HomeMy WebLinkAboutContracts & Agreements_53-2001CHANGE ORDER NO. 2
CITY OF REDLANDS
Issued April 17, 2001
• Advanced, with coordination through the respective project managers, will be
provided with the option to have direct contact as required with the technical staff at
the City and with senior users. This option will allow faster resolution of issues in
order to ensure that the timeline contemplated in the current project plan can be met.
For Advanced, the Steering Committee representatives will be Patricia Sorbara, Kathryn
McKay, Philip Playfair (Chief Marketing Officer) and Steven Hammond (Chief Information
Officer). Renata Anderson will continue to act as the Project Manager for Advanced.
Advanced is confident that the City's Steering Committee representatives (Mike Reynolds,
Gary Phelps and Rod Hill) and the representatives from Advanced will ensure resolution of
the issues.
With approval of Change Order No. 2 for the completion of the implementation, Advanced is
committed to completing the project within the hours identified in this Change Order.
CITY OF REDLANDS by: ADVANCED UTILITY SYSTEMS by:
PAT GILBREATH
Mayor
ATTEST:
President and CEO
8
CHANGE ORDER NO. 2
CITY OF REDLANDS
Issued April 17, 2001
BACKGROUND
On June 21st, 2000, Advanced Utility Systems Corporation (Advanced) and the City of
Redlands (the City) executed a Software License and Implementation Agreement (the
Agreement). The Agreement provided the foundation upon which Advanced would
implement CIS Infinity, its billing and customer service software, at the City. Included, as
Schedule B 1 in the Agreement is a Statement of Work, which represents a detailed outline of
the implementation, including the methodology and work plan. The estimated costs related
to the implementation are included in Schedule D of the Agreement.
Section 5.1(b) of the Agreement indicates that "Services will be charged to the Organization
at the rates and under the schedule set forth in Schedule D, on a not -to -exceed basis subject to
the maximum cost to the Customer of $173,000.00 as set forth in Schedule." It further states
that, "In no event will the cost to the Organization of the Services exceed the maximum
contract price as set forth in Schedule D, unless agreed upon in advanced in writing signed by
authorized representatives of both parties."
In Section VI of the Statement of Work, Assumption # 6 states that, "Any changes to the
original Statement of Work...will be escalated to the Steering Committee of each company
for resolution. This will include costing and changes to the implementation milestone dates
if applicable."
Section 1.1 (n) of the Agreement outlines the process under a Change Order may be issued to
change particular aspects of the Statement of Work and to cover additional work required to
complete the implementation.
REQUIREMENT FOR A CHANGE ORDER
Based on a number of changes to the original Statement of Work and project plan, it is
evident that the number of hours originally estimated by Advanced as required to complete
each aspect of the implementation will be insufficient. Outlined below are the specific
implementation details which have impacted on the hours used to date, as well as a revised
estimate of the number of hours required to complete the project.
From an overall perspective, the following factors have resulted in a need for additional
hours:
• Project Schedule: A six-month project was originally envisioned, beginning in late
June 2000 with a go live date of January 1, 2001. The project did begin in early July
2000, however, there have been several delays that have resulted in an extended time
CHANGE ORDER NO. 2
CITY OF REDLANDS
Issued April 17, 2001
frame. The current target date for live is July 10, 2001. Based on a twelve-month
implementation rather than a six-month implementation, during which time many
aspects of the implementation continued to progress, the hours in each category will
need to be increased.
• Data Conversion Issues: The inability to extract the City's data on a timely basis has
created the need to deal with issues not normally faced during an implementation of
CIS Infinity. These issues are outlined more fully below, however, this issue has
contributed significantly to the overall project delay.
• Project Management: The overall project management hours required for this project
have been far more significant than anticipated. This issue is outlined further below
however, this issue has impacted on the estimated hours.
On Wednesday, February 7`'', 2001 the members of the Steering Committee met by
teleconference to discuss the status of the Implementation. During that meeting,
representatives of Advanced indicated that it was likely that additional hours would be
required to complete the Implementation, based on the revised Project schedule.
The purpose of this Change Order is to make two significant changes to the Statement of
Work:
1. A revised Project Schedule.
2. Finalization of a process required to ensure a timely conversion of the City's data,
based on the involvement of a third party vendor.
3. Revision of the estimated hours required to complete each aspect of the
implementation, based on the revised Project schedule and the conversion process.
SCOPE OF WORK:
1. REVISED PROJECT SCHEDULE
On February 15, 2001, Renata Anderson, the Project Manager for Advanced provided Janet
Miller, the Project Manager for the City, with a final draft of the revised Project Schedule.
This plan was completed following a significant level of discussion between the City and
Advanced, and several draft plans. Janet Miller provided written approval of this Project
Plan on February 15, 2001. Based on that approval, Advanced and the City began work
toward the completion of the milestones delineated in the plan.
The primary issues which impacted on the requirement to revise the Project Plan were:
2
CHANGE ORDER NO. 2
CITY OF REDLANDS
Issued April 17, 2001
• The delay in the installation of the software from August 2000 (as per the original
project plan) to mid -December 2000. The delay was directly related to the length of
time required to complete the initial extraction of the data and the delay in the
installation of the hardware
• Ongoing delay in determining a workable approach for data extraction
• Finalization of the training plan was delayed for several reasons, including the
requirement that the Advanced training schedule be established around the schedule
set under the SunGard implementation.
Under the Agreement, a change of this magnitude must be approved by the Steering
Committee.
As you are aware from the teleconference held on February 7tt', the delay in the
implementation resulted in a requirement to change the Advanced Project Manager. As a
result of the extended timeframe of the project, the initial Project Manager, Kathryn McKay,
was no longer available for the project. Renata Anderson is now acting as Project Manager.
2. CONVERSION PROCESS
On April 3, 2001, Change Order No. 1 was approved by the City of Redlands. Under this
Change Order, a third party vendor will be responsible for the extraction of the data from a
back up tape provided by the City. The third party vendor will convert the data into Access
files. Advanced will interface directly with the third party vendor to expedite this phase.
Thirty (30) hours were approved in Change Order No. 1 to cover the additional consulting
hours required for Advanced to work with the third party vendor.
As a result of the change in the manner in which the City's data will be extracted, Advanced
will be required to build a new conversion routine to accommodate the files that will be
received from the third party vendor. Specifically, the initial conversion routine written by
Advanced was designed to relate the text files provided by the City to the structures required
by the Advanced CIS Infinity billing and customer service software. The third party vendor
will be providing the extracted data in Access and as such, Advanced will be required to re-
write the original conversion routines. In the long run, the Access files represent a more
efficient approach to the conversion process, however, it requires hours to re -write a routine
that can be used for all remaining conversions.
As at March 31, 2001, there are 65 hours remaining in the conversion category. Advanced
believes that in addition to the remaining 65 hours, another 120 hours will be required to
complete the conversion elements of the implementation.
Advanced is confident in the approach being taken, however, it is important to note that the
third party vendor may have additional requirements following their initial review of the data.
CHANGE ORDER NO. 2
CITY OF REDLANDS
Issued April 17, 2001
Although problems are not anticipated, Advanced feels it is necessary to advise the City of
this possible outcome.
3. SET-UP AND SOFTWARE INSTALLATION AND CONFIGURATION
As of March 31, 2001, the original estimate of the number of hours required to complete the
Set-up and Software Configuration had been exceeded by ninety-three (93) hours. There are
several factors impacting on the hours required in this category:
• The extended project schedule and timeframe (resulting in an extension of the
implementation by a minimum of six months).
• The number of hours dedicated to project management has been much higher than
anticipated. In particular, discussions with the Project Manager for the City have
been considerably more extensive than normally experienced. While this is not a
concern, it was not anticipated and has resulted in the usual number of hours quoted
in this area to be exceeded.
• The City Project Manager has regularly changed the reporting format provided by
Advanced. While this is not a concern, it was not anticipated and has increased the
effort required by Advanced to analyze the issues submitted.
• Business process analysis has been required in some areas, including consolidation of
rates and re -structuring of the account types, which was not anticipated in the original
quote.
At this time, it is anticipated that completion of the set-up and software configuration, as well
as project management will requirement approximately 80 hours per month. Based on the
remaining five months of the implementation, this will require the approval of an additional
400 hours.
TRAINING
As at March 31, 2001, there were 103 hours remaining in the training category. Based
primarily on the extended period of the contract, it is estimated that another 80 hours will be
required to complete a successful training process. In particular, based on the current status
of the project and the need to ensure that users are fully ready to use the system in a live
environment, Advanced would strongly recommend that on -site assistance be available to
users during the critical hard parallel phase, which is upcoming.
4
CHANGE ORDER NO. 2
CITY OF REDLANDS
Issued April 17, 2001
APPROVAL OF ADDITIONAL HOURS
Hours used to Date:
Service/
Estimated Hours
Conversion
Set-up and
Install
Training
Original Hours Estimated in Agreement
250
255
270
Hours Used as at March 31, 2001
185
348
167
Hour R.r.m' .1, 2001.
(5
-93
103
Additional Hours:
Service/
Estimated Hours
Conversion
Set-up and
Install
Training
Original Hours Estimated in Agreement
250
255
270
Add:i:tio:t al 1.:Io. • •s 1 equested in ;1. ang- Ord t• 2
1.20
400
81:1
Revised Total Hours Required for Project
370
655
350
As per the above chart, Advanced is submitting this Change Order in order to request
approval of the Additional Hours as required to complete the project:
Additional Conversion
Additional Set-up:
Additional Training:
$14,400.00 (120 hours x $120.00
$48,000.00 (400 hours x $120.00)
$9,600.00 (80 hours x $120.00)
Additional Cost: $72,000.00
The following chart reflects the initial pricing and the new pricing, based on the hours
included in the change order:
5
CHANGE ORDER NO. 2
CITY OF REDLANDS
Issued April 17, 2001
siek�i..
'77
o
Licenses
Server License
$35,000.00
User License
$45,000.00
Up size to Oracle Database
$ 0.00
$80,000.00
Services
Conversion - Original Agreement Amount
$30,000.00
$30,000.00
Increase due to Change Order No. 1:
Conversion Services by Third Party, Flat Rate
$39,020.00
Conversion - Advanced Consulting
3,600.00
$42,620.00
Increase due to Change Order No. 2:
$14,400.00
$14,400.00
Re -write of Conversion Routine
Set-up and Install -Original Agreement Amount
$30,600.00
$30,600.00
Increase due to Change Order No. 2:
$48, 000.00
$48, 000.00
Project Management, Software
Configuration
$32,400.00
$32,400.00
Training - Original Agreement Amount
$9,600.00
$9,600.00
Increase due to Change Order No. 2:
Additional On -site Training
Total
Total - Original Agreement Amount and
$215,620.00
Change Order No. 1
Total - Increase due to Change Order No. 2
$72,000.00
Total - Including Change Order No. 2
$287,620.00
6
CHANGE ORDER NO. 2
CITY OF REDLANDS
Issued April 17, 2001
PROCEDURAL CHANGES
As noted in the background section of this document, Advanced is required to submit a
Change Order if the total hours estimated for the project are expected to be exceeded. In
doing so, Advanced has prepared its proposal in an attempt to ensure that the hours reflected
are sufficient to complete the implementation. It is the position of Advanced that the Change
Order includes adequate hours to complete the project, however, we are only prepared to
provide this assurance based the commitment by the City that a series of conditions will be
met. If the City and Advanced can reach agreement on the following conditions, Advanced
is confident that a successful implementation is possible within the hours estimated by this
Change Order. Additional hours will only be contemplated if an unexpected situation were
to occur.
The proposed conditions for a successful completion of the project primarily require that the
project management process be streamlined and the hours dedicated to this aspect of the
implementation be controlled more closely. The situation can be better monitored and
controlled through the following approach:
• The City and Advanced will formally appoint Project Sponsors, which for the City
are designated as Bomiie Johnson and Gary Phelps and for Advanced are designated
as Patricia Sorbara and Kathryn McKay. The Project Sponsor will participate in
regular project meetings and will have responsibility to resolve issues that have not
been addressed at the project management level.
• Advanced will provide the City's Project Manager with the information required to
finalize a decision regarding the project. Should the City require additional
information or should the issue remain unresolved between the City and Advanced,
the issue will be escalated for resolution
• Either the City or Advanced can request escalation of an issue. Once requested, the
issue will be brought forward to a meeting of the Project Sponsors.
• The Steering Committees of Advanced and the City will meet every two weeks (via
teleconference) to discuss the progress of the project. At that time, an accounting of
the hours used to date will be provided and any issues that may impact on the project
or the estimated hours will be resolved based on a plan agreed upon by the Steering
Committee.
7
CHANGE ORDER NO. 2
CITY OF REDLANDS
Issued April 17, 2001
• Advanced, with coordination through the respective project managers, will be
provided with the option to have direct contact as required with the technical staff at
the City and with senior users. This option will allow faster resolution of issues in
order to ensure that the timeline contemplated in the current project plan can be met.
For Advanced, the Steering Committee representatives will be Patricia Sorbara, Kathryn
McKay, Philip Playfair (Chief Marketing Officer) and Steven Hammond (Chief Information
Officer). Renata Anderson will continue to act as the Project Manager for Advanced.
Advanced is confident that the City's Steering Committee representatives (Mike Reynolds,
Gary Phelps and Rod Hill) and the representatives from Advanced will ensure resolution of
the issues.
With approval of Change Order No. 2 for the completion of the implementation, Advanced is
committed to completing the project within the hours identified in this Change Order.
CITY OF REDLANDS by: ADVANCED UTILITY SYSTEMS by:
PAT GILBREATH PATRICIA SORBARA
Mayor President and CEO
8
Funding Request - Recycling and Litter Cleanup - On motion of
Councilmember George, seconded by Councilmember Haws, the City Council
authorized submittal of a beverage container recycling and litter cleanup
funding request to the Department of Conservation, Recycling Division by AYE
votes of all present.
Utility Billing Customer Information System - On motion of Councilmember
George, seconded by Councilmember Haws, the City Council authorized
Change Order No, 2 to the software and license implementation agreement with
Advanced Utility Systems Corporation for the City's Utility Billing Customer
Information System by AYE votes of all present.
Minor Subdivision No. 253, Parcel Map No. 15530, - Final Approval - On
motion of Councilmember George, seconded by Councilmember Haws, the City
Council approved, by AYE votes of all present, a subdivision improvement
agreement for Minor Subdivision No. 253, Parcel Map No. 15530, located on
the southeast corner of Redlands Boulevard and New Jersey Street (Essex
Development, applicant). On motion of Councilmember George, seconded by
Councilmember Haws, the City Council granted final approval for Minor
Subdivision No. 253, Parcel Map No. 15530, by AYE votes of all present.
COMMUNICATIONS
Appointments - Redevelopment Advisory Commission - On December 5, 2000,
the City Council approved the reactivation of the Redevelopment Advisory
Commission, Members on this commission must be residents of Redlands and
may not reside or own property within the Redevelopment Area boundaries,
Although several applications have been received, Mayor Gilbreath wanted to
re -advertise the availability of appointments. No action was taken at this
meeting.
Citrus Groves Policy - Mayor Pro Tem George asked the City Council to
authorize exploration of ways to assist "pocket" (five acres or less) citrus groves
especially in relation to the use of domestic water. Councilmember Haws felt
this fell within the recently adopted Citrus Policy. By concurrence, this was
referred to staff for a report.
Regional Transportation Plan - Mayor Pro Tem George reported about the
recently approved Regional Transportation Plan which will carry us to 2025 and
reviewed the contents. Included, as a "baseline project," is the extension of
Metrolink service to Redlands to be completed by 2010. Mayor Pro Tem
George will attempt to move this date up to 2005.
Congressman Jerry Lewis - Mayor Pro Tem George reported on the very
successful Jerry Lewis Appreciation Day held on April 11, 2001, in the Mitten
Building. He expressed his appreciation to the Redlands Allies, Chamber of
April 17, 2001
Page 4