HomeMy WebLinkAboutContracts & Agreements_20-2026STATE OF CALIFORNIA • DEPARTMENT OF TRANSPORTATION
NOTICE TO OWNER
DOT RW 13-04 (REV 02/2024) Page 1 of 2
NOTICE TO OWNER
Number 08-001141-01
District
County
Route
Post Mile
Project ID
EA
08
SB
210
32.84
0825000058
1 R400
FEDERAL AID NUMBER
N/A
OWNER'S FILE NUMBER
Caltrans Improvement Projects Route SBD 210
DATE
FREEWAY
02/12/2026
® YES NO
To: -
City of Redlands
Municipal Utilities & Engineering Department 35 Cajon Street, Suite 15A
Redlands, CA 92373
909-798-7698
Because of the State Highway construction project:
Construct a sidewalk on the south side of Lugonia Ave to facilitate continuous ADA pedestrian access. Construct an ADA curb ramp on the
southwest corner of Lugonia Ave and add a crosswalk.
Which affects your facilities:
Existing water facilities within the limits of the State's proposed construction project; Fire hydrant, Water vault cover, Air release valve
You are hereby ordered to:
Abandon existing fire hydrant, Adjust water vault cover, Remove and relocate air release valve per Caltrans approved relocation plans " City
of Redlands Municipal Utilities and Engineering Department" 3 sheets dated 11/21/2025.
Your work schedule shall be as follows:
Coordinate relocation work with State Relocation Inspector, Qays Aldulaimi (909) 519-0547. Relocations are to be completed
before construction of 07/24/2026. Adjustments to be completed during construction 07/24/2026 - 10/15/2026
Liability for the cost of the work is:
100% State
per City of Redlands superior and prior right.
Americans with Disabilities Act (ADA) Notice: This document is available in alternative accessible formats. For more information, please contact the Forms
Management Unit at (279) 234-2284, TTY 711, in writing at Forms Management Unit, 1120 N Street, MS-89, Sacramento, CA 95814, or by email at Forms.
Management. Un it(7a,dot.ca.gov.
STATE OF CALIFORNIA • DEPARTMENT OF TRANSPORTATION
NOTICE TO OWNER
DOT RW 13-04 (REV 02/2024)
Notify Qays Aldulaimi at telephone number (909) 519-0547, 72 hours prior to initial start of work, and 24 hours prior to
subsequent restart when your work schedule is interrupted.
DISTRICT DIRECTOR
DISTRICT DIVISION CHIEF
Page 2 of 2
BY Ga0tzf,�G
STRICT UTILITY COORDINATOR
CC: Resident Engineer
Permits
R/W
THIS NOTICE DOES NOT CONSTITUTE A PERMIT. OBTAIN AN ENCROACHMENT PERMIT BEFORE STARTING WORK.
The Parties agree that this Notice to Owner will set forth the terms, covenants, and conditions that are mutually agreed upon by the
parties, and that the Notice to Owner shall constitute the written agreement required by 23 CFR 645.113 ("Written Agreement').
Owner must submit all reimbursement and other payment claims arising from this Notice to Owner to Caltrans within 365 calendar
days of the completion of the relocation (the "Claim Period"), and Owner waives, releases, and forfeits all right to reimbursement and
any other payment for any claims that are submitted after the Claim Period.
Americans with Disabilities Act (ADA) Notice: This document is available in alternative accessible formats. For more information, please contact the Forms
Management Unit at (279) 234-2284, TTY 711, in writing at Forms Management Unit, 1120 N Street, MS-89, Sacramento, CA 95814, or by email at Forms.
Management.Unit(_)dot.ca.gov.
STATE OF CALIFORNIA • DEPARTMENT OF TRANSPORTATION Page 1 of 4
UTILITY AGREEMENT
DOT RW 13-05 (REV 10/2025)
DISTRICT COUNTY ROUTE POST MILE PROJECT ID
08 San Bernardino 210 32.84 0825000058
FEDERAL AID NUMBER OWNER'S FILE NUMBER
N/A Caltrans Improvement Projects Route SBD 210
FEDERAL PARTICIPATION/FEDERALLY ELIGIBLE/NEPA DOCUMENT
On the Project ❑ Yes ® No On the Utilities ❑ Yes ® No
Owner Payee Data No. 0000023379 or Form STD 204 is attached. ❑
UTILITY AGREEMENT NO. 08-001141-01 DATE 02/18/2026
The State of California, acting by and through the Department of Transportation, hereinafter called "STATE," proposes to Caltrans
Improvement Projects Route SBD 210
and
NAME City of Redlands
ADDRESS 35 Cajon Street, Suite 15A Redlands CA 92373
hereinafter called "OWNER," owns and maintains Fire hydrant, Water vault cover, Air release valve
within the limits of STATE's project which requires
The City of Redlands to abandon 1 fire hydrant, adjust water vault cover, remove and relocate air release valve
to accommodate STATE's project.
It is hereby mutually agreed that:
I. WORK TO BE DONE
In accordance with Notice to Owner No. 08-001141-01 dated 02/12/2026, OWNER shall abandon existing fire hydrant, adjust water
vault cover and remove and relocate air release valve. All work shall be performed substantially in accordance with OWNER's Plan
No. City of Redlands Municipal Utilities and Engineering Department dated Nov 11, 2025 consisting of 3 sheets, a copy of which is on
file in the District office of the Department of Transportation at 464 W 4th St San Bernardino CA 92401. Deviations from the OWNER's
plan described above initiated by either the STATE or the OWNER, shall be agreed upon by both parties hereto under a Revised
Notice to Owner. Such Revised Notices to Owner, approved by the STATE and agreed to/acknowledged by the OWNER, will
constitute an approved revision of the OWNER's plan described above and are hereby made a part hereof. No work under said
deviation shall commence prior to written execution by the OWNER of the Revised Notice to Owner. Changes in the scope of the
work will require an amendment to this Agreement in addition to the revised Notice to Owner.
Ili. LIABILITY FOR WORK
Existing facilities are located in their present position pursuant to rights superior to those of the STATE and will be relocated at
STATE expense.
III. PERFORMANCE OF WORK
OWNER agrees to perform the herein described work with its own forces or to cause the herein described work to be performed by
the OWNER's contractor, employed by written contract on a continuing basis to perform work of this type, and to provide and furnish
all necessary labor, materials, tools, and equipment required therefore, and to prosecute said work diligently to completion.
(a) Work performed by OWNER's contractor is a public work under the definition of Labor Code Section 1720(a) and is therefore
subject to prevailing wage requirements.
(b)Work performed directly by Owner's employees falls within the exception of Labor Code Section 1720(a)(1) and does not constitute
a public work under Section 1720(a)(2) and is not subject to prevailing wages. OWNER shall verify compliance with this requirement
in the administration of its contracts referenced above.
Americans with Disabilities Act (ADA) Notice: This document is available in alternative accessible formats. For more information, please contact the Forms Management
Unit at (279) 234-2284, TTY 711, in writing at Forms Management Unit, 1120 N Street, MS-89, Sacramento, CA 95814, or by email at Forms. Management. Unit@dot.ca.gov.
STATE OF CALIFORNIA • DEPARTMENT OF TRANSPORTATION Page 2 of 4
UTILITY AGREEMENT UTILITY AGREEMENT NO.
DOT RW 13-05 (REV 10/2025) 08-001141-01
Use of personnel requiring lodging and meal 'per diem' expenses shall not exceed the per diem expense amounts allowed under the California
Department of Human Resources travel expense guidelines. Accounting Form FA-1301 is to be completed and submitted for all non -State
personnel travel per diem. Owner shall also include an explanation why local employee or contract labor is not considered adequate for the
relocation work proposed.
IV. PAYMENT FOR WORK
The STATE shall pay its share of the actual and necessary cost of the herein described work within 45 days after receipt of OWNER's itemized
bill, signed by a responsible official of OWNER's organization and prepared on OWNER's letterhead, compiled on the basis of the actual
and necessary cost and expense incurred and charged or allocated to said work in accordance with the uniform system of accounts prescribed
for OWNER by the California Public Utilities Commission, Federal Energy Regulatory Commission or Federal Communications Commission,
whichever is applicable. It is understood and agreed that the STATE will not pay for any betterment or increase in capacity of OWNER's
facilities in the new location and that OWNER shall give credit to the STATE for the accrued depreciation of the replaced facilities and for the
salvage value of any material or parts salvaged and retained or sold by OWNER.
Not more frequently than once a month, but at least quarterly, OWNER will prepare and submit detailed itemized progress bills for costs
incurred not to exceed OWNER's recorded costs as of the billing date less estimated credits applicable to completed work. Payment of
progress bills not to exceed the amount of this Agreement may be made under the terms of this Agreement. Payment of progress bills which
exceed the amount of this Agreement may be made after receipt and approval by STATE of documentation supporting the cost increase and
after an Amendment to this Agreement has been executed by the parties to this Agreement.
The OWNER shall submit a final bill to the STATE within 360 days after the completion of the work described in Section I above. If the STATE
has not received a final bill within 360 days after notification of completion of OWNER's work described in Section I of this Agreement, and
STATE has delivered to OWNER fully executed Director's Deeds, Consents to Common Use or Joint Use Agreements for OWNER's facilities (if
required), STATE will provide written notification to OWNER of its intent to close its file within 30 days. OWNER hereby acknowledges, to the
extent allowed by law, that all remaining costs will be deemed to have been abandoned. If the STATE processes a final bill for payment more
than 360 days after notification of completion of OWNER's work, payment of the late bill may be subject to allocation and/or approval by the
California Transportation Commission.
The final billing shall be in the form of a detailed itemized statement of the total costs charged to the project, less the credits provided for in this
Agreement, and less any amounts covered by progress billings. However, the STATE shall not pay final bills which exceed the estimated cost
of this Agreement without documentation of the reason for the increase of said cost from the OWNER and approval of documentation by
STATE. Except, if the final bill exceeds the OWNER's estimated costs solely as the result of a revised Notice to Owner as provided for in
Section I, a copy of said revised Notice to Owner shall suffice as documentation. In either case, payment of the amount over the estimated cost
of this Agreement may be subject to allocation and/or approval by the California Transportation Commission.
In any event if the final bill exceeds 125% of the estimated cost of this Agreement, an Amended Agreement shall be executed by the parties to
this Agreement prior to the payment of the OWNER'S final bill. Any and all increases in costs that are the direct result of deviations from the
work described in Section I of this Agreement shall have the prior concurrence of STATE.
Detailed records from which the billing is compiled shall be retained by the OWNER for a period of three years from the date of the final
payment and will be available for audit by State and/or Federal auditors. In performing work under this Agreement, OWNER agrees to comply
with the Uniform System of Accounts for Public Utilities found at 18 CFR, Parts 101, 201, et al., to the extent they are applicable to OWNER
doing work on the project that is the subject of this agreement, the contract cost principles and procedures as set forth in 48 CFR, Chapter 1,
Subpart E, Part 31, et seq., 23 CFR, Chapter 1, Part 645 and 2 CFR, Part 200, et al. If a subsequent State and/or Federal audit determines
payments to be unallowable, OWNER agrees to reimburse AGENCY upon receipt of AGENCY billing. If OWNER is subject to repayment due to
failure by State/Local Public Agency (LPA) to comply with applicable laws, regulations, and ordinances, then State/LPA will ensure that
OWNER is compensated for actual cost in performing work under this agreement.
V. GENERAL CONDITIONS
All costs accrued by OWNER as a result of STATE's request of 10/03/2025 to review, study and/or prepare relocation plans and
estimates for the project associated with this Agreement may be billed pursuant to the terms and conditions of this Agreement.
If STATE's project which precipitated this Agreement is canceled or modified so as to eliminate the necessity of work by OWNER, STATE will
notify OWNER in writing and STATE reserves the right to terminate this Agreement by Amendment. The Amendment shall provide mutually
acceptable terms and conditions for terminating the Agreement.""AII obligations of STATE and/or LPA under the terms of this Agreement
are subject to the acceptance of the Agreement by LPA Board of Directors or the Delegated Authority (as applicable), the passage of the
annual Budget Act by the State Legislature, and the allocation of those funds by the California Transportation Commission.
"OWNER shall submit a Notice of Completion to the STATE within 30 days of the completion of the work described herein.
Americans with Disabilities Act (ADA) Notice: This document is available in alternative accessible formats. For more information, please contact the Forms Management
Unit at (279) 234-2284, TTY 711, in writing at Forms Management Unit, 1120 N Street, MS-89, Sacramento, CA 95814, or by email at Forms. Management. Unit@dot.ca.gov.
STATE OF CALIFORNIA • DEPARTMENT OF TRANSPORTATION Page 3 of 4
UTILITY AGREEMENT UTILITY AGREEMENT NO.
DOT RW 13-05 (REV 10/2025) 08-001141-01
VI. OIL COMPANY
VII. BUY AMERICA
OWNER understands and acknowledges that this project is subject to the requirements of the Buy America law (23 U.S.C., Section 313) and
applicable regulations, including 23 CFR 635.410, 2 CFR 184 and 2 CFR 200.322 and FHWA guidance, and will demonstrate Buy America
compliance by collecting written certifications) from the vendor(s) or by collecting written certification(s) from the manufacturer(s) i.e. mill test
report (MTR)or letter from Manufacturer on company letter head with an authorized representative signature stating the following, "All
manufacturing processes for these materials, including the application of coatings, have occurred in the United States.""AII documents obtained
to demonstrate Buy America compliance will be held by the OWNER for a period of three (3) years from the date of final payment to the
OWNER and will be made available to STATE or FHWA upon request." "One set of copies of all documents obtained to demonstrate Buy
America compliance will be attached to, and submitted with, the final invoice." "This does not include products for which waivers have been
granted under 23 CFR 635.410, 2 CFR 184, or other applicable provisions.
I agree that by providing my electronic signature for this form, I agree to conduct business transactions by electronic means and that my electronic
signature is the legal binding equivalent to my handwritten signature. I hereby agree that my electronic signature represents my execution or
authentication of this form, and my intent to be bound by it.
IN WITNESS WHEREOF, the above parties have executed this Agreement the day and year above written.
STATE: OWNER:
d J
By By i► r��^�b
Name Christine Senteno Date Name MAF,%o SAUIGC-DO Date
Title Deputy District Director RW & LS
APPROVAL RECOMMENDED:
Name fames Randy Davis
Title District Utility Coordinator
Title M A y p (L
2/23/2026 By Z�
Date Name Goutam K. Dobey Date
Title City Engineer
THIS AGREEMENT SHALL NOT BE EXECUTED BY THE STATE OF CALIFORNIA - DEPARTMENT OF TRANSPORTATION UNTIL
FUNDS ARE CERTIFIED.
Americans with Disabilities Act (ADA) Notice: This document is available in alternative accessible formats. For more information, please contact the Forms Management
Unit at (279) 234-2284, TTY 711, in writing at Forms Management Unit, 1120 N Street, MS-89, Sacramento, CA 95814, or by email at Forms. Management. Unit@dot.ca.gov.
STATE OF CALIFORNIA • DEPARTMENT OF TRANSPORTATION
Page 4 of 4
U I ILI I Y AGREEMENT
DOT RW 13-05 (REV 10/2025)
UTILITY AGREEMENT NO.
08-001141-01
CT
DOCUMENT
EVENT
TYPE
DEPT
UNIT
PROJECT
ID
PHASE
REPORTING
OBJ CODE (N)
BFY
AMOUNT
C401
2660
9
C401
2660
9
C401
2660
9
I agree that by providing my electronic signature for this form, I agree to conduct business transactions by electronic means and that my electronic
signature is the legal binding equivalent to my handwritten signature. I hereby agree that my electronic signature represents my execution or
authentication of this form, and my intent to be bound by it.
PROJECT ID FUNDING VERIFIED: REVIEW / REQUEST FUNDING:
Sign: Sign: 14"�a.d�
Print: Print: Sergio Kasten 2/23/2026
R/W Planning and Management Date Utility Coordinator Date
THE ESTIMATED COST TO THE STATE FOR ITS SHARE OF THE ABOVE -DESCRIBED WORK IS $20,680.00
CERTIFICATION OF FUNDS
I hereby certify upon my own personal knowledge that
budgeted funds are available for the period and purpose
of the expenditure shown here.
R/W Planning and Management
Date
ITEM
CHAP
STAT
FY
AMOUNT
Distribution: 2 originals to RAN Accounting
1 original to Utility Owner
1 original to Utility File
FUND TYPE
PROJECT ID AMOUNT
Design Funds
$
Construction Funds
$
R/W Funds
0825000058 $ 20,680.00
Americans with Disabilities Act (ADA) Notice: This document is available in alternative accessible formats. For more information, please contact the Forms Management
Unit at (279) 234-2284, TTY 711, in writing at Forms Management Unit, 1120 N Street, MS-89, Sacramento, CA 95814, or by email at Forms. Management. Unit@dot.ca.gov.
CW
10+00
--------------- . .....
-------------------------
R /W
F H TO BE Rel
BY OTHERS (CORW-3)—/
ITY TO ABANDON
IRE HYDRANT
F IRE?
WEST LUG O AVENUE)
H.H
I I + 0 0.1-0
w
>
VE
-- --------- ----
PROP
FAII 1,
INovember 21, 2025
STATE OF CAUIPORNIk
DEPARTAIL-N-F OF TRAMP ORTJkTI011s-
CALTRANS
DISMCT 8 - DESIGN
%NT'
LLJ
w
r-cw
A."rl%WVED
November 21, 2025
STATE OF CALEPOW
DEPARTMENT OF TRANSPORTATION
CALTRANS
DISTRICT 8 DESIG1.
-WET L U G 0 -V XAVENUE
w
APPROVED
November 21, 2025
STATIF OF ('ALtF0WlA
DEPARTMENT OF TKINSFORTATION
CALTRANS
DISTRICT 8 DESIGN
10