change orders subsequently approved by the Obligee. Progress payments, and final payment,
including the payment of all accrued retention,under the Contract and this Agreement, shall be
subject to the Obligee's quantification and acceptance of the Remaining Work provided under
the Contract and satisfaction of all other contractual requirements imposed by the Contract as a
condition precedent to such final payment. The Surety disputes the alleged claims, if any, that
the Obligee is asserting for liquidated or delay damages, as well as back charges for alleged
improperly completed work by the Principal and expressly reserves all rights, whether at law
or in equity, that it may have against the Obligee including but not limited to the rights of its
Principal against the Obligee.
5. Surety intends to relet the completion of the Remaining Work covered by the
Contract (Exhibit "A") for the Project to All American Asphalt, a licensed Contractor
("Completion Contractor"). The Obligee consents to Completion completing said Remaining
Work. The Completion Contractor shall be the Surety's representative with regard to
completion of the Remaining Work. All documents pertaining to pay estimates, progress and
final payments shall be sent to:
The Ohio Casualty Insurance Company c/o Jim Rumpf
Sr. Surety Claims Spec, IV
9450 Seward Road
Fairfield,OH 45014
Jaines.Rumpf@LibertyMutual.com
Phone: (317) 883-1006
6. In the event a dispute arises between the Obligee and the Completion
Contractor, or if the Completion Contractor is in default under the terms of the Contract, the
Obligee shall give the Surety written notice thereof within fifteen (15) calendar days of such
default.
7. The Surety, who will have no employees or representatives on the jobsite, shall
have no obligation to furnish any insurance under the Contract. The Completion Contractor
shall provide insurance coverage equivalent to that required under the Contract.
8. It is understood and agreed that the Surety,by entering this Agreement, is not acting
as a contractor,but instead in its capacity as a performance bond surety,
9. This Takeover Agreement is made without prejudice to either Party's rights to
prosecute any claim or claims which arise from performance of the Contract or this
Agreement. The Parties reserve the right to prosecute any of said claims for payment of all
sums due or to become due for performance under the Contract or this Agreement, except as
modified herein.
10. The time of performance shall be fifteen (15) calendar days from issuance of a
written notice to proceed from the Obligee to Completion Contractor. Time is of the essence
in this Agreement. The Surety acknowledges that liquidated damages are accruing based on the
original Project completion date of February 17, 2013. The Obligee agrees that liquidated
3
Lca\djrmAgreements\Takeover Agreement(FINAL).6.26,13.docx
damages shall step accruing upon the issuance of the notice to proceed from the Obligee to the
Completion Contractor.. If the Completion Contractor fails to complete the Remaining Work
within the above stated time,the Parties agree that the{obligee has the right to assert liquidated
damages pursuant to the terms of the Contract.
11. The Obligee agrees that it will not acknowledge or honor any claim or charges
against the Remaining Contract Balance by any alleged assignees, successors, creditors, or
transferees of Principal,or any other person or entity making claim to the Remaining Contract
Balance, withoutthe consent of the Surety, except by order of a court of competent
jurisdiction after due notice to the Surety.
12. The Obligee agrees that under no circumstances shall the Surety's liability exceed
the penal sum of its Band,and that all payments made by the Surety to any person or entity on
account of the work covered by the Contract shall be deemed to be payment under the Surety's
Bond and shall reduce the penal sum of the Bond in an equal amount. The Surety shall not
indebt the Obligee to any third party to pay for work in excess of the penal'sum of the Bond.
1 . In consideration of the work contemplated under the Contract and the Project, the
Obligee hereby expressly subro ates the Surety to, and>assigns, conveys, sets over, and
transfers to the Surety, any and all claims, causes of actions, interests, or demands that the
Obligee has, had, or may ever be entitled to assert'against Principal in connection with the
Contract or Project, and expressly agrees that the Surety may pursue such rights, claims,
interests, causes of actions, demands, and/or claims in any manner the Surety deems
appropriate, including but not limited to matters pending in any bankruptcy preceeding, to the
extent that the Surety in its sole discretion deems advisable.
14. The Parties agree to cooperate fully with each other to the end that the Project may
be completed as efficiently and quickly as reasonably possible under the circumstances.
15. The parties and their signatories hereto`' warrant that each'has the power and
authority to execute this Agreement. The parties agree that if the Surety certifies any claim
arising out of or relating to the Contract,the Project,or this Agreement, such certification will
be deemed properly certified if made by an officer of the Surety. The Parties have voluntarily
this Agreement based on their independent investigations.
1 . The provisions of this Agreement shall be applied and interpreted in a manner
consistent with each other so as to carry out the purposes and intent of the Parties, but if for
any reason any provision is unenforceable or invalid;:such provision shall be deemed severed
from this Takeover Agreement and the remaining provisions shall be earned out with the same
force and effect as if the severed portion had not been a part of this Agreement.
17. This Agreement shall not be construed to waive, limit, alter, or amend any of the
Surety's obligations,rights,defenses,or liabilities under the Surety's Bond..
1 . This Agreement constitutes the entire agreement between the Parties and supersedes
any and all prior agreements, arrangements, and/or understandings by and between the Parties
with respect to the subject matter hereof.Except as herein:modified,all terms and conditions of
4
1:\caldjm\Agreements\T*eover Agreement{FINIAL}.6.26.13.d x
the Contract shall remain unchanged and in fall force and effect.
19. This Agreement shall extend to and be binding upon the Parties and their
respective successors and assigns. No rights shall accrue hereunder to or for the use of any
other person, firm, corporation, or governmental entity other than the Parties and their
respective successors, assigns, and reinsurers.
20. The Surety agrees that it is not released from its Labor and Material Bond naming
the Obligee and the Principal in the penal sum of$289,660. Such payment bond shall extend
to claimants who perform work and/or supply materials to the Project after on or about March
20, 2013, the last day the Principal was on the Project.
21. The Surety reserves to itself all claims of any kind that Principal could have brought
against the Obligee pursuant to the Contract.
22. In the event of any action to enforce or interpret the terms or conditions of this
Agreement, the prevailing Party shall, in addition to, its costs, and any other relief, be entitle
to recover its reasonable attorneys' fees, including fees for use of in-house counsel by a Party.
23. This Agreement is made, executed and performed in San Bernardino, California
and shall be governed by and construed in accordance with the laws of the California.
5
1:\ca\djm\Agreements\Takeover Agreement(FINAL).6.26.I 3.docx
IN WITNESS WHEREOF, the Parties have executed this Agreement as of the date first
written above.
City of Redlands The Ohio Casualty Insurance Company
BY:
Pete Aguilar, Mayor Jr es Rumpf, Sr. ety Claims
Specialist IV
ATTEST:
r
Sam Irwin, CAy Clerk
6
I:\ca\djm\Agreements\Takeover Agreement(FINAL).6.26,I ldocx
C7x1.i. A ' (7?zisifoqy -- )
CITY OF REDLANDS
MUNICIPAL UTILITIES & ENGINEERING
DEPARTMENT
c x : ,
,,.
it
'it- �� .4
• r 4
In
til, id, l r
Ir /4- I .
'Iv Vior
SCS$$
Bid Proposal,Contract Documents and Specifications
For
BROOKSIDE AVENUE WATER PIPELINE
REPLACEMENT PROJECT
Project No. 71234
QskafEssio*
yQti KU Mq4,0 F1.
J
uti 8Ho_C 75646 Ir' ,
* 'ice
`�,g ClYt4! -
lir:* FCALtr`
1111/417)
July 2012
RECYCLED PAPER
(41
ALL AMERICAN ASPHALT
Engineering -Contractors -Asphalt Paving CSTATE
400 East 8 h St.
73A
P.O.Box 2220
Corona,California 92878.2229
Telephone:(961)736-7800 FAX:(961y 136-7640
Serving:Los Angela,Orange,Riverside,and San Bernardino Counties
To: Oates 1r30►2012
CITY OF REDLANDS From: Cody dawryUU t.
35 CAJON STREET Quote Ho. 231
REDLANDS,CA 92373
Phone Fax
We propose to furnish you labor and material in strict accordance with the plans and spedflcations as follows:
BROOKSIDE AVE.RECONSTRUCTION
SANMATEOST. TO ROMA ST.
Ilam No. Description Quantity ISM UnitPrics Total Price Y I
1 1 BROOKSIDE AVE. 1.0 LS 97,854.000 97,854.00
——97,854.00
87,854.00
LI Total Proposal Price: $97,854.00 I
ct t C nw ons:
( 1. LUMP SUM AMOUNT INCLUDES:
2. 5,862.5 SF OF 4"ASPHALT TRENCH PATCH REMOVAL AND REPLACEMENT.
3. 2.978 LF OF ASPHALT HEADER CUT 0"-2".
4. 2"VARIABLE DEPTH COLUMIWNG FULL WIDTH
S. 33,718 SF ASPHALT OVERLAY 2"
S. STRIPING TO BE INSTALLED PER ORIGINAL CONTRACT UMTS.
7. SIDE STREETS-1,883 SF OF 2"ASPHALT OVERLAY
8. BROOKSIDE AVE.TO BE CLOSED TO THRU TRAFFIC DRUING WORKING HOURS.DETOUR WILL
BE PROVIDED.
Quo al Nob: - — -�
Date: — Accepted by: