HomeMy WebLinkAboutOrdinances_2399_CCv0001.pdf ORDINANCE NO, 2399
AN ORDINANCE OF THE CITY OF R DLA DS ADDING CHAPTER 18,266 TO THE
REDLANDS MUNICIPAL CODE TO ESTABLISH REGULATIONS FOR SURFACE MINING
AND RECL AAIATION ACTIVITIES AND REPEALING ARTICLE XI OF THE REDLANDS
MLINLICIPAL CODE
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF REDLANDS AS
FOLLOWS.'
Section 1. article XI of the Redlands Municipal Code is hereby repeated in its entirety,
,tion 2. Chapter 18.266 relating to Surface Mining and Lard Reclamation is hereby added
to the Redlands Municipal Code to read as follows:
"Chapter 18.266
SURFACE MINING AND LAND RECLAMATION
1 .266.010 Purpose and Intent
18,266.020 Definition$
18,266.030 and State Regulations
1&266.040 Applicability
18.266.050 Vested Rights
18,266.060 Permit and Reclamation Plan
18166.070 X66.070 'rocessin
18.266.080 Performance Standards for Reclamation Plans
18,266.090 Reclamation Phasing
18,266.100 Statement of Responsibility
18,266,110 Findings for Approval
1 `266.120 Inspections
18,266,1310 Financial Assurances
18266,140 Interim Management Plans
l&'11-W150 Periodic Review
182W 160 Time Limits
18,266.170 Appeal
1&2W 1Violations and Penalties
18.266,190 Fees
l&266-200 Mineral Resource Protection
DA1 371-E 1
Y
N1
18,266,010 Pose and Intent, The City of Redlands recognizes that the extraction of
minerals is essential to the continued economic well-being of the City and its surrounding
community and that the reclamation of mined lands is necessary to prevent or minimize adverse
effects on the environment and to protect the public health, safety and welfare, The City also
recognizes that surface raining takes place in diverse areas where the geologic,topographic,climatic,
biological and social conditions are significantly different and that reclamation operations and the
specifications therefor may vary,accordingly, The purpose and intent of this Chapter is to regulate
surface mining operationsand implerneritthe minimum requirements of Califomia!s Surface Mining
and Reclamation Act of 1975 (Public Resources Code Sections 2710 et. jgq., as amended,
(hereinafter referred to as"SMARA"),Public Resources Code Section 2207,and the California Code
of Regulations adopted pursuant thereto, to ensure that:
A. Adverse environmental and other effects of surface mining operations will be
prevented or minimized and that the reclamation of mined lands will provide for the beneficial,
sustainable long-term productive use of such lands; and
B. The production and conservation of minerals will be encouraged while potential
hazards to public health and safety and adverseeffect s on the environment including,but not limired
to geologic subsidence, air pollution, water quality degradation, damage to biological resources,
flooding,erosion,degradation of scenic quality and noise pollution shall be reduced or eliminated.
18,266.020 Definitions. For purposes of this Chapter, the following words and phrases
shall be defined as follows.
A, "Area of Regional Significance" means an area designated by the Board which is
known to contain a deposit of minerals, the extraction of which is judged to be of prime importance
in meeting future needs for minerals in a particular region of the State within which the minerals are
located and which,if prematurely developed for alternate incompatible land uses,could result in the
premature loss of minerals that are of more than local significance.
B "Area of StatewideSignificance" means an area designated by the Board which is
known to contain a deposit of minerals,the extraction of which is judged to be of prime importance
in meeting future needs for minerals in the State and which, if prematurely developed for alternate
DJM3237LE 2
incompatible land uses, could result in,the permanent loss of minerals that are of more than local or
regional significance.
C, "Board" means the State Mining and Geology Board,
D, "Borrow Pits" means excavations created by the surface mining of rock,
unconsolidated geologic deposits or soil to provide material (borrow) for fill elsewhere.
E. " ;Et A" means the California Environmental Quality Act as enacted in Sections
21000 et, sem; of the Public Resources Code.
F. "Compatible Land Uses" means land uses inherently compatible with mining that
require a minimum public or private investment in structures or land improvements,and which may
allow mining because of the relative economic value of the land and its improvements. Examples
of such uses may include, but shall not be limited to, very low density residential, geographically
extensive but low impact industrial, recreational, agricultural, grazing and open space.
G. "Director"means the Director ofthe State ofCaliformaDepartmentof Conservation.
H, "Haul Road" means a road along which minerals and other materials are transported
from an area of excavation to a processing plant or stock pile area of a surface mining operation.
I. "Idle" means to curtail, for a period of one year or more, surface mining operations
by more than.90 percent of the operation's previous maximum annual mineral production,with the
intent to resume those surface mining operations at a future date.
J. "Incompatible Land Uses" means land uses inherently incompatible with mining
and/or that require public or private investment in structures, land improvements and landscaping
and that may prevent mining because of the greater economic value of the land and its
improvements. Examples of such uses may include, but shallnot be limited to, high density
residential, low density residential with high unit value.
, public facilities,geographically limited but
impact intensive industrial and commercial.
K "Mined Lands" means the surface, subsurface and ground water of an area in which
surface mining operations will be, are being, or have been conducted, including private ways and
roads appurtenant to any such area, land excavations, workings, mining waste and areas in which
structures, facilities, equipment, machines, tools or other materials or property which result from,
or are used in, surface mining operations are located,
DAM37LE 3
"Minerals"means any naturally:occurring chemical elernentor compound,or groups;
of elements and compounds, formed from inorganic processes and organic substances,
including, but not limited to, coal,peat, and bituminous rock, but excluding geothermal resources,
natural gas and petroleum.
"Operator" means any person who is engaged in surface raining operations, who
permits others to conduct surface minim operations on his property and who receives a financial
benefit therefrom, or who contracts with others to conduct operations on his behalf except for a
person who is engaged in surface raining operations as an employee with wages as sole
compensation.
"Overburden" means soil; rock or other material that lies above a mineral deposit or
in between mineral deposits, before or after its removal by surface mining operations.
0. "Person" means any individual, firm, association, corporation, organization or
partnership, or any city, county or district of the Mate, or any department or agency thereof:
R "Reclamation"means the process of land treatment that minimizes water degradation,
air pollution,damage to aquatic or wildlife habitat,flooding,erosion and either adverse effects from
mining operations,including adverse surface effects incidental to underground mines,so that mined
lands are reclaimed to a usable condition which are readily adaptable for alternative land uses and
create no danger to public health or safety. Reclamation may extend to lands surrounding rained
lands, and may require backfilling, grading, recoiling, reveetation, soil compaction, stabilization
or outer measures.:
"State Regulations" means collectively the California Surface Mining and
Reclamation Act of 1975 (the "Act") (Public Resources Code Sections 2710 et. Lm.), Public
Resources Code Section 2207 and the California Code ofRegulations implementing theAct(14 Cal.
Code of Regulations Section 3500 et. se . and 14 Cat. Cade ofRegulations, Article 9, Chapter
Sections 3700 et. —se-q.).
"Stream Bed Skimming" means excavation of sand and gravel from stream bed
deposits above the mean summer water level or stream bottom, whichever is higher.
"Surface Mining Operation(s)" means all or any part of the process involved in the
mining of minerals by removing overburden and raining directly from mineral deposits, open pit
ying,or surface
I _,of minerals naturally exposed,mining by the auger method,dredging or quarry
work incidental to an underground mine.Surface mining operations shall include,but are not limited
to in place distillation, retorting or leaching; the production and disposal of mining waste,
prospecting and exploratory, activities-, and the creation of borrow pits, stream bed skimming,
segregation and stockpiling of mined materials and their recovery,
18,266030 SMARA and State Regulations=, The State Regulations, as those provisions
may be amended from time to time, are made a part of this Chapter by this reference and shall have
the same force and effect as if the provisions therein were specifically and fully set out herein,
excepting that when the provisions of this Chapter are more restrictive than conflicting State
Regulations, this Chapter shall prevail.
l&266.040 Applicability.
A. Requirement for Conditional Use Permit. Unless exempted by the provisions of this
Chapter,any person whet proposes to conduct Surface Mining Operations,or rho proposes to permit
another person to engage in Surface Mining Operations on his property shall, prior to the
commencement of said operations, file and obtain approval from the City for a Conditional Use
Permit as provided in Chapter 18.192 of this Code, a Reclamation Plan in accordance with the
provisions set forth in this Chapter, and the State Regulations, and any applicable financial
assurances for reclamation, A Conditional Use Permit shall be required for all surface mining
operations in all zoning districts in which surface mining is allowed and for the expansion or
substantial change of operation of any surface mine forwhich such expansion or change has not leen
thereby approved, including any operation;which meets the definition of a"rion-conforming use" as
provided for in this Code.
B Rtquirement for Reclamation Plan, A Reclamation Plan shall be required for all
surface mining operations including those portions of existing surface mining operations which
claim to have vested rights as defined by the State Regulations,unless otherwise exempted from the
requirements of the State Regulations or as set forth herein,
C, EAemption s, This Chapter shall not apply to the following activities,-
5
I Excavations or grading conducted for farming or on-site construction for the
purpose of restoring land following a flood or natural disaster.
Onsite excavation and onsite earthmoving activities which are an integral and
necessary part of a construction project that are undertaken to prepare a site for construction of
structures, landscaping, or other land improvements, including the related excavation, grading,
compaction or the creation of fills, road cuts, and embankments, whether or not surplus materials
are exported from the site.subject to all of the following conditions: (a)all required permits for the
construction, landscaping or related land improvements have been approved by a public agency in
accordance with applicable provisions of state land and locally adopted plans and ordinances,
including but not limited to, CEQA; (b) the City's approval of the construction project included
consideration of the onsite excavation and onsite earthmoving activities pursuant to EQA; (c)the
approved construction project is consistentwith the general plan or zoning ofthe site;and(d)surplus
materials shall not be exported from the site unless and until actual construction work has
commenced and shall cease if its determined that construction activities have terminated, have been
indefinitely suspended, or are no longer being actively pursued.
3 Prospecting for, or the extraction of, minerals for commercial purposes and
the removal of overburden in total amounts of less than 1,000 cubic yards in anyone location of one
acre or less,
4. Surface mining operations that are required by federal law to protect a
mining claim, if such operations are conducted solely for that purpose.
5Such other surface mining operations which the Board determines to be of an
infrequent nature and which involve only minor surface disturbances,
6, Emergency excavations or grading conducted by the Department of Water
Resources or the Reclamation Board for the purpose of averting, alleviating, repairing,or restoring
damage to property due to imminent or recent floods, disaster or other emergencies.
7, The solar evaporation of sea water or bay water for the production of salt and
related minerals.
8, Excavations or grading for roadbed materials for construction and
maintenance for timber or forest operations if the land is owned by the same person or entity, and
WMI237LE 6
if the excavation is conducted adjacent to timber or forest operating roads. This exemption is only
available if slope stability and erosion are controlled in accordancewith Board regulations and, on
closure of the site,the person closing the site implements, where necessary, revegetation measures
and post-closure uses in consultation with the Department of Forestry and Fire Protection, This
exemption does not apply to onsite excavation or;grading that occurs within 100 feet of a Class One
water course or 75 feet of a Class Two water course, or excavation for materials that are sold for
commercial purposes.
An exemption under this Chapter does not exempt a project or activity from the application
of other Federal, State and local regulations, ordinances or policies including, but not limited to,
CEQA,
18,2166050 Vested Rialits,
No person who obtained a vested right to conduct surface mining operations prior to January
1, 1976, shall be required to secure a permit to mine, so long as the vested right continues and as
long as no substantial changes have been made in the operation except in accordance with SMARA,
State regulations and this Chapter. Where a person with vested rights has continued surface mining
in the same area subsequent to January 1, 1976, he shall obtain City of Redlands approval of a
Reclamation Plan covering the mined lands disturbed by such subsequent surface mining. In those
cases where an overlap exists in the horizontal and/or vertical sense)between pre-and post-Act
mining, the Reclamation Plan shall call for reclamation proportional to that disturbance caused by
the mining after the effective date of the Act(January 1, 1976), All other requirements of State law
and this Chapter shall apply to vested mining,
18,266,060 Permit and Reclamation Plan.
A. An application for aConditional Urse Permit or Reclamation Plan for surface mining
operations or a land reclamation project shall be made on the form provided by the Community
Development Department. The application shall be filed in accordance with this Chapter and any
written procedures established by the Community Development Director.
P. Copies of the Reclamation Plan application as may be required by the Community
DA13231711 7
Development Director shall be submitted in conjunction with all applications for Conditional Use
Permits for surface mining operations. For surface mining operations that are exempt from a
Conditional Use Permit pursuant to this Chapter, the Reclamation Plan application shall include
information concerning the mining operation that is required for processing the Reclamation Plan,
CApplications shall include all required environmental review forms and information
prescribed by the Community Development Director,
D. Upon completion of the environmental review procedure and filing of all documents
required by the Community Development Director, consideration of the Conditional Use Permit or
Reclamation Plan for the proposed or existing surface mine shall be completed pursuant to this Code
at a noticed public hearing before the Planning Commission, and pursuant to Section 2774 of the
Public Resources Code.
18.266,070 Processing.
A. Within thirty(30)days of acceptance of an application for a Conditional Use Pen-nit
to conduct surface mining operations and/or for a Reclamation Plan as complete, the Community
Development Department shall notify the Director of the filing of the application,Whenever mining
operations are proposed in the I 00-year flood plain of any stream, as shown in Zone A of the Flood
Insurance Rate Maps issued by the Federal Emergency Management Agency,and within one mile,
upstream or downstream, of any state highway bridge, the Community Development Department
shall also notify the State Department of Transportation that the application has been received.
B. The Community Development Department shall process the application in accordance
with CEQA and the City's CEQA Guidelines and prepare a staff report with recommendations for
consideration to the Planning Commission. Prior to final approval of a Reclamation Plan,financial
assurances (as provided in this Chapter), or any amendments to the Reclamation Plan or existing
financial assurances,the Planning Commission shall certify to the Director that the Reclamation Plan
and/or financial assurance complies with the applicable requirements of the State regulations and
submit the plan, assurances, or amendments to the Director for review. The Planning Commission
may conditionally approve the Reclamation Plan and financial assurances before submittal to the
Director.. If a Conditional Use Permit is being processed concurrently with the Reclamation Plan,
DA132371-E 8
the Planning Commission may simultaneously also conceptually approve the Conditional Use
Permit. However, the Planning Commission may defer action on the Conditional Use Permit until
taking final action on the Reclamation Plan and financial assurance. If necessary to comply with
permit processing deadlines, the Planning Commission may conditionally approve the Conditional
Use Permit with, the condition that the Community Development Department shall not issue the
Conditional Use Permit for the mining operation until financial assurances have been reviewed by
the Director and final action has been taken on the Reclamation Plan and financial assurances.
The Director shall have 30 days to prepare written comments on the Reclamation Plan and
financial assurances and 45 days to review and comment, if the Director so chooses, The Planning
Commission shall evaluate written comments received from the Directorduring the45-day comment
period. The Community Development Department shall prepare a written response describing the
disposition of the major issues raised by the State for the Planning Commission's approval. When
the Planning Commission's position Is at variance with the recommendations and objections raised
in the Director's comments,the written response shall address in detail,why specific comments and
suggestions were not accepted. Copies of any written comments received and responses prepared
by the Planning Commission shall be promptly forwarded to the operator/applicant, The Planning
Commission may approve,conditionally approve,or deny the Reclamation Plan pursuant to Section
2774 of the Public Resources Code, and the financial assurances pursuant to vSection 2770(d)of the
Public Resources Code.
C. The Community Development Department sball forward a copy of each approved
Conditional Use Permit for mining operations and/or approved_Reclamation Plan,and a copy of the
financial assurances to the Director. By July I of each year, the Community Development
Department shall submit to the Director for each active or idle mining operation a copy of the
Conditional Use Permit or Reclamation Plan amendments, as applicable, or a statement that there
have been no changes during the previous year,
D, Annual Reports. Surface mining operators shall forward an annual status report to
the Director and the City Community Development Department on adate established by the Director
upon forms furnished by the Board,
DA13237LE 9
18,266.080 Performance Standards for Reclamation Plans
X All new or revised Reclamation Plans shall conform to minimum statewide
performance standards required pursuant to Public Resources Code Sec. 2773 (b), as Conditional
Use Permit and/or Reclamation Plan,pursuant to Section B adopted by the Board, including but not
limited to '�,vildlife habitat, backfilling, revegetation, drainage, agricultural land reclamation,
equipment removal, stream protection, topsoil salvage, and waste management.
The City of Redlands may impose additional performance standards developed either in
review of individual projects, as warranted, or through the formulation and adoption of City-wide
performance standards.
18.266.090 Reclamation Phasing.
Reclamation activities may be phased with respect to the mining operation and shall be
initiated at the earliest possible time on those portions of the mined lands that will not be subject to
further disturbance(see also, Interim Management Plans for Idle Mining Operations,hereinbelow),
Interim reclamation may also be required for mined lands that have been disturbed and that may be
disturbed again in future operations, Reclamation may be done on an annual basis, in stages
compatible with continuing operations, or on completion of all excavation, removal, or fill, as
approved by the City-Each phase of reclamation shall be specifically described in the Reclamation
Plan and shall include(a)the beginning and expected ending dates for each phase,(b)all reclamation
activities required; (c)criteria for measuring completion of specific reclamation activities; and(d)
estimated costs as provided under Financial Assurances hereinbelow,
18.266.100 Statement of Responsibilily
The person submitting the Reclamation Plan shall sign a statement accepting responsibility
for reclaiming the mined lands in accordance with the Reclamation Plan. Said statement shall be
kept by the Planning Department in the mining operator's permanent record. Upon sale or transfer
of the operation, the new operator shall submit a signed statement of responsibility to the Planning
Department for placement in the permanent record.
DAD 2-17LE 10
18.266.110 Findings for Approval
A, Approval of aConditional Use Permit, In addition to the findings for approval of a
Conditional Use .Permit contained in Chapter 18.192 of this Code, Conditional Use Permits for
surface mining operations shall include a fi
whether the surface mining operation is in compliance with the approved Conditional Use Permit
and/or Reclamation Flan, approved financial assurances,and the Mate regulations. In no event shall
less than one inspection be conducted in any calendar year. Said inspections may be made by state-
registered geologist,state-registered civil engineer,state-licensed landscape architect,state registered
forester, who is experienced in hand reclamation and who has not been employed by the mining
operation in any capacity during the previous 12 months, or other qualified specialists, as selected
by the Community Development Director and as retained by the City, All inspections shall be
conducted using; a form approved and provided by the State Mining and Geology Board. The
Community Development Department shall notify the l irectorwithin thirty(30)days ofcompletion
of the inspection that the said inspection has been conducted and shall forward a copy of said
inspection notice and any supporting documentation to the mining operator. The operator shall be
solely responsible for the reasonable dust of such inspection.
1&266;130 Financial Assurances
A; To ensure that reclamation will proceed in accordance with the approved Reclamation
Plan, the City shall rewire as a condition of approval of any Surface Mining Operation security
which will be released upon satisfactory performance.
The applicant may post security in an acceptable form of surety bond, trust fund,
irrevocable letter of credit from an accredited financial institution;or other method acceptable to the
City and the Board as specified in statewide regulations adopted by the Board, and which the City"
reasonably determines are adequate to perform reclamation in accordance with the surface raining
operation's approved Reclamation Plan. Financial assurances shall be made payable to the City and
the Department of Conservation, Financial assurances shall be required to ensure compliance with
elements of the Reclamation flan, including but not limited to, reve etatian and landscaping
requirements;restoration or aquatic or wildlife habitat;restoration ofwater bodies and water quality;
slope stability and erosion and drainage control, disposal of hazardous materials; and other
mitigation measures, Financial assurances for such elements of the Flan shall be monitored by the
Community Development Department-
WN1.12237Lr 1 ,
<k
u;:
C. The amount of the financial assurances shall be based upon the estimated costs of
reclamation for the years or phases stipulated in pursuant to the approved Reclamation Plan,
including any maintenance of reclaimed areas as may be required, subject to adjustment for the
actual amount required to reclaim lands disturbed by surface mining activities since January 1, 1976,
and new lands to be disturbed by surface mining activities in the upcoming year, as provided in
paragraph (6) herein below. Cost estimates shall be prepared by a licensed engineer and/or other
qualified professionals retained by the operator and approved by the Community Development
Director- The estimated amount of the financial assurance shall be based on an analysis of physical
activities necessary to implement the approved Reclamation Plan, the unit costs for each of these
activities, the number of units of each of these activities, and the actual administrative costs.
Financial assurances to ensure compliance with revegetation,restoration of waterbodies,restoration
of aquatic or wildlife habitat, and any other applicable element of the approved Reclamation Plan
shall be based upon cost estimates that include butmay not be limited to labor,equipment,materials,
mobilization of equipment, administration, and reasonable profit by a commercial operator other
than the permittee.
D. In projecting the costs of financial assurances, it shall be assumed without prejudice
or insinuation that the surface mining operation could be abandoned by the operator and,
consequently, the City or State may need to contract with a third party commercial company for
reclamation of the site,
E The financial assurances shall remain in effect for the duration of the surface mining
operation and any additional period until reclamation is completed including any maintenance
required.
F, The amount of financial assurances required of a surface mining operation for any
one year shall be adjusted annually to account for new lands disturbed by operations, inflation, and
reclamation of lands accomplished in accordance with the approved Reclamation Plan.The financial
assurances shall include estimates to cover reclamation for existing conditions and anticipated
activities during the upcoming year, excepting that the permittee may not claim credit for
reclamation scheduled for completion during the coming year
G, Revisions to financial assurances shall be submitted to the Community Development
DA1323711 13
Director each year prior to the anniversary date for approval of the financial assurances, The
financial assurance shall cover the cost of existing disturbance and anticipated activities for the next
calendar year, including any required interim reclamation, If revisions to the financial assurances
are not required, the operator shall explain, in writing, why revisions are not required.
18,266,140 Interim Manaaement Plans
A 'ithin 90 days of a surface mining operation,becoming idle, the operation shall
submit to the Community Development Department a proposed Interim Management Plan (the
"IXIP").The proposed IMP shall fully comply with the requirements of Public Resources Code,Sec,
2770 (h)and shall provide measures the operator will implement to maintain the site in compliance
with SMARA, and all conditions of the Conditional Use Permit and/or Reclamation Plan. The
proposed IMP shall be processed as an amendment to the Reclamation Plan and shall not be
considered a project for the purposes of environmental review,
& Financial assurances for idle operations shall be continued as addressed in the
Reclamation Plan or an otherwise approved through the Idle mine's IMP. Upon receipt of a
complete proposed IMP, the Community Development Department shall forward the 1W to the
Department of Conservation for review. The M shall be submitted to the Department of
Conservation at least 45 days prior to approval by the Planning Commission.
C, Within 60 days of receipt of the proposed M, or a longer period mutually agreed
upon by the Community Development Director and the operator, the Planning Commission shall
review and approve or deny the M in accordance with this Chapter. The operator shall have thirty
(30)days or a longer period mutually agreed upon by the operator and the Community Development
Director to submit a revised ILII''.The Planning Commission shall approve or deny the revised IW
within sixty l)days of receipt. If the Planning Commission denies the revised IMP, the operator
may appeal that action to the City Council.
D. The INIP may remain in effect for a period not to exceed five years,at which time the
Planning Commission may renew the LMP for another period not to exceed five years or require the
surface mining operator to commence reclamation in accordance with its approved Reclamation
Plan.
OAN13237LE 14
18.266.1 5th Periodic Review
As a condition of approval for either the Conditional Use Permit or the Reclamation Flan,
a periodic review schedule shall be established to evaluate the compliance with such permit or plan,
18,266,160
pirnel imitf trcoral aence ert E se} er it f r nrtace? inir C er lir r
The time limits for commencing surface mining operations Haat are permitted pursuant to
this Chapter shill be as provided in this Code.
18.266.170 Anneals
Any person aggrieved by an act or determination of the Planning Commission in the exercise
of the authority granted herein shall have the right to appeal to the City Council. An appeal shall be
tiled on farms provided by the City within ten(1 0)calendar days after the date of the decision being
appealed.
18,266,180 Violations and Penalties
If the Community Development Director, based upon an annual inspection or otherwise
confirmed by an inspection of the mining operation, determines that a surface reining operation is
not in compliance with this Chapter, the applicable Conditional Use Permit, any required permit
and/or the Reclamation Plan,the City shall follow the procedures set forth in Public Resources Code
Sections 2774.1 and 2771.2 concerning violations and penalties, as well as those provisions of this
Code for revocation and/or abandonment of a Conditional t...Tse Permit which are not preempted by
M
18.266.190 Pees..
The City shall establish such feesas it deems necessary to coverthe reasonable costs incurred
in implementing this Chapter and the State regulations, including but not limiter/to processing of
applications,annual reports,inspections,monitoring,enforcement and compliance, Such fees shall
be paid by the operator of the surface mining and./or reclamation plan,as required by the City,at the
time of tiling of the Conditional Use Permit application, Declamation Plan application, or at such
WN13237L
1
4
other time as is determined by the City to be appropriate in order to ensure that all reasonable costs
of implementing this Chapter are borne by the operator.
18,266-100 Mineral Resource Protection
Mine development is encouraged in compatible areas before encroachment of conflicting
uses. Mineral resource areas that have been classified by the State Department of Conservation's
Division of Mines and Geology or designated by the State Mining and Geology Board, as well as
existing surface mining operations that remain in compliance with the provisions of this Chapter,
shall be protected from intrusion by incompatible land uses that may impede or preclude mineral
extraction or processing, to the extent possible consistent with the City's General Plan,
In accordance with Public Resources Code 2762,theCity's General Plan and resource maps
will be prepared to reflect mineral information (classification and/or designation report)within 12
months of receipt from the State Mining and Geology board ofsuch information. Land use decisions
within the City will be guided by information provided on the location of identified mineral
resources of regional significance. Conservation and potential development of identified mineral
resource areas will be considered and encouraged. Recordation on property titles of the presence of
important mineral resources within the identified mineral resources areas may be encouraged as a
condition of approval of any development project in the impacted area. Prior to approving a use that
would otherwise be incompatible with mineral resource protection, conditions of approval may be
applied to encroaching development projects to minimize potential conflicts.
Section Severability:
If any section,subsection, sentence clause or phrase of this ordinance is for any reason held
to be 'invalid or unconstitutional by the decision of a court of competent jurisdiction, it shall not
affect the remaining portions of the ordinance,
10
The Mayor shall sign this ordinance and the City shall certify to the adoption of this
ordinance and shall cause it, or a summary of it, to be published once in the Redlands Daily Facts,
a newspaper of general circulation within the City,and thereafter,this ordinance shall take effect in
accordance with law.
C ty kethnds\j
Mayo , City of
i
ATTEST'
Cit y erk Nif R
of t161 of
'0
1, Lorrie Poyzer,City Clerk of the City of Redlands,hereby certify that the foregoing ordinance was
duly adopted by the City Council at a regular meeting thereof held on the 18tway of Mav
1999 by the following vote;
AYES: Councilmembers Banda, Gilbreath, George, Freedman; Mayor Cunningham
NOES- None
ABSTAIN: None
ABSENT- None
C i'tyYer k, Cit glands
DA13217LE 17