HomeMy WebLinkAboutContracts & Agreements_197A-2023THIRD AMENDMENT TO AGREEMENT TO PERFORM PROFESSIONAL SERVICES
This third amendment ("Third Amendment") to the agreement for professional
environmental consulting services ("Agreement"), dated December 7, 2021, by and between the
City of Redlands, a municipal corporation, and a general law city ("City"), and Lilburn
Corporation, a California corporation ("Consultant"), is made and entered into this 18th day of
October 2023.
RECITALS
WHEREAS, the Parties entered into a Professional Services Agreement ("Agreement") on
December 7, 2021, to provide professional environmental consulting services, with the Agreement
expiring on December 31, 2023; and
WHEREAS, the Parties entered into a First Amendment to the Agreement ("First
Amendment") on July 7, 2022; and
WHEREAS, the Parties entered into a Second Amendment to the Agreement ("Second
Amendment") on July 1, 2023; and
WHEREAS, it is the desire of the Parties to amend their existing Agreement, specifically
to update the total compensation to consultant, scope of services, and project costs of the
Agreement.
NOW, THEREFORE, for good and valuable consideration in the receipt of which is hereby
acknowledged City and Consultant agree as follows:
AGREEMENT
Section 1. Article 5 of the Agreement, entitled "Payments to Consultant," is hereby
amended to read as follows:
"5.1 Total compensation for Consultant's performance of the Services shall not exceed the
amount of thirty-eight thousand one -hundred sixty-five dollars ($38,165). City shall pay
Consultant on a time and materials basis up to the not -to -exceed amount in accordance with Exhibit
"B" entitled Project Costs and Hourly Rates" attached hereto and incorporated herein by
reference."
Section 2. Exhibit "A" entitled "Scope of Services" and as described in Article 2.1 and
made part of the First Amendment is hereby replaced with a new Exhibit "A", which is attached
hereto and incorporated herein and into the Agreement by this reference.
Section 3. Exhibit `B" entitled "Project Costs and Hourly Rates" and as described in Article
5.1 and made part of the Agreement is hereby replaced with a new Exhibit `B", which is attached
hereto and incorporated herein and into the Agreement by this reference.
1
I:\cmo\Agreeements\Lilbum Comomtion Third Amendment FY22-0278.docx-ms
Section 4. All other provisions of the Agreement and the Second Amendment shall remain
unchanged by this Third Amendment and in effect.
Section 5. This Amendment may be executed in counterparts, each of which shall be
deemed an original, but all of which, together, shall constitute one and the same instrument.
IN WITNESS WHEREOF, the parties have executed this Third Amendment, to be
effective as of October 18, 2023.
CITY OF &F•DLANDS
rL
4Crles M. Duggan, Jr., City Manager
ATTEST:
nlne Donaldson, City Clerk
LILBURN CORPORATION
By:
2
1:1cmolAgreements1Li16um Corporation Third Amendment FY22-0278.docx-ms
l�
Cheryl A bbs, Vice President
Exhibit "A"
Scope of Services
IApproach and Methodology
The City of Redlands is requesting the services of an environmental consulting firm to prepare and
process a California Environmental Quality Act (CEQA) document for a proposed residential
development in the eastern portion of the City. Our methodology for preparation of the CEQA
Initial Study, public review noticing, and presence at public hearings, as requested in the City's
Scope Request is described herein. Our scope of work will lead to the City's adoption of a CEQA
document that will provide for future development of the project. The City currently expects that
the proposed project would comply with CEQA with preparation of an Initial Study/Mitigated
Negative Declaration.
Our overall approach is summarized below. Following this summary, the tasks required are
described in detail.
❑ Meet with City and Applicant to Review Proposed Project
❑ Prepare a Comprehensive Project Description for use in the Initial Study
❑ Review Applicant's Technical Studies for Biological and Cultural Resources, and Traffic
Impacts
❑ Prepare Draft Initial Study and Mitigation Monitoring and Reporting Program (MMRP)
o Finalize Initial Study and MMRP
o Prepare required CEQA notices including Notice of Intent (NOI), Notice of Completion
(NOC) and SCH Summary Form
❑ Submit Notices to State Clearinghouse electronically and produce and Circulate Initial
Study as directed by City
o Review and Discuss Comments Received on Document; prepare or assist City staff with
Responses
❑ Prepare Mitigated Negative Declaration for City adoption
❑ Meet with City staff prior to public hearing(s)
o Attend up to four public hearings to support City staff
o File Notice of Determination (NOD) with the San Bernardino County Clerk of the Board
❑ Provide monthly progress reports and invoices
TASK 1: MEET WITH PROJECT APPLICANT AND CITY; REVIEW PROPOSED
PROJECT AND OBJECTIVES
The purpose of this task is to collect and review all pertinent background data necessary to conduct
the environmental analysis. It will be necessary to obtain sufficient design detail and site
disturbance information to conduct an adequate environmental evaluation. We will review the Site
Plan, Grading Plan, and Landscape Plan, as well as the project objectives. Any focused technical
3
1:\Gino \Agreements\Lilburn Corpomtion Third Amendment FY22-0278,docx-ms
studies provided to the City by the Applicant will be obtained during the meeting for incorporation
into the Initial Study.
TASK 2: DEVELOP PROJECT DESCRIPTION
In this task we will prepare a CEQA Project Description for use in the Initial Study and for
reviewing and preparing the technical reports. The Project Description will be developed in
cooperation with City staff and the Applicant. The Project Description will include a summary of
the project as proposed, a discussion of the existing conditions of the site and vicinity, a discussion
of the site plans, and graphics. The graphics prepared for use in the Initial Study will be based in
part on exhibits prepared to date by the project designers and engineers. Lilburn Corporation will
review the Applicant's architectural renderings for adequacy in portraying changes in the visual
character of the site. We will photograph the site to document surrounding land uses and current
site conditions. Final approval of the Project Description will be provided by the City.
TASK 3: PEER REVIEW FOCUSED STUDIES
The City of Redlands will provide Lilburn Corporation with three technical studies that will be
prepared by the Applicant. Our subconsultants will provide a peer review of those studies. Lilburn
Corporation will provide the City with peer review memos summarizing results of the reviews for
each of the studies. We have included sub consulting firms that are authorized by the City to
prepare focused studies; 1) ELMT Consulting, hie. for biological resources surveys, trapping, and
habitat assessments; 2) Brian F. Smith for cultural resources; and 3) Ganddini Group, Inc. for
traffic.
TASK 4: PREPARE INITIAL STUDY & MMRP
Based on the findings of the technical studies prepared and reviewed, and the information
contained in the Project Description, we will prepare an Administrative Draft Initial Study to
evaluate all potential environmental impacts associated with the proposed project.
We will utilize the City's current format for an Initial Study. The Initial Study will include mitigation
measures for any identified significant or potentially significant impacts, and supporting
documentation as required. We will incorporate relevant and available information from the site visit
and the technical studies. Revisions to the Site Plan received after this work is initiated may result in
changes/updates being required for the IS. The August 2023 update to the Site Plan resulted in a
change to the lettered lots, sizes and quantity. In addition to the Project Description the Air Quality
and Greenhouse Gas sections of the IS will need to be updated. Lilburn Corporation will update the
completed Air Quality/Greenhouse Gas Analysis that was based on the Ca1EEMod v. 2020, using the
most recent version, which is 2022 and incorporating an updated construction schedule.
Lilburn Corporation will address all CEQA and City -required environmental resource areas. We
will summarize and incorporate the findings of all technical studies provided to us. We will assist
Planning staff with identifying and/or refining any necessary mitigation measures that would result
from the City's consultation with local Native American Tribes. Mitigation measures would be
incorporated as necessary into the Initial Study to address potential impacts during the Project's
construction phase.
4
I:\cmo\Agreements\Lilburn Corporation Third Amendment FY22-0278.docx-ms
Lilburn Corporation will submit the Administrative Initial Study electronically for the City's
review. The City will then provide comments/revisions to Lilburn Corporation. Following
completion of the review by staff, we will revise the document as necessary and prepare a final draft
Initial Study. We will also prepare a Mitigation Monitoring and Reporting Program (MMRP) to
include mitigation measures identified. The MMRP will be circulated as part of the Initial Study.
The City may conduct a final review before determining the document is ready to release for public
review.
Notices and Circulation: Upon approval of the Initial Study, Lilburn Corporation will prepare
notices for the City to conduct a 30-day public review. Our cost estimate includes the preparation
of the Notice of Completion and Notice of Intent. We will also be responsible for circulating the
document electronically to the State Clearinghouse along with the Summary Form for Electronic
Submittal, and to responsible and trustee agencies, and other interested agencies/parties including
Tribal Governments. The City will prepare and publish the legal notice in the Redlands Daily Facts
(or other newspaper of general circulation). We will also prepare a Notice of Availability (NOA)
for the City's distribution as required.
TASK 5: FINAL DOCUMENTS
Upon completion of the public review process, we will discuss any comments received with City
staff and determine appropriate responses and prepare letters for the City to submit to the
commenters. Lilburn Corporation would discuss with the City any substantive changes that should
be made to the project or the Initial Study as a result of the comments received. We will also
update the MMRP as necessary in consideration of any public input that results in City changes to
mitigation measures.
Lilburn Corporation will prepare the Notice of Determination (NOD) and upon City approval, we
will file the notice, if requested with the County Clerk of the Board. The Applicant will provide a
check for the applicable NOD filing fees.
TASK 6: PROJECT MANAGEMENT & MEETINGS
Throughout the project, coordination with the City will be regularly initiated to discuss results of
analyses, obtain additional information as necessary, resolve any contract administration issues, and
provide schedule updates. We will attend a kick-off meeting and will participate in regular conference
calls if directed.
Lilburn Corporation will attend a staff meeting to discuss the final CEQA document and findings
prior to public hearings that will be scheduled with the Planning Commission (PC) and possibly
City Council. Our Fee Proposal includes attendance at up to four public hearings.
5
C\cmo\Agreements\Lilburn Corporation Third Amendment FY22-0278.docx-ms
Exhibit "B"
Project Costs and Hourly Rates
Cost Estimate for Environmental Consulting Services
Initial Study for TTM No. 20402
City of Redlands
COST CATEGORY
Principal,
Project
Dieetar
TASKS
Task 1: Site Visit, Kick-off Mfg w/ City & Applicant
Project
Manager
Slg0tn.
Sr.
Emaon.
Analyst
$18MMIr.
LABOR
Env mt.
Analyst
4984r
3
Docun ent
Manager
St23rlr
Hems
7
Costa
$1,059
Subconsufanta
Other Dkect
Cots
(.ane dwatl 3)
523
$1.082
Task 2: CHQAProject Description
1
2
4
$683
$683
Task 3: Pea Review Technical Shidies
2
$450
$5,900
$6,350
Task 4: Initial Study & Notices for Public Review
24
21
105
4
157
$19,557
$2,300
$21,857
Task 5: Final Docnments7AMAMRP/NOD
6
10
4
21
$2.777
$2,777
Task 6: Project Mgmt., Staf£Mte
Public Hauings (4)
)TAL TASKS ` j
4
24
2
I'
30
$5.416
529,942
$8,223
$5,416
$38,165
a Subconsultants
a Includes SBK11 Protocol Trapping