HomeMy WebLinkAboutContracts & Agreements_172-2026AGREEMENT TO PERFORM PROFESSIONAL SERVICES
This agreement for the provision of Professional Environmental Services to Implement
the Alabama Street Septage Ponds Remedial Action Plan ("Agreement") is made and entered in
this 1st day of September, 2026 ("Effective Date"), by and between the City of Redlands, a
municipal corporation ("City") and Rincon Consultants, Inc. a California corporation.
("Consultant"). City and Consultant are sometimes individually referred to herein as a "Party"
and, together, as the "Parties." In consideration of the mutual promises contained herein, City
and Consultant agree as follows:
ARTICLE 1 — ENGAGEMENT OF CONSULTANT
1.1 City hereby engages Consultant to provide professional environmental services related to
the implementation of the Alabama Street Septage Ponds Remedial Action Plan services
for City (the "Services").
1.2 The Services shall be performed by Consultant in a professional manner, and Consultant
represents that it has the skill and the professional expertise necessary to provide the
Services to City at a level of competency presently maintained by other practicing
professional consultants in the industry providing like and similar types of Services.
ARTICLE 2 — SERVICES OF CONSULTANT
2.1 The Services that Consultant shall perform are more particularly described in Exhibit
"A," titled "Scope of Services," which is attached hereto and incorporated herein by this
reference.
2.2 Consultant shall comply with applicable federal, state and local laws and regulations in
the performance of this Agreement including, but not limited to, any applicable State
prevailing wage laws.
ARTICLE 3 — RESPONSIBILITIES OF CITY
3.1 City designates Monica Heredia, Municipal Utilities and Engineering Director, as City's
representative with respect to performance of the Services, and such person shall have the
authority to transmit instructions, receive information, interpret and define City's policies
and decisions with respect to performance of the Services.
ARTICLE 4 — PERFORMANCE OF SERVICES
4.1 Consultant shall perform and complete the Services in a prompt and diligent manner in
accordance with the schedule set forth in Exhibit "B," titled "Project Schedule," which is
attached hereto and incorporated herein by reference.
4.2 The term of this Agreement shall be for a period of three (3) years commencing as of the
Effective Date, unless terminated earlier as provided herein.
1
1Acuno\Agreement9\Rincon Professional Services Agreement.bm.08.19.2026.FY2728-29.doc
4.3 If Consultant's Services include deliverable electronic visual presentation materials, such
materials shall be delivered in a form, and made available to City, consistent with City
Council -adopted policy for the same. It shall be the obligation of Consultant to obtain a
copy of such policy from City staff.
ARTICLE 5 — PAYMENTS TO CONSULTANT
5.1 Total compensation for Consultant's performance of the Services shall not exceed the
amount of six hundred forty thousand ($640,000.00). City shall pay Consultant on a time
and materials basis up to the not to exceed amount in accordance with Exhibit "C," titled
("Fee Schedule") which is attached hereto and incorporated herein by reference.
5.2 Consultant shall submit monthly invoices to City describing the Services performed
during the preceding month. Consultant's invoices shall include a brief description of the
Services performed, the dates the Services were performed, the number of hours spent
and by whom, and a description of reimbursable expenses related to the Services. City
shall pay Consultant no later than thirty (30) days after receipt and approval by City of
Consultant's invoice.
5.3 Any notice or other communication required, or which may be given, pursuant to this
Agreement, shall be in writing. Any such notice shall be deemed delivered (i) on the date
of delivery in person; (ii) five (5) days after deposit in first class registered mail, with
return receipt requested; (iii) on the actual delivery date if deposited with an overnight
courier; or (iv) on the date sent by facsimile or electronic mail transmission (including
PDF), if confirmed with a copy sent contemporaneously by first class, certified,
registered or express mail; in each case properly posted and fully prepaid to the
appropriate address set forth below, or such other address as a Party may provide notice
in accordance with this section:
CITY:
CONSULTANT:
City Clerk
Ryan Thacher, Principal
City of Redlands
Rincon Consultants, Inc.
35 Cajon Street
2060 Knoll Drive
P.O. Box 3005 (mailing)
Ventura, CA 93003
Redlands, CA 92373
rthacher@rineonconsultants.com
jdonaldson@cityofredlands.org
Phone:831-566-3081
Phone: (909) 798-7531
ARTICLE 6 — INSURANCE AND INDEMNFICATION
6.1 The following insurance coverage required by this Agreement shall be maintained by
Consultant for the duration of its performance of the Services. Consultant shall not
perform any Services unless and until the required insurance listed below is obtained by
Consultant. Consultant shall provide City with certificates of insurance and endorsements
I:\cmo\Agreements\Rincon Professional Services AgreemenLbm.08.19.2026.FY2728-29.doe
evidencing such insurance prior to commencement of the Services. Insurance policies
shall include a provision prohibiting cancellation or modification of the policy except
upon thirty (30) days prior written notice to City.
A. Workers' Compensation and Employer's Liability insurance in the amount that meets
statutory requirements with an insurance carrier acceptable to City, or certification to
City that Consultant is self -insured or exempt from dhe workers' compensation laws
of the State of California. Consultant shall execute and provide City with Exhibit
"D," titled "Workers' Compensation Insurance Certification," which is attached
hereto and incorporated herein by this reference, prior to performance of the Services.
B. Comprehensive General Liability insurance with carriers acceptable to City in the
minimum amount of One Million Dollars ($1,000,000) per occurrence and Two
Million Dollars ($2,000,000) aggregate, for public liability, property damage and
personal injury is required. City shall be named as an additional insured and such
insurance shall be primary and non-contributing to any insurance or self-insurance
maintained by City.
C. Consultant shall secure and maintain professional liability insurance throughout the
term of this Agreement in the amount of One Million Dollars ($1,000,000) per claim
made.
D. Business Auto Liability coverage, with minimum limits of One Million Dollars
($1,000,000) per occurrence, combined single limit bodily injury liability and
property damage liability. This coverage shall include all Consultant owned vehicles
used in connection with Consultant's provision of the Services, hired and non -owned
vehicles, and employee non -ownership vehicles. City shall be named as an additional
insured and such insurance shall be primary and non-contributing to any insurance or
self-insurance maintained by City.
E. Consultant is expressly prohibited from assigning or subcontracting any of the
Services without the prior written consent of City. In the event of mutual agreement
by the Parties to assign or subcontract a portion of the Services, Consultant shall add
such assignee or subcontractor as an additional insured to the insurance policies
required hereby and provide City with the insurance endorsements prior to any
Services being performed by the assignee or subcontractor.
6.2 Consultant shall defend, indemnify and hold harmless City and its elected and appointed
officials, employees and agents from and against any and all claims, losses or liability,
including attorneys' fees, arising from injury or death to persons or damage to property
occasioned by any negligent act or omission by, or the willful misconduct of, Consultant,
or its officers, employees and agents in performing the Services.
ARTICLE 7 — CONFLICTS OF INTEREST
3
1:\cmo\AgiccmenIs\Rinwn Professional Seivices Agieemcnlbm.08.19.2026.PY2728-29.doe
7.1 Consultant covenants and represents that it does not have any investment or interest in
any real property that may be the subject of this Agreement or any other source of
income, interest in real property or investment that would be affected in any mammr or
degree by the performance of Consultant's Services. Consultant further covenants and
represents that in the performance of its duties hereunder, no person having any such
interest shall perform any Services under this Agreement.
7.2 Consultant agrees it is not a designated employee within the meaning of the Political
Reform Act because Consultant:
A. Does not make a governmental decision whether to:
(i) approve a rate, rule or regulation, or adopt or enforce a City law;
(ii) issue, deny, suspend or revoke any City permit, license, application,
certification, approval, order or similar authorization or entitlement;
(iii) authorize City to enter into, modify or renew a contract;
(iv) grant City approval to a contract that requires City approval and to which
City is a party, or to the specifications for such a contract;
(v) grant City approval to a plan, design, report, study or similar item;
(vi) adopt, or grant City approval of, policies, standards or guidelines for City
or for any subdivision thereof.
B. Does not serve in a staff capacity with City and in that capacity, participate in
making a governmental decision or otherwise perform the same or substantially
the same duties for City that would otherwise be performed by an individual
holding a position specified in City's Conflict of Interest Code under Government
Code section 87302.
7.3 In the event City determines that Consultant must disclose its financial interests,
Consultant shall complete and file a Fair Political Practices Commission Form 700,
Statement'of Economic Interests, with the City Clerk's office pursuant to the written
instructions provided by the City Clerk.
ARTICLE 8 — GENERAL CONSIDERATIONS
8.1 In the event any action is commenced to enforce or interpret any of the terms or
conditions of this Agreement the prevailing Party shall, in addition to any costs and other
relief, be entitled to the recovery of its reasonable attorneys' fees, including fees for the
use of in-house counsel by a Party.
8.2 Consultant shall not assign any of the Services, except with the prior written approval of
City and in strict compliance with the terms and conditions of this Agreement. Ally
assignment or attempted assignment without such prior written consent may, in the sole
discretion of City, result in City's immediate termination of this Agreement.
4
lAcmo\Agreements\Rincon Professional Services Agreement.bm.08.19.2026.FY2728-29.doe
8.3 Consultant is for all purposes under this Agreement an independent contractor and shall
perform the Services as an independent contractor. Neither City nor any its agents shall
have control over the conduct of Consultant or Consultant's employees, except as herein
set forth. Consultant shall supply all necessary tools and instrumentalities required to
perform the Services. Assigned personnel employed by Consultant are for its account
only, and in no event shall Consultant or personnel retained by it be deemed to have been
employed by City or engaged by City for the account of, or on behalf of City. Consultant
shall have no authority, express or implied, to act on behalf of City in any capacity
whatsoever as an agent, nor shall Consultant have any authority, express or implied, to
bind City to any obligation.
8.4 This Agreement may be terminated by City, in its sole discretion, by providing not less
than five (5) days prior written notice to Consultant of City's intent to terminate. If this
Agreement is terminated by City, an adjustment to Consultant's compensation shall be
made, but (t) no amount shall be allowed for anticipated profit or unperformed Services,
and (2) any payment due Consultant at the time of termination may be adjusted to the
extent of any additional costs to City occasioned by any default by Consultant. 'Upon
receipt of a termination notice, Consultant shall immediately discontinue its provision of
the Services and, within five (5) days of the date of the termination notice, deliver or
otherwise make available to City, copies (in both hard copy and electronic form, where
applicable) of project related data, design calculations, drawings, specifications, reports,
estimates, summaries and such other information and materials as may have been
accumulated by Consultant in performing the Services. Consultant shall be compensated
on a pro-rata basis for Services completed up to the date of termination.
8.5 Consultant shall maintain books, ledgers, invoices, accounts and other records and
documents evidencing costs and expenses related to the Services for a period of three (3)
years, or for any longer period required by law, from the date of final payment to
Consultant pursuant to this Agreement. Such books shall be available at reasonable times
for examination by City at the office of Consultant.
8.6 This Agreement, including the Exhibits incorporated herein by reference, represents the
entire agreement and understanding between the Parties as to the matters contained
herein, and any prior negotiations, written proposals or verbal agreements relating to such
matters are superseded by this Agreement. Except as otherwise provided for herein, ally
amendment to this Agreement shall be in writing, approved by City and signed by City
and Consultant.
8.7 This Agreement shall be governed by and construed in accordance with the laws of the
State of California, without regard to its conflicts of laws provisions. The Parties agree
that all actions or proceedings arising in connection with this Agreement shall be tried
and litigated only in the state courts located in San Bernardino County, California, and
the federal courts located in Riverside County, California.
8.8 if one or more of the sentences, clauses, paragraphs or sections contained in this
Agreement is declared invalid, void or unenforceable by a court of competent
5
1:\cmo\Agreements\Rincon Professional Services Agreement.bm,08.19.2026.PY2728-29.dno
jurisdiction, the same shall be deemed severable from the remainder of this Agreement
and shall not affect, impair or invalidate the remaining sentences, clauses, paragraphs or
sections contained herein, unless to do so would deprive a Party of a material benefit of
its bargain under this Agreement.
IN WITNESS WHEREOF, duly authorized representatives of City and Consultant have
signed in confirmation of this Agreement.
CITY OF REDLAND
4A'
. B
Mario Saucedo, Mayor
ATTEST:
ie 1 Donaldson, City Clerk
RINCON CONSULTANTS, INC.
6
I:lcmo\AgreementslRincon Professional Services Agreement.bm.08.19.2026.FY2728-29.doe
EXHIBIT "A"
SCOPE OF SERVICES
The scope of work for implementing the selected remedial actions is described below.
Task 1 Pre -implementation Activities
The purpose of Task 1 is to prepare the work plans, health and safety documents, permitting
materials, and institutional control elements needed to support regulatory review and initiate
field implementation of the selected remedial actions.
Task 11 Implementation Work Plan
Consultant will prepare an Implementation Work Plan describing the planned scope of work for
each selected remedial action: cleaning and inspecting the Imhoff Tanks and AST, destroying the
dry groundwater monitoring wells, installing two additional groundwater monitoring wells, and
long-term monitoring of the groundwater at the site. The Implementation Work Plan will be
subject to review and approval by the Regional Board.
Attached to the Implementation Work Plan will be a HASP prepared for the remedial action
implementation activities described in the FS/RAP. This plan will describe the steps necessary
for the field crew to operate on site in a safe and healthy manner, including steps to minimize
exposure of the crew to potential contaminants. The preparation of such a plan is required by
Federal guidelines for site assessment work. The HASP will be prepared in accordance with
California Occupational Safety and Health Administration requirements (CCR Title 8 Section
5192) and contains safety provisions for routine response activities and unexpected emergencies.
The plan contains information on chemical and physical hazards, personal protective equipment,
decontamination procedures, personnel responsibilities, and emergency response protocols. The
HASP will be presented to all onsite personnel and signed prior to the commencement of work.
Task 1.2 Long-term Groundwater Sampling and Analysis Plan
Prior to initiation of the first semi-annual groundwater sampling event, Consultant will prepare a
sampling and analysis plan (SAP) that will include analytical and sampling requirements for
semi-annual groundwater monitoring as well as a detailed groundwater monitoring plan. The
SAP will be submitted to the Regional Board for review and approval prior to the first semi-
annual groundwater sampling event.
The SAP may be updated as needed based on the groundwater data collected, any significant
changes to the groundwater monitoring plan, or new or updated analytical methods.
Task 1.3 Soil Management Plan
Consultant will prepare a Soil Management Plan (SMP) to prescribe appropriate soil handling
and management activities to be conducted during future earth moving activities at the site in the
vicinity of the Septage Ponds, Imhoff Tanks, or AST. The purpose of the SMP is to provide
construction and/or other workers with guidance for the proper handling and management of
impacted soil, when or if encountered, during future earth moving activities. The SMP will be
subject to review and approval by the Regional Board.
7
1Acmo\Agreements\12incon Professional Services AgrecmcnLbm.08.19.2026FV2728-29.doe
Task 1.4 Land Use Covenant Support
Consultant will support the City in the preparation and implementation of a Land Use Covenant
(LUC) required by the RAP to ensure long-term protection of human health and the
environment. The LUC will establish institutional controls for the Septage Ponds and Imhoff
Tank areas where residual impacts will remain in place. Consultant's role will include assisting
the City by providing technical content, site data, and recommended restrictions for
incorporation into the LUC, as well as coordinating with the Regional Board and other
stakeholders, including the adjacent property owner, as necessary. The City, with its legal
counsel, will prepare, finalize, and record the LUC. The LUC is anticipated to include land -use
restrictions limiting development to non -sensitive uses, requirements for implementing an SMP
during any future earthwork (see Task 1.3), prohibitions on intrusive activities without prior
regulatory approval, and notification and reporting obligations for future property owners. Once
finalized, the LUC will be recorded on the property title and will remain in effect in perpetuity.
Task 2 Tank Cleaning, Inspections, and Reporting
The purpose of Task 2 is to clean and inspect the Imhoff Tanks and AST, to characterize residual
materials, and document conditions for Regional Board review as outlined in the FS/RAP.
Task 2.1 Pre -field Activities
Pre -field preparation activities will be conducted prior to the tank cleanings and inspections.
These activities will include coordination between Consultant, the licensed contractor conducting
the cleaning, and the City and preparation for the field activities.
Task2.2 hnhoff Tanks and ASTRemoval
As an alternative to Tasks 2.2 and 2.3, an excavator and breaker may be used to remove the two
concrete Imhoff Tanks. Under this scenario, the concrete would be sized using the breaker to
transport to a recycler. The concrete is assumed to be non -hazardous and free of staining. Upon
completion of the removal of the Imhoff tanks, the cavities would be backfilled with "clean"
import backfill material to the surface and the area will be rough graded. The backfill would be
placed in estimated 12-inch lift and compacted with a compaction wheel attached to the
excavator. The AST would be loaded on a flatbed truck with the excavator and transported to a
local recycling facility. Consultant assumes the AST does not contain any liquid.
Consultant would collect waste characterization samples of the sediment removed from the
Imhoff Tanks for disposal at an approved facility. Consultant assumes 4 samples of the sediment
removed from the Imhoff Tanks would be collected. Samples will be analyzed for Title 22
Metals by Environmental Protection Agency (EPA) Method 6010, TPH by EPA method 8015B,
and VOCs by EPA Method 8260B by a California certified laboratory via standard turnaround
time.
Task 2.3 Tank Cleaning and Inspection Memorandum
Following completion of the cleaning and inspection (or removal) of the Imhoff Tanks and AST,
a memorandum will be prepared that describes the activities conducted during the cleanings and
inspections (or removal) of the tanks. At a minimum the memorandum will include details about
the debris or material within the tanks, the cleaning (removal) methods used, the debris or
material removed from the tanks, the results of the visual inspections of the cleaned tanks, the
8
IAcmo\Agremnenls\Rincon Professional Services Agreementbm.08.19.2026.PY2728-29.doc
analytical results of the waste characterization samples, and waste manifests for the disposed
material. This report will be subject to review and approval by the Regional Board.
Task 3 Groundwater Monitoring Well Destruction
The purpose of Task 3 is to properly destroy seven dry groundwater monitoring wells at the site
in accordance with regulatory requirements as outlined in the FS/RAP.
Task 3.1 Pre -field Activities
Pre -field preparation activities will be conducted prior to groundwater monitoring well
destruction. These activities will include coordination between Consultant, the licensed
contractor conducting the destruction, and the City and preparation for the field activities as well
as the subtasks below.
Task 3.2 Well Locating
During site visits in 2018, some of the historical groundwater monitoring wells were located by
Consultant personnel; however, several wells were not located. Consultant will conduct a multi -
tiered approach to attempt to locate the groundwater monitoring wells. Consultant will review
state and local databases to determine approximate and relative locations of the groundwater
monitoring wells. Additionally, Consultant will review historical aerials and site maps.
Once the general vicinity of the wells is determined, Consultant will mobilize to the site with a
licensed contractor to deploy ground penetrating radar (GPR) in an attempt to locate the wells. In
addition, Consultant personnel will be equipped with a metal detector in an effort to locate steel
flush mount covers for the wells. It is anticipated that locating activities will be completed in one
day.
Consultant assumes that the general vicinity of each of the wells will be cleared of vegetation by
the City prior to conducting GPR activities.
Task3.3 Penuitting
Consultant will obtain the appropriate permit(s) from San Bernardino County Environmental
Health Services (EHS) to destroy the seven dry groundwater monitoring wells. This task includes
completing applications and associated paperwork, coordination with EHS, and applicable
permit fees.
Task3.4 USAMark-out
The dry groundwater monitoring well locations will be pre -marked with white flags and white
spray paint and notify Underground Service Alert (USA) utility marking service prior to
performing well destruction activities. California law requires this notification no less than 48
hours prior to drilling, not including the date of notification. In addition, the City will provide
any information they have regarding underground utilities in the project vicinity.
Task 3.5 Monitoring Well Destruction
Well destruction of the groundwater monitoring wells will be performed by a C-57 well driller
that is registered with San Bernardino Comity. The wells will be pressure grouted with approved
material from the bottom of the wellbore to ground surface. The groundwater monitoring well
9
1:\emo\AgreemenlsU2incon Professional services Agreement.bm.08.19.2026.FY2728-29.doc
will be over drilled to a depth of approximately 20 feet below ground surface. The wellbore will
be sealed from approximately 20 feet below ground surface to the ground surface with
impervious material to prevent any surface water or contaminants from entering the well and
potentially reaching groundwater. It is anticipated that destruction of groundwater monitoring
wells will take up to three days.
Task 3.6 Monitoring Well Destruction Memorandum
Following completion of the destruction of the dry groundwater monitoring wells, a summary
memorandum will be prepared describing the completion of the groundwater monitoring well
destruction. At a minimum it will include the locations of each of the dry groundwater
monitoring wells and the general procedures for groundwater monitoring well destruction. This
memorandum will be subject to review and approval by the Regional Board.
Task 4 Groundwater Monitoring Well Installation
The purpose of Task 4 is to install and develop two new groundwater monitoring wells necessary
to support long-term groundwater monitoring as outlined in the FS/RAP.
Task 4.1 Pro -field Activities
Pre -field preparation activities will be conducted prior to groundwater monitoring well
destruction. These activities will include coordination between Consultant, the licensed
contractor performing the installation, and the City and preparation for the field activities as well
as the subtasks below.
Task 4.2 Permitting
Consultant will obtain the appropriate pennit(s) from San Berardino County MIS to install two
groundwater monitoring wells. This task includes completing applications and associated
paperwork, coordination with EHS, and applicable permit fees.
Task4.3 USA Mart -out
The two groundwater monitoring well locations will be pre -marked with white flags and white
spray paint and we will notify USA utility marking service prior to performing well installation
activities. California law requires this notification no less than 48 hours prior to drilling, not
including the date of notification. In addition, the City will provide any information they have
regarding underground utilities in the project vicinity. Consultant assumes that prior to mark -out
activities, the City will conduct clearing and grading activities, as needed, so that drilling
equipment may access the groundwater monitoring well locations.
Task 4.4 Monitoring Well Drilling and Development
The two groundwater monitoring wells will be installed using an 8-inch diameter hollow -stein
auger to a target total depth of 250 feet bgs where a screen will be placed from approximately
220 to 250 feet bgs. It is anticipated that installation of each well will take up to 7.5 days to
complete.
A 4-inch diameter Schedule 80 PVC well will be installed in each borehole; the bottom 30 foot
well screen will be slotted Schedule 80 PVC pipe, with 0.010-inch slots, and solid Schedule 80
10
1:\cmo\Agreements\Rincon Professional Services Agreement.bm.08.19.2026.FY2728-29.doc
PVC pipe (riser) will be placed from the top of the well screen to land surface. The annulus
between the groundwater monitoring well and the borehole will be backfilled with Monterey No.
2/12 sand from the total borehole depth, to 5 feet above the top of the well screen. A 3-foot thick
(minimum) hydrated bentonite seal will be installed above the sand pack. Hydrated bentonite
groat will be installed from the top of the bentonite sea] of the filter pack to 2 feet bgs. Concrete
will be placed from 0 to 2 feet bgs. A traffic -rated vault as well as a riser and pad (given the
terrain) will be installed around the groundwater monitoring well. A locking cap will be placed
on top of the PVC riser at grade and a bottom PVC cap will either be screwed on or secured with
stainless steel screws for each groundwater monitoring well.
Well development activities will be initiated at least 48 hours after groundwater monitoring well
installation. The monitoring wells will be developed by pumping, surging, and bailing until
sediments in the bottom of the groundwater monitoring well are removed, the extracted water
becomes clear, and all indicator parameters become stable (California Environmental Protection
Agency 1995). The groundwater monitoring wells will be developed until water quality
parameters (pH, temperature, conductivity, and turbidity) stabilize. Water quality field
parameters will be collected and recorded throughout the development process.
Task 4.5 Well Survey
The two newly installed groundwater monitoring wells and the one groundwater monitoring well
installed in 2022 will be surveyed by a State of California Licensed Land Surveyor. The
elevation and the latitude and longitude of the top of well casing will be surveyed for each
groundwater monitoring well.
Task 4.6 Investigation Derived Waste
Investigative derived waste (IDW) will be generated from purged groundwater into 55-gallon
drums. Consultant will collect two IDW-water samples from groundwater purged from the two
newly installed wells. The samples will be submitted to a laboratory and will be analyzed for
VOCs by EPA Method 8260B, TPH by EPA Method 8015, and Title 22 Metals by EPA Method
6010/7417 for waste disposal purposes. Consultant will contract with a waste hauler to pick up
and transport the drums to a waste facility.
Task 4.7 Well Installation Memorandum
Upon completion of the installation of the groundwater monitoring wells, Consultant will
prepare a completion memorandum detailing, at a minimum, the well construction details and
well development procedures. This memorandum will be subject to review and approval by the
Regional Board.
Tasks Remedial Action Implementation Reporting
A Remedial Action Implementation Report will be prepared to describe the activities conducted
as described in Tasks 1 through 4. The Report will reference the memoranda and Regional Board
approval letters for each memorandum.
11
I:\cmo\AgreemcnlsUiincon Professional Services Agreement.bra 08.19.2026,PY2728-29.doc
Task 6 Long-term Groundwater Monitoring
The purpose of Task 6 is to conduct semi-annual groundwater sampling and reporting to evaluate
potential contaminant migration and ensure long-term protectiveness of the approved remedial
actions.
Task 6.1 Year 1. Groundwater Monitoring
Consultant assumes that Year 1 groundwater monitoring will be conducted in 2027 and consist
of:
• Completing pre -field preparation activities including coordination between Consultant,
subcontractors, and the City.
• Installing a dedicated pump equipped with high density tubing in each of the groundwater
wells to be sampled and monitored long term (total of 3 pumps).
• Performing one 3-year groundwater monitoring event with the analyte list shown in Table 1.
One groundwater sample will be collected from each monitoring well (total of 3 samples). One
duplicate sample will be collected and one equipment blank sample will be collected during
each sampling event.
• Performing one semi-annual groundwater monitoring event with the analyte list shown in
Table 2. One groundwater sample will be collected from each monitoring well (total of 3
samples). One duplicate sample will be collected and one equipment blank sample will be
collected during each sampling event.
• During each groundwater monitoring event, field parameters including pH, specific
conductance, dissolved oxygen, and temperature will be monitored prior to collecting
groundwater samples. Groundwater samples will be stored in a cooler chilled to 4 degrees
Celsius and will be couriered to a State -certified analytical laboratory using chain -of -custody
protocol. Consultant assumes the City will contract directly with the analytical laboratory.
Analytical laboratory costs are not included in this proposal.
• Preparing and submitting an annual report for review and approval by the Regional 'Board.
Groundwater monitoring activities and analytical results will be reported to the City and the
Regional 'Board in a letter report. The letter report will include groundwater levels, calculated
groundwater gradient, analytical results, and any other pertinent observations as well as a status
update of ongoing remediation activities.
• Disposing of purged groundwater after the second monitoring event of the year. IDW will be
generated ftom purged groundwater into 55-gallon drums. Consultant will collect one IDW-
water sample ftom the drums each year. The samples will be submitted to a laboratory and will
be analyzed for VOCs by EPA Method 8260B, TPH by EPA Method 8015, and Title 22
Metals by EPA Method 6010/7417 for waste disposal purposes. Consultant will contract with a
waste hauler to pick up and transport the drums to a waste facility after the second monitoring
event of the year.
Table 1. Analyte List for 3-year Groundwater Monitoring Events
12
I:\cmo\Agreements\Rineon Professional services Agreemenlbm.08.19.2026.PY2728-29.doe
Lead
PFOA/PFOS
Semi-annual
Semi-annual
EPA Method 6010B
EPA Method 1633
PFAS — Full List
Every 3 Yeats
EPA Method 1633
Total Cations
Total Anions
Every 3 Years
Every 3 Years
EPA Method 1
EPA Method 1
Hydroxide (OH)
Every 3 Years
EPA Method 2
Specific Conductance
(Electrical Conductivity)
Every 3 Years
EPA Method 120.1
Total Hardness
Every 3 Years
EPA Method 130
pH
Every 3 Years
EPA Method 150.1
Total Dissolved Solids
Every 3 Years
EPA Method 160.1
Iron (Fe)
Manganese (Mn)
Every 3 Years
Every 3 Years
EPA Method 200.7 / 236.1.
EPA Method 200.7 / 243.1
Zinc (Zn)
Every 3 Years
EPA Method 200.7 / 289.1
Boron (B)
Carbonate CaCO3
Every 3 Years
Every 3 Years
EPA Method 212.3 / 200.7
EPA Method 310.2
Bicarbonate (HCO3)
Every 3 Years
EPA Method 310.2
Total Alkalinity
Every 3 Years
EPA Method 310.1
Chloride (Cl)
Every 3 Years
EPA Method 325
Fluoride (F)
Every 3 Years
EPA Method 340
Nitrate (NO3)
Every 3 Years
EPA Method 353.2
Phosphate (PO4)
Every 3 Years
EPA Method 365.2
Total Phosphorus
Every 3 Years
EPA Method 365.1/365.2
Sulfate (SO4)
Every 3 Years
EPA Method 375
Chemical Oxygen Demand
Every 3 Years
EPA Method 410
Total Organic Carbon
Phenols
Every 3 Years
Every 3 Years
EPA Method 415
CPA Method 420.1
Total Organic Halogens
Every 3 Years
EPA Method 450.1
Volatile Organic Compounds
(VOCs)
Every 3 Years
EPA Method 8260B
Total Petroleum Hydrocarbons
(TPH) — Gas, 'Diesel, and
Motor Oil Range
Every 3 Yeas
EPA Method 8015M
Notes:
13
1:\cmo\Agrcc nentsTjncon Professional Services Agreement.bm.08.19.2026.FY2728-22doc
Sampling and Analysis Plan (see Task 1.2)
EPA - United States Environmental Protection Agency
PEAS - per- and polyfluoroalkyl substances
PFOA - perfluorooctanoic acid
PFOS - perfluorooctanesulfonie acid
Table 2. Analyte List for Semi-annual Groundwater Events
Lead Semi-annual EPA Method 6010E
PFOA/PFOS Semi-annual EPA Method 1633
Notes:
Methods for groundwater analysis will be finalized in the Long-term Groundwater Sampling and Analysis
Plan (see Task 1.2)
EPA - United States Environmental Protection Agency
PFOA - perfluorooctanoic acid
PFOS - perfluorooctanesulfonic acid
Task 6.2 Training for Groundwater Monitoring
Consultant will conduct training with City staff to take over responsibility for groundwater
monitoring beyond the first year of groundwater monitoring activities (i.e., training to occur
during year 1 monitoring activities). Consultant will train during two sampling events, which
will include coordination with the analytical laboratory, preparation of sampling equipment and
bottleware, collection of samples, and submittal of samples to the analytical laboratory.
Consultant assumes the City will contract directly with the analytical laboratory and manage
IDW during these training events. Costs associated with IDW and analytical laboratory costs are
not included in this proposal.
Task 7 Contingency
Due to the potential unknowns (e.g., well locations, well construction information) and
challenges installing prior wells at the site and in the local region, Consultant has included a 10-
percent contingency budget to account for potential budget overruns. Consultant will not expend
this budget without prior written approval from the City.
General Assumptions
Costs for written documents (Tasks 1.1, 1.2, 1.3, 2.4, 3.5, 4.7, 5, and 6.1) include responding
to one round of comments from the City, and one round of comments from the Regional
Board.
• Consultant is not responsible for any damages to underground improvements not clearly or
accurately marked by the City. Consultant will contact DigAlert for utility mark -outs;
14
L emo\AgreementA incon Professional Sorvices Agreemenl.bm.08. 19.2026.FY2728-29.doe
however, it should be noted that DigAlert often does not mark the location of subsurface
utilities located on private property. If Consultant damages any subsurface utility or structure
that is not identified by the City, then the City will assume the cost and all liability related to
repair and injury that may occur as a result of such an occurrence.
• The subsurface is amenable to well installation using the methods described in this proposal
and the sampling can be completed in the specified time frame. Consultant will advise the
City of any necessary revisions to the work scope as well as additional costs, if required.
• Laboratory analytical costs included in this proposal assume a standard turnaround time.
• An annual escalation of 3.5% was applied to costs projected in 2027, 2028, and 2029.
15
1:\cmo\Agremnents\Rincon Professional Services Agreemont.bm.08.19.2026.PY2728-29.doc
EXHIBIT 'B"
PROJECT SCHEDULE
Pre -implementation Activities
6 months after approval of FS/RAP
Second half of 2026
Long-term Groundwater Sampling and
6 months after approval of FS/RAP
Second half of 2026
Analysis Plan
Soil Management Plan
6 months after approval of FS/RAP
Second half of 2026
Imhoff Tank Cleaning, Inspections,
6 months after approval of FS/RAP
Second half of 2026
and Reporting
Aboveground Storage Tank Cleaning,
6 months after approval of FS/RAP
Second half of 2026
Inspections, and Reporting
Groundwater Monitoring Well
6 months after approval of FS/RAP
Second half of 2026
Destruction
Groundwater Monitoring Well
1 year after approval of FS/RAP
Second half 2027
Installation
Annual Groundwater Monitoring and
Once every year after the installation of
First half of 2028, 2029,
Reporting
the groundwater monitoring wells
and 2030
Remedial Action Implementation
6 months after completion of all
First half of 2028
Report
remedial action alternatives
Land Use Covenant
1 year after groundwater monitoring
Second half 2028
well installation
* Schedule is subject to change due to permitting, site conditions, and coordination needs; therefore, an
agreement term of 3 years is proposed.
16
1:\cmo\Agreemcntsl2incon Professional Services Agreement. m.09.19.2026.PY272R-29.doe
EXHIBIT "C"
FEESCHEDULE
Task 1 Pre -implementation Activities
$35,800
Taslc 1.1 Implementation Work Plan
$10,000
Task 1.2 Long-term Groundwater Sampling and Analysis Plan
$8,000
Task 1.3 Soil Management Plan
$8,000
Task 1.4 Land Use Covenant Support
$9,800
Task2 Tank Cleaning, Inspections, and Reporting
$141,300
Task2.1 Pre -field Activities
$2,400
Task 2.2 Imhoff Tanks and AST Removal
$134,900
Task 2.3 Tank Cleaning and Inspection Memorandum
$4,000
Task 3 Groundwater Monitoring Well Destruction
$60,700
Task 3.1 Pre -field Activities
Task 3.2 Well Locating
$3,300
$7,300
Task 3.3 Permitting
$9,000
Task 3.4 USA Mark -out
Task 3.5 Monitoring Well Destruction
Task 3.6 Monitoring Well Destruction Memorandum
$3,700
$33,400
$4,000
Task 4 Groundwater Monitoring Well Installation
$340,600
Task 4.1 Pre -field Activities
$3,300
Task 4.2 Permitting
$4,800
Task 4.3 USA Mark -out
$3,700
Task 4.4 Monitoring Well Drilling and Installation
$302,300
Tasl<4.5 Well Survey
$7,300
Task 4.6Investigation Derived Waste
Task 4.7 Monitoring Well Memorandum
Task 5 Remedial Action Implementation Reporting
$16,200
$4,000
$7,500
Task 6 Long-term Groundwater Monitoring (First 3 Years)
$54,100
Task 6.1 Year 1 Groundwater Monitoring
Task 6.2 Groundwater Monitoring Training
6 Total
$42,700
$11,400
$640,000
17
1:\cmo\Agreements\Rinwn Professional Services Agreement.bm.08.19.2026.PY2728-29.doc
EXHIBIT "D"
WORKERS' COMPENSATION INSURANCE CERTIFICATION
Every employer, except the State, shall secure the payment of compensation in one or more of
the following ways:
(a) By being insured against liability to pay compensation by one or more insurers
duly authorized to write compensation insurance in this State.
(b) By securing from the Director of Industrial Relations, a certificate of consent to
self -insure, either as an individual employer, or as one employer in a group of
employers, which may be given upon furnishing proof satisfactory to the Director
of Industrial Relations of ability to self -insure and to pay any compensation that
may become due to his or her employees.
CHECK ONE
XI am aware of the provisions of Section 3700 of the Labor Code which requires every
employer to be insured against liability for Workers' Compensation or to undertake self-
insurance in accordance with the provisions of that Code, and I will comply with such provisions
before commencing the performance of the work and activities required or permitted under this
Agreement. (Labor Code §1861).
I affirm that at all times, in performing the work and activities required or permitted wider
this Agreement, I shall not employ any person in any manner such that I become subject to the
workers' compensation laws of California. However, at any time, if I employ any person such
that I become subject to the workers' compensation laws of California, immediately 1 shall
provide the City with a certificate of consent to self -insure, or a certification of workers'
compensation insurance.
I certify under penalty of perjury under the laws of the State of California that the information
and representations made in this certificate are true and correct.