Loading...
HomeMy WebLinkAboutContracts & Agreements_124-2021REPORT/RECOMMENDATION TO THE BOARD OF SUPERVISORS OF SAN BERNARDINO COUNTY AND RECORD OF ACTION July 27, 2021 FROM BRENDON BIGGS, Director, Department of Public Works — Transportation SUBJECT Cooperative Agreement with the City of Redlands for a Pavement Improvement Project on Wabash Avenue and Other Roads in the Mentone, Redlands, and Yucaipa Areas RECOMMENDATION(S) 1 Approve Cooperative Agreement No 21-576 with the City of Redlands to construct pavement improvements on Wabash Avenue and Other Roads in the Mentone, Redlands, and Yucaipa areas at an estimated total cost of $3,485,000 2 Authorize the Director of the Department of Public Works to increase San Bernardino County's contribution under the Cooperative Agreement by up to 25 percent (from $3,421,000 to $4,276,250), should costs dictate such an increase (Presenter• Brendon Biggs, Director, 387-7906) COUNTY AND CHIEF EXECUTIVE OFFICER GOALS & OBJECTIVES Ensure Development of a Well -Planned, Balanced, and Sustainable County Pursue County Goals and Objectives by Working with Other Agencies and Stakeholders. FINANCIAL IMPACT Approval of this item will not result in the use of Discretionary General Funding (Net County Cost) The Department of Public Works (Department) is funded by Gas Tax revenue, fee revenue, and other state and local funding The total cost to make the necessary pavement improvements on Wabash Avenue and Other Roads in the Mentone, Redlands, and Yucaipa areas (Project) is estimated to be $3,485,000 The San Bernardino County (County) estimated share cost of $3,421,000 will be funded by the County's Measure I Local Streets Program - San Bernardino Valley Subarea funds The remaining amount of $64,000 will be financed by the City of Redlands (City) local funds Sufficient appropriation and revenue are included in the Department's 2021-22 Road Operations budget and will be included in future recommended budgets (6650002142 34TX1809) BACKGROUND INFORMATION The Project consists of 30 64 miles of pavement reconstruction, mill and overlay, which replaces a portion of the roadway with new asphalt concrete material, and application of oil -based slurry seal and chip seal to the pavements All work for the Project will be done within the existing road rights -of -way and therefore, no additional right-of-way is required for the Project. The Project is primarily in the unincorporated areas of Mentone, Redlands, and Yucaipa, and partially within the City of Redlands (see Exhibit "A" attached to the Agreement for list of the proposed roads), and therefore is of mutual benefit to both Parties This Project has been identified as a priority Item 40 Page 1 of 3 Cooperative Agreement with the City of Redlands for a Pavement Improvement Project on Wabash Avenue and Other Roads in the Mentone, Redlands, and Yucaipa Areas July 27, 2021 based on current pavement condition, amount of truck traffic carried, daily traffic count, and other criteria established under the Department's Pavement Preservation Program The Project meets the County and Chief Executive Officer's goals and objectives by jointly working with the City in an effort to ensure the development of a well -planned, balanced, and sustainable County by constructing pavement improvements on various roads in the Mentone, Redlands, and Yucaipa areas, with the purpose of providing improved pavement surfaces on which motorists travel In accordance with the terms of the Agreement, the County will serve as the lead agency for the Project design, utility relocation, construction, construction engineering, inspection, and California Environmental Quality Act compliance, and will provide the City with the plans and specifications prior to the Project construction for the City's review and approval In addition, the City agrees to provide the County a no -cost permit for work in the City's right-of-way, and pay its share of the Project cost, up to $80,000, which is the City's estimated share of $64,000, plus 25 percent increase over the estimated amount, should actual Project costs dictate such an increase The City will provide a representative to discuss and/or resolve issues that may arise during the construction of the Project. The County's share of the Project cost shall not exceed $4,276,250, (which is 25 percent increase over County's estimated share of $3,421,000) The County and City's shares of the Project cost shall not exceed the Agreement's stated amounts absent a written and approved amendment to the Agreement. The Project construction is anticipated to commence in the Spring of 2022 Unless the Agreement is terminated pursuant to terms outlined in the Agreement, the Agreement shall terminate upon completion of the Project and final payment by the City, or on December 31, 2026, whichever occurs first. The City approved the Agreement on July 6, 2021 PROCUREMENT Not applicable REVIEW BY OTHERS This item has been reviewed by County Counsel (Suzanne Bryant, Deputy County Counsel, 387-5455) on June 9, 2021, Finance (Jessica Trillo, Administrative Analyst, 387-4222) on July 6, 2021, and County Finance and Administration (Matthew Erickson, County Chief Financial Officer, 387-5423) on July 12, 2021 Item 40 Page2of3 Cooperative Agreement with the City of Redlands for a Pavement Improvement Project on Wabash Avenue and Other Roads in the Mentone, Redlands, and Yucaipa Areas July 27, 2021 Record of Action of the Board of Supervisors San Bernardino County APPROVED (CONSENT CALENDAR) Moved Dawn Rowe Seconded Col Paul Cook (Ret ) Ayes Col Paul Cook (Ret ), Janice Rutherford, Curt Hagman, Joe Baca, Jr Abstained Dawn Rowe Lynna Monell, CLERK OF THE BOARD BY DATED IJtiIy 27, 202 cc LA PW/Trans- Srirajan w/agree Contractor- C/O PW/Trans w/agree File- w/agree 07/29/2021 Item 40 Page 3 of 3 THE INFORMATION IN THIS BOX IS NOT A PART OF THE CONTRACT AND IS FOR COUNTY USE ONLY SAN BERNARDINO COUNTY Public Works Department Contract Representative Telephone Number Project Contractor Contractor Representative Telephone Number Contract Term Original Contract Amount Amendment Amount Total Contract Amount Cost Center Contract Number crl LP SAP Number Sundaramoorthy (Sri) Srirajan, P E , Engineering Manager 387-8166 Wabash Avenue and Other Roads City of Redlands Goutam Dobey, Engineering Manager 798-7524 Expiration 12/31/2026 $64,000 (not -to -exceed $80,000) $0 Not -to -Exceed $80,000 6650002142 40608842 34TX1809 IT IS HEREBY AGREED AS FOLLOWS• WHEREAS, the County of San Bernardino (hereinafter referred to as "COUNTY") and the City of Redlands (hereinafter referred to as "CITY"), also are each referred to herein as "Party" and collectively as "Parties", desire to cooperate and jointly participate in a project to rehabilitate various pavements in the Mentone and Redlands areas, see Exhibit "A" for list of proposed roads, which is attached hereto and incorporated herein by this reference, (hereinafter referred to as "PROJECT"), and WHEREAS, the PROJECT is primarily within the jurisdiction of the COUNTY and partially in the jurisdiction of the CITY, and will be of mutual benefit to the Parties, and WHEREAS, the PROJECT consists of 30 64 miles of pavement improvements on various roads in the Redlands and Mentone areas, and WHEREAS, California Streets and Highways Code sections 1685 and 1803 authorize CITY to contract with COUNTY for the maintenance, construction or repair of CITY streets and roads, if the legislative body of CITY determines that it is necessary for the more efficient maintenance, construction, or repair of its streets and roads, and Standard Contract Page 1 of 13 WHEREAS, the legislative body of CITY determines that it is necessary for the more efficient maintenance, construction, or repair of its streets and roads to contract with COUNTY for the PROJECT, and WHEREAS, the total PROJECT cost is estimated to be $3,485,000; and WHEREAS, COUNTY's share of PROJECT cost is estimated to be $3,421,000 and the CITY's share of PROJECT cost is estimated at $64,000 as more particularly set forth in Exhibit "B", which is attached hereto and incorporated herein by this reference, and WHEREAS, the above -described costs are proportioned based on the work to be performed in each Party's jurisdiction, and WHEREAS, COUNTY and CITY desire to set forth the responsibilities and obligations of each as they pertain to such participation, and to the design, construction, and funding of the proposed PROJECT 1 0 COUNTY AGREES TO 1 1 Act as the Lead Agency in the design, utility relocation, construction, construction engineering, inspection, and California Environmental Quality Act (CEQA) compliance (Public Resources Code section 21000 et. seq ) of the PROJECT Right -of -Way services are not anticipated and therefore, are not included in this agreement. 1 2 Provide plans and specifications for the PROJECT for CITY's review and approval 1 3 Arrange for relocation of all utilities which interfere with construction of the PROJECT, within the entire PROJECT limits, pursuant to Paragraph 3 9 below 1 4 Construct the PROJECT by contract in accordance with the plans and specifications of COUNTY, which will be reviewed and approved by CITY prior to construction 1 5 Obtain a no -cost permit from CITY for work performed within the CITY's right-of-way 1 6 Advertise, award, and administer the construction of the PROJECT, in accordance with the provisions of the California Public Contract Code applicable to COUNTY, and initially fund the PROJECT construction with CITY reimbursing COUNTY for CITY's share of the PROJECT cost. 1 7 Require its contractor to maintain and to comply throughout the term of any contract awarded by COUNTY with the insurance requirements described in County Policy Numbers 11-07 and 11- 07SP 1 8 Provide adequate inspection of all items of work performed under the construction contract with COUNTY's contractor or subcontractors for the PROJECT and maintain adequate records of inspection and materials testing for review by CITY COUNTY shall provide copies of any records of inspection and materials testing to CITY within ten (10) days of COUNTY's receipt of written demand from CITY for such records. Copies of records shall be included as a PROJECT cost. 1 9 Upon PROJECT completion, calculate actual COUNTY and CITY PROJECT share percentages based on the cost for final work performed in each Party's jurisdiction, which shall include any changes made within the COUNTY and/or CITY jurisdiction as provided in this Agreement. 1 10 Based on the COUNTY percentage calculated pursuant to Paragraph 1 9, pay its share of the PROJECT cost. The PROJECT cost shall include cost of design, utility relocation, construction, construction engineering, inspection, CEQA compliance and COUNTY overhead COUNTY's share of PROJECT cost is estimated to be $3,421,000 and shall not exceed $4,276,250 (25% increase over the COUNTY's PROJECT cost estimate) absent a written amendment to this Agreement pursuant to Paragraph 3 17 below 1 11 Submit to the CITY an itemized accounting of actual PROJECT costs incurred by COUNTY and an invoice Said invoice shall set forth all actual PROJECT costs incurred by COUNTY, together with adequate documentation of said expenditures CITY's share of PROJECT costs is estimated to be $64,000 and shall not exceed $16,000 (25% increase over the PROJECT cost estimate) for unanticipated PROJECT cost, bringing a possible total amount not -to -exceed $80,000 1 12 Include compliance with any applicable requirements of CEQA, as well as completing the required CEQA documentation 2 0 CITY AGREES TO. 2 1 Review and approve the plans and specifications of the PROJECT Revised 5/12/21 Page 2 of 13 2 2 Provide a no -cost permit to the COUNTY for COUNTY's work in CITY's right-of-way 2 3 Provide a qualified representative who shall have the authority to discuss and attempt to resolve issues concerning the PROJECT with the COUNTY 2 4 Based on percentage calculated pursuant to Paragraph 1 9 above, pay CITY's share of the PROJECT cost. The PROJECT cost shall include design, utility relocation, construction, construction engineering, inspection, CEQA compliance and COUNTY overhead CITY's share of the PROJECT cost is currently estimated to be $64,000 and shall not exceed $16,000 (25% increase over the PROJECT cost estimate) for unanticipated PROJECT cost, bringing a possible total amount not -to -exceed $80,000 2 5 Pay COUNTY within thirty (30) days after receipt of the itemized invoice as set forth in Paragraph 1 11 of the Agreement. 3 0 IT IS MUTUALLY AGREED 3 1 Except for activities that are impossible to perform during the construction phase of PROJECT, before, during and after CITY's acceptance of completed PROJECT, the CITY shall be responsible for performing any and all work (including, but not limited to, maintenance) for CITY streets in the PROJECT limits that are in the CITY incorporated area 3 2 COUNTY agrees to indemnify and hold harmless CITY and its officers, employees, agents, and volunteers from any and all claims, actions or losses, damages, and/or liability resulting from the COUNTY's negligent acts or omissions which arise from the COUNTY's performance of its obligations under this agreement. 3 3 CITY agrees to indemnify, defend (with counsel approved by COUNTY) and hold harmless the COUNTY and its officers, employees, agents and volunteers from any and all claims, actions, losses, damages and/or liability arising out of its obligations under this agreement. 3 4 In the event the COUNTY and/or CITY is found to be comparatively at fault for any claim, action, loss or damage which results from their respective obligations under the Agreement, the COUNTY and/or CITY shall indemnify the other to the extent of its comparative fault. 3 5 In the event of litigation arising from this Agreement, each Party to the Agreement shall bear its own costs, including attorney(s) fees. This Paragraph shall not apply to the costs or attorney(s) fees relative to Paragraphs 3.2, 3 3 and 3 4 indemnification 3 6 COUNTY and CITY are authorized self -insured public entities for purposes of Professional Liability, General Liability, Automobile Liability and Workers' Compensation and warrant that through their respective programs of self-insurance, they have adequate coverage or resources to protect against liabilities arising out of the performance of the terms, conditions or obligations of this Agreement. 3 7 The Parties acknowledge that final PROJECT costs may ultimately exceed current estimates of PROJECT costs. Any additional PROJECT costs resulting from increased bid prices, change orders, or arising from unforeseen site conditions, including Utility relocation (but not from requested additional work by the COUNTY or CITY, which is addressed in Paragraph 3 8 below) over the estimated total of the PROJECT's cost of $3,485,000 (which is the sum of $3,421,000 from COUNTY and $64,000 from CITY) shall be borne by each Party based upon where the work is required (e g whether the work is required in the COUNTY or CITY jurisdiction) 3 8 If either COUNTY or CITY requests additional work that is beyond the scope of the original PROJECT, and not considered by all Parties to be a necessary part of the PROJECT, said work, if approved by both Parties, will be paid solely by the agency requesting the work, unless both Parties agree by written amendment to allocate the cost that is mutually acceptable 3 9 In the case wherein one of the Parties owns a utility that needs to be relocated for the PROJECT and that Party does not have prior rights for that utility, it will be the sole responsibility of that Party to relocate the utility at the Party's cost. This shall not be included as a PROJECT cost. In the case that a utility relocation is determined to be a PROJECT cost based on that utility having prior rights, the relocation of the utility will be included as a PROJECT cost for which the Party will be responsible for funding the work. 3 10 As design progresses, if it is found by COUNTY's Director of Public Works, or the Director's designee, that a cost overrun of more than 25% of the estimated total of the PROJECT costs will occur, COUNTY shall provide CITY notice of this fact and COUNTY and CITY shall endeavor to agree upon an alternative course of action, including amending the amounts and Exhibit B with Revised 5/12/21 Page 3 of 13 revised cost estimates If, after thirty (30) days of COUNTY notice, an alternative course of action is not mutually agreed upon in writing between the COUNTY and CITY, this Agreement shall be deemed to be terminated by mutual consent. 3 11 COUNTY shall notify CITY of the bids received and the amounts thereof In the event that either Party intends to cancel this Agreement based upon the bids or amount thereof, said Party shall notify the other Party at a reasonable time prior to the awarding of a contract to construct the PROJECT to avoid any detrimental reliance by either Party, contractor or potential contractor 3 12 If after opening bids for the PROJECT, it is found that the responsive and responsible low bid amount is 25% or less over the construction cost shown in Exhibit B, COUNTY may award the contract. 3 13 If, upon opening of bids, it is found that the responsive and responsible low bid amount is over 25% more than the construction cost shown in Exhibit B, COUNTY shall not award the contract unless 1) COUNTY receives written permission from the CITY's Director of Public Works or designee, to proceed with the award, and 2) COUNTY's Board of Supervisors approves the award of the construction contract. If the above described conditions are not met, COUNTY and CITY shall endeavor to agree upon an alternative course of action, including re -bidding of the PROJECT If, after thirty (30) days of the bid opening, an alternative course of action is not mutually agreed upon in writing, this Agreement shall be deemed to be terminated by mutual consent. 3 14 Contract Change Order forms will be delivered by fax or email, must be approved and signed by CITY, and returned within two (2) business days The CITY shall not unreasonably withhold approval of change orders If a CITY disapproved or modified change order is later found to be a cost of the PROJECT, then the CITY shall be responsible for any costs, awards, judgments or settlements associated with the disapproved or modified change order 3 15 This Agreement may be cancelled upon thirty (30) days advance written notice of either Party, provided however, that neither Party may cancel this Agreement after COUNTY awards a contract to construct the PROJECT In the event of cancellation as provided herein, including termination pursuant to Paragraphs 3 10, 3 11, and 3 13 above, all PROJECT expenses incurred prior to the effective date of cancellation/termination shall be paid by the Parties based on the calculated percentage share pursuant to Paragraph 1 9 above The Parties recognize and agree that the provisions governing utility relocation and construction are dependent upon the Parties first satisfying CEQA. As provided in this Paragraph, the Agreement may be cancelled with or without cause, before, during and after CEQA review/approval 3 16 Except as provided in Paragraph 3 15, and except for the Parties' operation, maintenance and indemnification obligations contained herein which shall survive termination, this Agreement shall terminate upon completion of the PROJECT and payment of final billing by the CITY for its share of the PROJECT costs 3 17 This Agreement contains the entire agreement of the Parties with respect to subject matter hereof, and supersedes all prior negotiations, understandings or agreements. No supplement, modification, or amendment of this Agreement shall be binding unless executed in writing and signed by both Parties 3 18 This Agreement shall be governed by the laws of the State of California. Any action or proceeding between CITY and COUNTY concerning the interpretation or enforcement of this Agreement, or which arises out of or is in any way connected with this Agreement or the PROJECT, shall be instituted and tried in the appropriate state court, located in the County of San Bernardino, California 3 19 Time is of the essence for each and every provision of this Agreement. 3 20 Since the Parties or their agents have participated fully in the preparation of this Agreement, the language of this Agreement shall be construed simply, according to its fair meaning, and not strictly for or against any Party Any term referencing time, days or period for performance shall be deemed COUNTY work days The captions of the various articles and Paragraphs are for convenience and ease or reference only, and do not define, limit, augment, or describe the scope, content, or intent of this Agreement. 3 21 No waiver of any default shall constitute a waiver of any other default or breach, whether of the same or other covenant or condition No waiver, benefit, privilege, or service voluntarily given or Revised 5/12/21 Page 4 of 13 performed by a Party shall give the other Party any contractual rights by custom, estoppel, or otherwise 3 22 If a court of competent jurisdiction declares any portion of this Agreement invalid, illegal, or otherwise unenforceable, the remaining provisions shall continue in full force and effect, unless the purpose of this Agreement is frustrated 3 23 This Agreement may be signed in counterparts, each of which shall constitute an original 3 24 This Agreement will be effective on the date signed and approved by both Parties and shall conclude upon satisfaction of the terms identified in Paragraph 3 16 or December 31, 2026 (whichever occurs first) 3.25 The Recitals are incorporated into the body of this Agreement. THIS AGREEMENT shall inure to the benefit of and be binding upon the successors and assigns of both Parties. SIGNATURES ON THE FOLLOWING PAGE Revised 5/12/21 Page 5 of 13 SAN BERNARDINO COUNTY ► CI OF REDLNDS (Print or type name 'fcorporation company contractor etc.) By Curt Hagman, Chairman, Bo d of Supervisors (Au orized signature sign in blue ink) Dated JUL 2 7 2021 SIGNED AND CERTIF •,I • tT.TA - COPY OF THIS DOCUMENT HA DE1RTO THE .''CHAIRMAN OEM H�,BARD� 'L-ynna Mlonell'\ i/ It 6; Boar• of Supervisors rdinounty l Pd By FOR COUNTY USE ONLY Name Paul T Barich (Print or type name of person signing contract) Title MAYOR Dated Address (Print or Type) 7-7-21 30 Cajon Street, Suite 200 Redlands, CA 92373 ATTEST onaldson, City Clerk Approved as to Legal Form SEE ATTACHED Suzanne Bryant Deputy County Counsel Date Reviewed for Contract Com dy Silao P Engineering anager Date 7/3 20 2/ Reviewed/Appro by Department Brendon Biggs � Director ! Date ( r? I Revised 5/12/21 Page 6 of 13 SAN BERNARDINO COUNTY ► CITY OF REDLANDS (Pant or type name of corporation company contractor etc.) By ► Curt Hagman Chairman, Board of Supervisors (Authorized signature sign in blue ink) Dated Name SIGNED AND CERTIFIED THAT A COPY OF THIS DOCUMENT HAS BEEN DELIVERED TO THE CHAIRMAN OF THE BOARD Lynna Monell Clerk of the Board of Supervisors San Bernardino County By Dated Deputy FOR COUNTY USE ONLY Title (Print or type name of person .signing contract) Address (Print or Type) Approves as to Legal Form Suzan Brya eputy Ciunty Co Date_JUL' 111.0Z) Reviewed for Contract Compliance ► Andy Silao P E Engineering Manager Date Reviewed/Approved by Department Brendon Biggs Director Date Revised 5/12/21 Page 6 of 13 EXHIBIT A FOR CITY OF REDLANDS AND SAN BERNARDINO COUNTY PAVEMENT IMPROVEMENT IN THE MENTONE, REDLANDS AND YUCAIPA AREAS WABASH AVENUE AND OTHER ROADS Road Name Road Limits County Length City Length Total Length Scope of Work County and City of Redlands Shared Roads. CEDAR LANE 02M E,PLUMWOOD LN E .04M 0 02 0 02 0 04 Slurry Seal II CITRUS AVENUE WABASH AVE E/CRAFTON AVE 0 95 0 07 1.02 Slurry III NAPLES AVENUE 04M E,WABASH AVE E/OPAL WAY 0 09 0 09 0 18 Slurry Seal II SAN BERNARDINO AVENUE WABASH AVE E/OPAL AVE 0 23 0 07 0 30 Slurry III SIXTH AVENUE WABASH AVE E/WALNUT ST 0 44 0 06 0 50 Leveling Course, Chip Seal, Slurry Seal II SYLVAN BLVD WABASH AVE E 11M 0 00 0 06 0 06 Slurry Seal II WABASH AVENUE 05M N/NAPLES AVE N/SH38 0 04 0 04 0 08 Slurry III WABASH AVENUE 09M S,SEVENTH ST N/ 13M N,SEVENTH S 0 10 0 11 0.21 Leveling Course, Chip Seal, Slurry Seal II City Only Roads. WABASH AVENUE 0.13M N, SEVENTH ST N/6TH AVE 0 00 0 13 0 13 Leveling Course, Chip Seal, Slurry Seal II WABASH AVENUE 0.14M S, SEVENTH ST N 0.05M 0 00 0 05 0 05 Leveling Course, Chip Seal, Slurry Seal II County Only Roads AGATE AVENUE COLTON AVE N/0 08M S,NICE AVE 0 17 0.00 0 17 Slurry Seal II AGATE AVENUE 08M S,NICE AVE N/ 05M N,SALERNO AVE 0 77 0.00 0 77 Slurry Seal II ALDERWOOD LANE 12M S,CEDAR LN N/CEDAR LN 0 12 0.00 0 12 Slurry Seal II ALDERWOOD LANE 01M S,BEECH TREE LN N/MADEIRA AVE 0 04 0 00 0 04 Slurry Seal II ALDERWOOD LANE CEDAR LN N/.01M S,BEECH TREE LN 0 08 0.00 0 08 Slurry Seal II AMETHYST STREET BON VIEW DR N/SH38 (FAS 589) 0 35 0.00 0.35 Slurry Seal II ANSLEY LANE NICE AVE N 12M 0 12 0.00 0 12 Slurry Seal II ANZIO AVENUE SALERNO AVE N&E/CRAFTON AV 0 21 0.00 0 21 Slurry Seal 11 APPLEWOOD LANE SIERRA PINE DR N/BEECH TREE CT 0 04 0 00 0 04 Slurry Seal II BARBARA LEE LANE MOSS ST N 05M 0 05 0 00 0 05 Slurry Seal II Revised 5/12/21 Page 7 of 13 Road Name Road Limits County Length City Length Total Length Scope of Work BEECH TREE COURT .05M W, APPLEWOOD DR E/APPLEWOOD DR 0 05 0 00 0.05 Slurry Seal II BEECH TREE LANE LAURELWOOD LN E/ALDERWOOD LN 0 05 0 00 0 05 Slurry Seal II BEECH TREE PLACE WHITEWOOD DR E/PLUMWOOD LN 0 05 0.00 0.05 Slurry Seal II BERYL AVENUE COLTON AVE N/ 02M S,MOSS ST 0 13 0.00 0.13 Slurry Seal II BONITA COURT WARD WAY E 10M 0 10 0.00 0.10 Slurry Seal II BONVIEW DRIVE AMETHYST ST NELY/ZANJA WAY 0 13 0.00 0 13 Slurry Seal II BRIGHTON AVENUE OPAL AVE E/TOURMALINE AVE 0 15 0.00 0 15 Slurry Seal II CAPRI AVENUE OPAL AVE E/CRAFTON AVE 0 72 0.00 0 72 Slurry III CAPRI AVENUE WABASH AVE E .25M 0 25 0.00 0 25 Slurry Seal II CEDAR LANE LAURALWOOD LN E/ 01M W,ALDERWOOD LN 0 03 0 00 0 03 Slurry Seal II CEDAR LANE 03M E,MAPLEWOOD LN E/PLUMWOOD LN 0 07 0.00 0 07 Slurry Seal II CEDAR LANE 01M W,ALDERWOOD LN E 06M 0 06 0.00 0 06 Slurry Seal II CEDAR LANE 05ME,ALDERWOOD LN E/ 03ME,MAPLEWOOD 0 04 0.00 0 04 Slurry Seal II CEDAR LANE PLUMWOOD LN E 02M 0 02 0.00 0 02 Slurry Seal II CHAPARREL LANE HAZELWOOD AVE E 14M 0 14 0.00 0 14 Slurry Seal II CHESAPEAKE LANE AGATE AVE E/ 04M E,MONTEREY CT 0 14 0.00 0 14 Slurry Seal II CHRYSOLITE AVENUE NAPLES AVE N/SAN BDNO AVE 0 59 0.00 0.59 Slurry Seal II CINNABAR COURT GRANITE ST N/ 03M N,PEBBLE ST 0 08 0 00 0.08 Slurry Seal II CITRUS AVENUE CRAFTON AVE E/.23M E,RESERVOIR RD 0 98 0 00 0.98 Patch, Chip Seal, Slurry Seal II COLTON AVENUE CRAFTON AVE E/RESERVOIR RD 0 76 0 00 0 76 Slurry III COLTON AVENUE WABASH AVE E/CRAFTON AVE 1.01 0 00 1.01 Slurry III FIFTH AVENUE WABASH AVE E/CRAFTON AVE 0 96 0 00 0 96 Mill and Overlay GARNET STREET SH38 N/ 57M S,NEWPORT AVE 0.13 0 00 0 13 Slurry III GARNET STREET 08M S, MENTONE AVE N/MENTONE AVE 0.08 0 00 0 08 Slurry Seal II GARNET STREET MENTONE AVE N/SH38 0 12 0 00 0 12 Slurry Seal II GOLD BANNER DRIVE MOSS ST N 05M 0 05 0 00 0 05 Slurry Seal II GRANITE STREET BERYL AVE E/RHYOLITE ST 0 18 0 00 0 18 Slurry Seal II HAMPTON ROAD 14M W,RIDGEWOOD DR E 03M 0 03 0 00 0 03 Cape Seal HAZELWOOD AVENUE COLTON AVE N/LARIMORE LN 0.15 0 00 0 15 Slurry Seal II HIGHLAND AVENUE CRAFTON AVE E 35M 0 35 0.00 0.35 Leveling Course, Chip Seal, Slurry II HIGHLAND AVENUE 13M E,WABASH AVE E/CRAFTON AVE 0 89 0 00 0.89 Leveling Course, Chip Seal, Slurry II JASPER AVENUE NAPLES AVE N/SAN BERNARDINO AVE 0 58 0 00 0.58 Slurry Seal II Revised 5/12/21 Page 8 of 13 Road Name Road Limits County Length City Length Total Length Scope of Work JULIAN DRIVE EAST MENTONE BLVD SH38 N/END 0 04 0.00 0 04 Leveling Course, Chip Seal, Slurry Seal II JULIAN DRIVE WEST MENTONE BLVD SH38 N/END 0 03 0.00 0 03 Leveling Course, Chip Seal, Slurry Seal II KING STREET FIFTH AVE N/COLTON AVE 1.01 0.00 1 01 Slurry III LA COLINA DRIVE WALNUT ST SE/0015MSE,ST CATHERINE ST 0 33 0.00 0 33 Leveling Course, Chip Seal, Slurry Seal II LA DONIA LANE MOSS ST N 05M 0 05 0.00 0 05 Slurry Seal II LARIMORE LANE HAZELWOOD AVE E 11M 0 11 0 00 0 11 Slurry Seal II LAURELWOOD LANE CEDAR LN N/BEECH TREE LN 0 09 0 00 0 09 Slurry Seal II LINDA AVENUE NAPLES AVE N/MENTONE BLVD-SH 38 0 09 0 00 0 09 Slurry Seal II MADEIRA AVENUE 02ME,ALDERWOOD E/ 07ME,WHITEWOOD LN 0 14 0 00 0 14 Slurry Seal II MADEIRA AVENUE MALACHITE AVE E/CRAFTON AVE 0 31 0 00 0.31 Slurry Seal II MADEIRA AVENUE 03M W,ALDERWOOD LN E 05M 0 05 0 00 0 05 Slurry Seal II MALACHITE AVENUE MENTONE BLVD SH38 N/CAPRI 0.34 0 00 0.34 Slurry Seal II MAPLE COURT CEDAR LN S&E 08M 0 08 0 00 0 08 Slurry Seal II MAPLEWOOD LANE CEDAR LANE N .09M 0 09 0 00 0 09 Slurry Seal II MENTONE AVENUE AMETHYST ST E/GARNET ST 0 26 0 00 0 26 Slurry Seal II MONTEREY COURT 06M S,CHESAPEAKE LN N/CHESAPEAKE LN 0 06 0 00 0 06 Slurry Seal II MOSS STREET BERYL AVE E/ROCK ST 0 11 0 00 0 11 Slurry Seal II MOSS STREET AGATE ST E/CRAFTON AVE 0 25 0 00 0 25 Slurry Seal II MOSS STREET ROCK ST E/AGATE AVE 0 12 0 00 0 12 Slurry Seal II NAPLES AVENUE AMETHYST ST E/0005M E,ZANJERO CT 0 23 0.00 0 23 Slurry Seal II NAPLES AVENUE END E/LINDA AVE 0 06 0 00 0 06 Slurry Seal II NEWPORT AVENUE GARNET E/EMERALD AVE 0 26 0.00 0 26 Patch, Overlay OLIVINE AVENUE NICE AVE N/MENTONE BLVD (SH38) 0 24 0.00 0.24 Slurry Seal II OLIVINE AVENUE MENTONE BL SH38 N/CAPRI 0 34 0.00 0.34 Slurry Seal II OPAL AVENUE SH38 N/SAN BDNO AVE 0 50 0.00 0.50 Slurry III OPAL AVENUE FIFTH AVE N/COLTON AVE 1 00 0.00 1.00 Slurry III OPAL AVENUE COLTON AVE N/0010M S,NICE AVE 0 16 0.00 0 16 Slurry III OPAL AVENUE 0010M S,NICE AVE N/SH38 0 36 0.00 0.36 Slurry III OPAL AVENUE SAN BERNARDINO AVE N 0.39M 0 39 0.00 0.39 Slurry III OPAL AVENUE END N/ 04M N,SEVENTH ST 0 17 0 00 0 17 Patch, Chip Seal, Slurry Seal II OPAL AVENUE SIXTH ST N/FIFTH AVE 0 26 0 00 0 26 Patch, Chip Seal, Slurry Seal II OPAL WAY NAPLES AVE N/0008M N,MENTONE BLVD 0 16 0 00 0 16 Slurry Seal II Revised 5/12/21 Page 9 of 13 Road Name Road Limits County Length City Length Total Length Scope of Work OVERCREST DRIVE 52M N,TENNESSEE ST N/WALNUT ST 0 56 0 00 0.56 Slurry Seal II OVERCREST DRIVE TENNESSEE ST N 52M 0 52 0 00 0.52 Leveling Course, Chip Seal, Slurry Seal II PEBBLE STREET CINNABAR CT E/RHYOLITE ST 0 08 0 00 0 08 Slurry Seal II PLUMWOOD LANE CEDAR LN N/BEECH TREE PL 0 10 0 00 0 10 Slurry Seal II PLUMWOOD LANE MENTONE BLVD N/CEDAR LN 0 13 0 00 0 13 Slurry Seal II QUARRY STREET OLIVINE AVE E/AGATE AVE 0 16 0 00 0 16 Slurry Seal II RESERVOIR ROAD COLTON AVE N/NICE AVE 0 26 0 00 0 26 Slurry Seal II RHYOLITE STREET GRANITE ST N/MOSS ST 0 11 0 00 0 11 Slurry Seal II ROCK STREET MOSS ST N/NICE AVE 0.09 0 00 0 09 Slurry Seal II ROSE STREET ZANJA DR N/NAPLES AVE 0.09 0 00 0 09 Slurry Seal II SALERNO AVENUE AGATE AVE E/CRAFTON AVE 0.22 0 00 0 22 Slurry Seal II SAN BERNARDINO AVENUE OPAL AVE E/ 05M E,SOFFEL ST 0.19 0 00 0 19 Slurry Seal II SAND COURT ROCK ST E/END 0.08 0 00 0 08 Slurry Seal II SANDSTONE COURT GRANITE ST N/END 0.08 0 00 0 08 Slurry Seal II SAPPHIRE STREET COLTON AVE N/MENTONE BLVD (SH38) 0.49 0 00 0 49 Slurry Seal II SAPPHIRE STREET MENTONE BLVD SH38 N/END 0.25 0 00 0 25 Slurry Seal II SAPPHIRE STREET FLORIDA ST NE .3M 0.30 0 00 0.30 Patch, Overlay SAPPHIRE STREET 0 43M N, Florida St NE & E 0.21M 0.07 0 00 0 07 Overlay SEVENTH STREET WABASH AVE E/OPAL AVE 0.27 0 00 0 27 Patch, Chip Seal, Slurry Seal II SIERRA PINE DRIVE CRAFTON AVE E/LAURELWOOD LN 0 11 0 00 0 11 Slurry Seal II SLIGER ROAD END E&N&E/0004M E,WARD WAY 0.21 0 00 0 21 Slurry Seal II SOFFEL STREET OPAL AVE E&N/SAN BDNO AVE 0.23 0 00 0 23 Slurry Seal II ST CATHERINE STREET LA COLINA DR NW/END 0 06 0 00 0 06 Leveling Course, Chip Seal, Slurry Seal II STONE COURT MOSS ST N/END 0 05 0 00 0 05 Slurry Seal II STONEWOOD STREET HAZELWOOD AVE E/SAPPHIRE ST 0 16 0 00 0 16 Slurry Seal II THIRD AVENUE CRAFTON E/RESERVOIR RD 0 69 0 00 0 69 Leveling Course, Chip Seal, Slurry Seal II TURQUOISE AVENUE FLORENCE AVE N/SAN BDNO AVE 0 66 0 00 0 66 Slurry Seal II TURQUOISE AVENUE NICE AVE N/FLORENCE AVE 0 08 0 00 0 08 Slurry Seal II VALENCIA DRIVE WALNUT ST NE/END 0 19 0 00 0 19 Patch, Chip Seal, Slurry Seal II WABASH AVENUE 25M N,SAN BERNARDINO AVE N 17M 0 17 0 00 0 17 Leveling Course, Slurry Seal III WABASH AVENUE SH38 N/0.12M 0 06 0 00 0.06 Mill and Overlay WABASH AVENUE 0 12M N,SH38 N/CAPRI AVE 0 11 0 00 0 11 Reconstruction Revised 5/12/21 Page 10 of 13 Road Name Road Limits County Length City Length Total Length Scope of Work WABASH AVENUE CAPRI AVE N/SAN BDNO AVE 0 08 0 00 0.08 Reconstruction WABASH AVENUE .30M S, SEVENTH ST N 16M 0 16 0.00 0 16 Leveling Course, Chip Seal, Slurry Seal II WABASH AVENUE 6TH AVE N/5TH AVE 0 12 0 00 0 12 Slurry Seal II WALNUT STREET CITRUS AVE N .34M 0.34 0 00 0.34 Slurry Seal II WALNUT STREET OVERCREST N/FIFTH AVE 0 49 0 00 0 49 Chip Seal, Slurry Seal II WALNUT STREET FIFTH AVE N/CITRUS AVE 0.51 0 00 0.51 Chip Seal, Slurry Seal II WARD WAY 03M S,ZANJA VIEW DR N/MILL CRK RD 0 25 0 00 0.25 Slurry Seal II WHITEWOOD DRIVE CEDAR LN N/MADEIRA AVE 0 11 0 00 0 11 Slurry Seal II ZANJA DRIVE AMETHYST E/ZANJA WAY 0 15 0 00 0 15 Slurry Seal II ZANJA VIEW DRIVE WARD WAY E/END 0 12 0 00 0 12 Slurry Seal II ZANJA WAY BON VIEW NE&N/NAPLES AVE 0 14 0 00 0 14 Slurry Seal II ZANJERO COURT END N/NAPLES AVE 0 06 0 00 0 06 Slurry Seal II Total Project Miles 29 94 0 70 30 64 Revised 5/12/21 Page 11 of 13 Exhibit B ESTIMATE OF PROJECT COSTS FOR CITY OF REDLANDS AND SAN BERNARDINO COUNTY PAVEMENT IMPROVEMENTS IN THE MENTONE, REDLANDS, AND YUCAIPA AREAS WABASH AVENUE AND OTHER ROADS DESCRIPTION TOTAL COST SAN BERNARDINO COUNTY SHARE CITY OF REDLANDS SHARE Construction and Contingency $2,840,000 $2,787,000 $52,000 All Other Costs such as design survey, CEQA compliance construction engineering inspection and County overhead $ 645,000 $ 634,000 $12,000 Total $3,485,000 $3,421,000 $64,000 Revised 5/12/21 Page 12 of 13 Sa Bernardino Ave Madeira Ave Colton Ave 3rd Ave Ci rus Ave Highland Ave th Ave t Hampton Rd COUNTY OF SAN BERNARDINO DEPARTMENT OF PUBLIC WORKS DISTRICT 3 YARD 5 WO TX1809 Exhibit C LOCATION MAP Mentone and Yucaipa Areas y,rFlorida St Newport Ave Julian Dr West ounlep Acres SAN BERNARI)INt) COUNTY Julian Dr East Mill Creek Rd Legends Slurry Seal Type II (County and/or City of Redlands shared road Slurry Seal Type III (County and/or City of Redlands shared road) Mill and Overlay (County only road) Reconstruction (County only road) Leveling Course, Chip Seal and Slurry Seal Type II (County and/or City of Redlands shared road) Chip Seal and Slurry Seal Type II (County only road) Leveling Course and Overlay (County only road) Overlay (County only road) LOCATION MAP WABASH AVENUE AND OTHER ROADS Various Roads / Locations Reconstruction, Mill and Overlay, Overlay, Slurry Seal -Type II, Slurry Seal -Type III, Chip Seal, Leveling Course Revised 5/12/21 Page 13 of 13