HomeMy WebLinkAboutContracts & Agreements_31-2016 CONTRACT
MEMORANDUM OF UNDERSTANDING
BETWEEN THE
SAN BERNARDINO TRANSPORTATION AUTHORITY
AND THE CITY OF REDLANDS
FOR THE DEVELOPMENT OF
THE INTERSTATE 10/ALABAMA STREET INTERCHANGE PROJECT
I. PARTIES AND TERM
A. This Memorandum of Understanding ("MOU") is entered by and between the
SAN BERNARDINO TRANSPORTATION AUTHORITY ("SANBAG") and the CITY OF
REDLANDS ("PROJECT SPONSOR") (together, the "PARTIES") on the Effective Date
defined later herein.
B. The Term of this MOU will commence on the Effective Date and, unless earlier terminated as
provided in Section V, Paragraph D of this MOU, terminate upon the date a notice of
completion is recorded for the Interstate 10 at Alabama Street Interchange Project
("PROJECT") or September 30, 2021, whichever is earlier.
II. RECITALS
A. WHEREAS, the PROJECT is included in the approved SANBAG 10-Year Delivery Plan and
SANBAG Development Mitigation Nexus Study and is eligible to receive funds from the
Measure 12010-2040 Valley Freeway Interchange Program,
B. WHEREAS, the PARTIES desire to proceed with development of the PROJECT.
C. WHEREAS, the PARTIES are entering into this MOU for the purpose of documenting the
terms and conditions of cooperation between the PARTIES required to complete the PROJECT
with respect to cost, funding, schedule, and scope, as detailed in Exhibit A, attached hereto and
incorporated herein by this reference.
D. WHEREAS, a conceptual layout of the PROJECT is shown in Exhibit B, attached hereto and
incorporated herein by this reference.
E. WHEREAS, the PARTIES acknowledge the intent to move forward with the PROJECT, the
Public and Local Agency funding shares required to complete the PROJECT, and the
reasonable expectation of their availability.
F. WHEREAS, the Public Share is defined as the percentage share of PROJECT cost calculated as
the total cost of the PROJECT minus the development share (or Local Agency share), and the
Local Agency share is defined as the percentage share of the PROJECT cost assigned as the
development contribution percentage as listed in the SANBAG Development Mitigation Nexus
Study.
G. WHEREAS, the PARTIES understand that the purpose of this MOU is to outline the steps and
funds necessary to complete the PROJECT, but this MOU does not commit the PARTIES to
perform work or provide funding for the PROJECT, and imposes no enforceable obligations
upon the PARTIES and does not grant any rights.
H. WHEREAS, the PARTIES desire to memorialize in this MOU the framework and funding
necessary for completion of the PROJECT to assist the Parties in their decision-making and
budgeting for the PROJECT.
I. WHEREAS, the PARTIES understand that a cooperative agreement will be developed for each
phase of the PROJECT that will identify the specific roles and responsibilities of SANBAG and
PROJECT SPONSOR including specific funding commitments.
IIL SANBAG'S RESPONSIBILITIES
A. SANBAG will be responsible for the Public Share of PROJECT costs in accordance with
Measure 12010-2040 Valley Freeway Interchange Program Strategic Plan Policy 40005 (Policy
40005) and subsequent cooperative agreements.
B. SANBAG will consider the development of a Loan Agreement(s) for the Local Share of
PROJECT costs, if requested by the PROJECT SPONSOR, in accordance with Policy 40005.
C. SANBAG will assign a qualified member of its staff to coordinate with the PROJECT
SPONSOR, as determined reasonably necessary by SANBAG to facilitate delivery of the
PROJECT.
D. PROJECT SPONSOR and SANBAG shall consult on a funding strategy for PROJECT
completion at least six months prior to completion of the design phase.
IV. PROJECT SPONSOR'S RESPONSIBILITIES
A. PROJECT SPONSOR will be responsible for the Local Share of the PROJECT costs in
accordance with Policy 40005 and subsequent agreements, including loan agreements.
B. PROJECT SPONSOR will assign a qualified member of its staff to coordinate with SANBAG,
as determined reasonably necessary by PROJECT SPONSOR to facilitate delivery of the
PROJECT.
C. PROJECT SPONSOR acknowledges that in accordance with Policy 40005--VFI-2, PROJECT
SPONSOR is responsible for nominating the PROJECT. If freeway interchange project
nominations by SANBAG sponsoring member agencies exceed the available funding,
SANBAG shall allocate funds to sponsors of the nominated projects in order of project priority
as assigned in the Strategic Plan. Failure to provide its Local Share of funding in a timely
manner could jeopardize the schedule and/or delivery of the PROJECT and could put other
projects lower on SANBAG's Measure I interchange priority list in a position to utilize the
A-1
available public share which have the local share available. Lower ranked projects could take
precedence in Measure I funding for a period of time until additional funding is available for the
PROJECT SPONSOR to meet its Local Share requirement for its PROJECT, pursuant to
Strategic Plan Policy VFI-21. SANBAG will provide a written notice to PROJECT SPONSOR
if PROJECT is in jeopardy of losing its funding priority to another project, and PROJECT
SPONSOR will be provided 60 days to respond with a funding plan.
D. PROJECT SPONSOR and SANBAG shall consult on a funding strategy for PROJECT
completion at least six months prior to completion of the design phase.
V. MISCELLANEOUS
A. The PARTIES will act in good faith to see the construction of the PROJECT is completed.
B. The PARTIES acknowledge that should federal funds be used in the environmental or design
phases of work, Federal Highway Administration (FHWA) requires that the PROJECT must
move to a capital phase (right of way or construction) within ten years or the federal funds may
be required to be repaid to FHWA. Responsibilities related to the federal funding will be
outlined in the funding cooperative agreement(s).
C. Recitals. The Recitals stated above are integral parts of this MOU and are hereby incorporated
into the terms of this MOU.
D. Termination. Both SANBAG and PROJECT SPONSOR shall have the right at any time, to
terminate this MOU, by giving thirty (30) calendar days prior written notice to the other Party,
specifying the date of termination. Termination of the MOU will not terminate the PARTIES'
continuing obligations under any cooperative agreements generally referenced in Section 11,
Paragraph 1. Termination of this MOU by request of PROJECT SPONSOR will be understood
by SANBAG that PROJECT SPONSOR wishes to discontinue work on the PROJECT, unless
otherwise stated in an active cooperative agreement or in a subsequent MOU or agreement.
E. Notification. Each Party will designate a person to be responsible for day-to-day
communications regarding work under the PROJECT. For PROJECT SPONSOR, that person
will be Chris Diggs, Municipal Utilities and Engineering Department Director for the CITY OF
REDLANDS. For SANBAG, that person shall be Paula Beauchamp. All notices and
communications regarding this MOU, interpretation of the terms of this MOU, or changes
thereto will be provided as follows:
CITY OF REDLANDS SANBAG
35 Cajon Street, Ste. 15A San Bernardino Associated
Redlands, CA 92373 Governments
ATTN: Chris Diggs, Municipal 1170 W. 3rd Street
Utilities and Engineering Director San Bernardino, CA 92110-1715
CC: Ross Wittman ATTN: Executive Director
CC: Andrea Zureick
F. Amendment. In the event that the PARTIES determine that the provisions of this MOU should
be altered, the PARTIES may execute an amendment to add, delete, or amend any provision of
this MOU. All such amendments must be in the form of a written instrument signed by the
original signatories of this MOU, or their successors or designees.
A-2
In witness whereof the PARTIES have executed this MOO on the dates written below and this MOO is
effective upon execution of this MOO by SANBAG ("Effective Date"),
SA BAG CITY OF RETS LA
Ryan McEachron Paul W. Foster, Mayor
Board President ATTEST:
Sam Irwin, ity Clerk
Date: Date:
APPROVED AS TO FORM: APPROVED AS TO FORM:
By: By:
Eileen Monaghan Teichert Daniel J. McIA0
General Counsel City Attorney
CONCURRENCE:
By:
Jeffery Hill
Contract Administrator
A-3
Exhibit A
Project Scope:
The PROJECT will improve the Alabama Street at I-10, including intersection work, turning lanes, and striping.
It is anticipated that SANBAG will be lead on all phases of work.
Project Cost Estimate* and Funding Shares:
Public Share: 49.50%
Nexus Development Impact Fee Share (DIF, "Development Share" or"Local Share"): 50.50%
Local Jurisdictional Split of the DIF Share: Redlands 34.90%, County of San Bernardino 65.10%a
Estimated Cost Public Share Development Share
Phase (Escalated at (49.5%) (50.5%)
3.5%/year to 612019)
Project Study Report $ 347,000 $ 171,765 $ 175,235
Project Approval &Environmental
Document $ 922,000 $ 456,390 $ 465,610
Design $ 462,000 $ 228,690 $ 233,310
Right-of-Way (including Utilities) $ 36,000 $ 17,820 $ 18,180
Construction(including Construction
Management) $ 8,122,000 $ 4,020,390 $ 4,101,610
Landscape(Extended Maintenance) $ 749,000 $ 370,755 $ 378,245
SANBAG Oversight $ 330,000 $ 163,350 $ 166,650
Total $ 10,968,000 $ 5,429,160 $ 5,538,840
* Project estimate is based on conceptual level layouts as PSR has not been completed. Construction Phase cost
includes approximately $90,000 for landscaping.
Project Milestones:
Milestone Actual
(Forecast)
Start of Project January 2016
PSR Approval December 2016
Environmental Approval December 2017
Design Approved/ROW Certified December 2018
Construction Notice to Proceed" June 2019
Completed for Beneficial Use June 2020
A-4
x
M f w
r �
Z
1 - 1Lq
L4
its
# J �
r f a
r
u, ( ry
!
f �
d ry .....:y
io
41
P r
^�f
r
i
r
til
a '
i
I �
I
� f
��✓ a wh, !�jr/f�f/i'I `/� J �f�� r �vGl �e 4 � r'� 1�%%�
r '
i
r
iG 6,
;
1,
I _ o
l t
o
F'
e
� w �i�•` 'U � � f r�tiJ �i t. �
dw
�1
i
lllf %� 1
r,