HomeMy WebLinkAboutContracts & Agreements_193-2023FIRST AMENDMENT TO PUBLIC WORKS CONSTRUCTION CONTRACT
This first amendment ("First Amendment") to the Public Works Construction Contract for
the PMP 2022 Street Resurfacing Project dated April 18, 2023 (the "Contract"), by and between
the City of Redlands, a municipal corporation and general law city ("City"), and Matich
Corporation, a California corporation ("Contractor"), is made and entered into this 17th day of
October 2023.
RECITALS
WHEREAS, it is the desire of the City and Contractor to amend their existing Contract,
specifically to amend the time for completion from receipt of notice to proceed two hundred fifteen
(215) calendar days of the contract to December 16, 2023, and
WHEREAS, the City Council approved the contract with contractor for work in accordance
with the Contract Documents for City's PMP 2022 Street Resurfacing Project, Project No. 211006;
NOW, THEREFORE, in consideration of the mutual promises contained herein City and
Contractor agree as follows:
AGREEMENT
Section 1. The time for completion, as set forth in Section 3 of the Contract, is hereby
amended to increase Contractor's time for completion and shall read as follows:
"TIME FOR COMPLETION: The Work shall be completed within two hundred fifteen
(215) calendar days from and after the date of City's issuance of a Notice to Proceed to
Contractor."
Section 2. All other provisions of the Contract shall remain unchanged by this First
Amendment, and in effect.
IN WITNESS WHEREOF, the parties have executed this First Amendment, to be effective
as of the 17th day of October 20
CITY 0 ANDS
Eddie Tejeda, Mayor
ATTEST:
ne Donaldson, City Clerk
By:
Jason
1
I:\cmo\Agreements\Matich Corporation First Amendment FY22-0271.docx-ms
MATICH CORPORATION
/
ice President